| Part of the Global Gas Infrastructure Tracker, a Global Energy Monitor project. |
Penco Lirquén FSRU, also known as Octopus LNG Terminal and FSRU Penco Lirquén, is a proposed LNG import terminal in Chile.
Location
Table 1: Location details
| Name | Location | Coordinates (WGS 84) |
|---|---|---|
| Penco Lirquén FSRU | Concepción Bay, Bulnes, Biobío region (VIII), Chile[1] | -36.683333, -73.033333 (approximate) |
The map below shows the approximate location of the terminal:
Project Details
Table 2: Infrastructure details
| Name | Facility type | Status | Capacity | Total terminal capacity | Offshore | Associated infrastructure |
|---|---|---|---|---|---|---|
| Penco Lirquén FSRU | import[2][3] | proposed[4][5] | 2.7 mtpa[6] | 2.7 mtpa | True | El Campesino power station[7] |
Table 3: Cost
| Name | Facility type | Cost | Total known terminal costs |
|---|---|---|---|
| Penco Lirquén FSRU | import[2][3] | – | – |
Financing
No financing data available.
Table 4: Project timeline
| Name | Facility type | Status | Proposal year | FID year | Construction year | Operating year | Inactive year |
|---|---|---|---|---|---|---|---|
| Penco Lirquén FSRU | import[2][3] | proposed[4][5] | 2014[1][2][8] | – | – | –[9][4][6][9][4][6] | –[10] |
Ownership
Table 5: Ownership
| Name | Facility type | Status | Owners | Parent companies | Operator |
|---|---|---|---|---|---|
| Penco Lirquén FSRU | import[2][3] | proposed[4][5] | Biobiogenera [50%]; Cheniere Energy Inc [50%][1][2][1][2] | Biobiogenera [50.0%]; Cheniere Energy Inc [50.0%] | – |
Table 6: Vessel ownership
| Name | Facility type | Status | Vessel owners | Vessel operator |
|---|---|---|---|---|
| Penco Lirquén FSRU | import[2][3] | proposed[4][5] | Höegh Evi[3] | Höegh Evi[3] |
Background
Formerly known as the Octopus LNG project, Penco Lirquén was to comprise a floating storage regasification unit (FSRU) in Concepción Bay. The LNG project was expected to have capacity of 0.39 bcfd and send gas to the onshore network via a 2.5km submarine pipeline.[11]
The Penco-Lirquén LNG import terminal was proposed as a joint venture of Biobiogenera (50%) and Cheniere Energy (50%)[12][13] to provide LNG to the proposed El Campesino power station, which was to be developed as a joint venture between Biobiogenera and Electricite de France (EDF).[14]
In May 2015, Norway’s Höegh LNG signed a 20 year contract with Penco-Lirquén's predecessor, Octopus LNG, to provide the FSRU (floating storage and regasification unit) for the LNG import project. As of May 2017, the project had been delayed 12-18 months due to environmental concerns.[15]
After six years of delays, including the revocation of the project's original environmental license by Chile's Supreme Court for failure to properly consult with indigenous groups[16], the terminal was unanimously approved by the Regional Commission for Environmental Assessment in August 2019.[17]
However, as of February 2020, construction plans remained suspended due to new legal challenges stemming from the project developers' inadequate consideration of citizen input during the environmental assessment process, including failure to consult with the Koñintu Lafken Mapu and Peumellén indigenous communities.[18][19][20] As of May 2021, opponents of the project were reportedly preparing to present their grievances before the Committee of Environmental Ministers, with plans to take their case to Valdivia's Environmental Court if necessary.[21]
As of June 2022, the Penco Lirquén LNG terminal and the El Campesino power station both appeared to be shelved, as the owners had provided no further news about either project in more than two years, and 2021 news reports indicated that a different gas and solar power project had been proposed for the same site.[22]
Environmental approval of the project in October 2023
In October 2023, nine years after the project was first proposed, Chile's Committee of Ministers gave unanimous environmental approval for the Penco Lirquén LNG terminal to move forward.[23][24] The mayors of the neighboring communities of Talcahuano and Penco immediately announced plans to revive legal opposition to the project.[25] As of July 2024, forecasts called for the terminal to begin commercial operations in 2027.[26][27]
After the project's approval, however, "the company GM Energy did not confirm the execution of the project in the short term and stated that the company's current focus is on implementing renewable energy projects, mainly solar and storage, that support the country's goal of carbon neutrality by 2050."[28] The project's official website has been inactive since at least 2021.[29]
