Tanjung Bin power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Tanjung Bin power station is an operating power station of at least 3100-megawatts (MW) in Tanjung Bin, Serkat, Pontian, Johor, Malaysia.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Tanjung Bin power station Tanjung Bin, Serkat, Pontian, Johor, Malaysia 1.334, 103.5422 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2, Unit 3, Unit 4: 1.334, 103.5422

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 1 operating coal - bituminous 700 subcritical 2006 2031 (planned)
Unit 2 operating coal - bituminous 700 subcritical 2007 2031 (planned)
Unit 3 operating coal - bituminous 700 subcritical 2007 2031 (planned)
Unit 4 operating coal - bituminous 1000 ultra-supercritical 2016

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 Malakoff Corporation Bhd [100.0%]
Unit 2 Malakoff Corporation Bhd [100.0%]
Unit 3 Malakoff Corporation Bhd [100.0%]
Unit 4 Malakoff Corporation Bhd [100.0%]

Project-level coal details

  • Coal source(s): imported

Background

The Tanjung Bin power station originally consisted of three 700 MW coal-fired subcritical units that went into operation in 2006 and 2007.[1][2] As of April 2016, coal for fueling the plant was imported via an attached coal port.[3] 

In July 2023, as a component of Malaysia's National Energy Transition Roadmap, a biomass co-firing pilot was announced at Tanjung Bin power station. The program was to begin in 2024 and reach 15% pellets, wood chips, and husk by 2027.[4]

Planned retirement

In March 2021, Malaysia's Suruhanjaya Tenega (Energy Commission) released a generation development plan covering 2021-39. Additional background is available at the Unnamed Malaysia coal projects wiki. The plan forecasted retiring the original Tanjung Bin power station units by 2031 (2,100 MW).[5][6][7]

Expansion (T4)

Construction on the 1,000 MW coal plant expansion, also known as T4, began in 2012.[8] Completion was planned for March 2016, but has been delayed by at least six months, according to sponsor Malakoff in 2014.[9]

In March 2015, Tanjung Bin Energy Sdn Bhd denied reports that the Tanjung Bin Energy Power Plant (T4) project had been delayed six months, and said the plant would commence commercial operations on March 1, 2016 as scheduled.[10]

On March 21, 2016, the new 1,000 MW unit achieved commercial operation. It had been synchronized on October 15, 2015[11] and used ultra-supercritical combustion technnology.[12]

The new unit 4 is located on a 65ha site adjacent to the older units, and shares common infrastructure such as coal-handing facilities, power evacuation, sea-water intake and other access facilities.[11]

In January 2022, Malakoff appointed international energy technology and solution provider RJM International to conduct an audit and help improve the plant's performance.[13]

New jetty

Construction of the Tanjung Bin New Coal Unloading Jetty (NCUJ), a part of the power plant, began in 2017.[2]

In March 2022, arbitration was settled between Tanjung Bin Energy (TBE) and the contractors hired to construct the unloading jetty and bulk handling system at the Tanjung Bin power plant. TBE alleged in March 2020 that contractors had failed to complete all work stated in the contract.[14]

Financing

In March 2012, a financing agreement for unit 4 was closed. US$2,132.06 million in loans was provided by Sumitomo Mitsui Banking Corporation, Mizuho Financial Group, HSBC, MUFG Bank, OCBC Bank, and RHB Bank. HSBC acted as financial adviser.[15]

Contractor

Tanjung Bin is Alstom's second contract for an ultra-supercritical coal plant in Malaysia, following in the heels in Manjung power station Unit 4.[16] Alstom's boilers are built by Wuhan Boiler Company, located in Wuhan China and owned 51% by Alstom.[17]

Articles and Resources

References

  1. "Coal-Fired Power Plants in Malaysia," Industcards, accessed January 2014
  2. 2.0 2.1 "Tanjung Bin Energy Power Plant, Johor," Power Technology, accessed November 2021
  3. "Tanjung Bin Coal Power Plant Malaysia," GEO, accessed April 2016
  4. "Malaysia: National Energy Transition Roadmap Part 1 – Flagship catalyst projects and initiatives," Baker McKenzie, August 4, 2023
  5. Report on Peninsular Malaysia Generation Development Plan 2019 (2020 – 2030), Suruhanjaya Tenega, February 2020
  6. Report on Peninsular Malaysia Generation Development Plan 2020 (2021 – 2039), Suruhanjaya Tenega, March 2021
  7. Malaysia to reduce coal capacity by 4.2GW by 2039, Argus Media, March 24, 2021
  8. "Malakoff’s Tanjung Bin Expansion on Track for a 3,100MW Final Capacity," Power Insider, August 14, 2012
  9. "Tanjung Bin power plant delay a setback to Malakoff’s listing," The Star, September 9, 2014
  10. "Malakoff power plant on track for 2016 start," Borneo Post, March 27, 2015
  11. 11.0 11.1 "Malakoff’s Tanjung Bin Energy Power Plant achieves COD," The Sun Daily, 22 March 2016
  12. "Tanjung Bin, Malaysia: Ultra-supercritical coal-fired power plant," Alstom, July 20, 2015
  13. "Malakoff Appoints RJM To Improve Performance Of Its Tanjung Bin 4 Power Plant," Business Today, January 13, 2022
  14. "Malakoff, contractors settle Tanjung Bin power plant work completion disputes," The Edge Markets, March 28, 2022
  15. "Preview of Tanjung Bin Power Plant Financing (1000MW) | Transaction | IJGlobal". ijglobal.com. Retrieved 2020-11-23.
  16. "Tanjung Bin, Malaysia Two-pass boiler," Alstom, 2015
  17. "Manjung 4: An ultra-supercritical first in Southeast Asia," Alstom, accessed September 2015

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.