Financing
In December 2016 a group of ten international banks agreed to provide loans totalling US$850 million for the development of the Penco Lirquén LNG terminal and the 640MW El Campesino combined cycle gas turbine plant. The banks involved included DNB Nord, Societé Générale, Mitsubishi UFJ, Crédit Agricole, Sumitomo Mitsui Banking Corporation, BNP Paribas, KDB, Scotia, BCI and Siemens.[30][22]
Opposition
On June 28, 2016, the Evaluation Commission of the Biobio Region approved the LNG terminal project. Various parts of the province were subsequently blockaded by citizens protesting the project's approval on the grounds that proper environmental regulatory procedures had not been followed. In addition to the blockades, there was a strike among public sector workers who then demonstrated in the streets. According to reports, the demonstrations were met with police repression. In the neighborhood of Lord Cochrane and the Lirquén Hospital, demonstrators blockaded traffic in protest of the Penco-Lirquén terminal and its potential environmental impacts. Seven people were arrested.[31]
In February 2017, the LNG terminal project had its environmental approval revoked by the Chilean Supreme Court. The ruling was the result of a lawsuit brought forward by the Konintu Lafken Mapu Indigenous association. The court stated that the original permit granted by the regional environmental evaluation service acted illegally by prematurely terminating the project’s indigenous consultation phase.[32]
Civil society and environmental groups have continued to protest against the Penco-Lirquén project for a variety of reasons, including the terminal's perceived impact on air, soil and water quality, tourism, and the local fishing economy.[19]
In May 2025, the municipality of Penco formally joined the judicial process as a third‑party intervenor before the Tercer Tribunal Ambiental de Valdivia, aiming to revoke the project's approval. Among other factors, the municipality presented arguments claiming irreparable collective harm to the territory and public health, deficiencies in the environmental assessment, omissions in the indigenous consultation process, and threats to vulnerable species and ecosystems, including marine biodiversity and coastal wetlands.[33][34][35]
Articles and Resources
Additional data
To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.
References
- ↑ 1.0 1.1 1.2 1.3 https://tankterminals.com/news/chiles-third-lng-regas-terminal-in-the-works/.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 https://www.lngindustry.com/liquefaction/31072015/Cheniere-enters-LNG-SPA-with-Central-El-Campesino-1087/.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 3.2 3.3 3.4 3.5 3.6 https://www.lngindustry.com/liquid-natural-gas/03092012/Hoegh-LNG-awarded-contract-for-FSRU-in-Chile127/.
{{cite web}}: Missing or empty|title=(help) - ↑ 4.0 4.1 4.2 4.3 4.4 4.5 https://www.biobiochile.cl/noticias/nacional/region-del-bio-bio/2023/10/25/tras-9-anos-comite-de-ministros-aprueba-cuestionado-proyecto-terminal-maritimo-gnl-penco-lirquen.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 5.0 5.1 5.2 5.3 https://www.terram.cl/sorpresa-en-el-biobio-comite-de-ministros-aprobo-resistido-proyecto-gnl-penco-lirquen/.
{{cite web}}: Missing or empty|title=(help) - ↑ 6.0 6.1 6.2 https://www.igu.org/resources/2024-world-lng-report/.
{{cite web}}: Missing or empty|title=(help) - ↑ http://www.prnewswire.com/news-releases/cheniere-marketing-and-central-el-campesino-sign-20-year-lng-sale-and-purchase-agreement-300121610.html.
{{cite web}}: Missing or empty|title=(help) - ↑ https://hrudnick.sitios.ing.uc.cl/alumno13/precioGNL/Informe%20GNL%20mercados%20electricos%20(1).html.
{{cite web}}: Missing or empty|title=(help) - ↑ 9.0 9.1 https://naturalgasintel.com/news/china-driving-asian-lng-import-surge-as-mexico-liquefaction-projects-advance/.
{{cite web}}: Missing or empty|title=(help) - ↑ https://www.powerfinancerisk.com/pdf/PFR05102021.
{{cite web}}: Missing or empty|title=(help) - ↑ Andrés Pizarro Pinto, Juan Sebastián Venegas Molina (2013). "Estimación del Precio de GNL a Largo Plazo: El proyecto Octopus en Concepción". Pontificia Universidad Católica de Chile.
{{cite web}}: CS1 maint: url-status (link) - ↑ Cite error: Invalid
<ref>tag; no text was provided for refs named:1 - ↑ Cite error: Invalid
<ref>tag; no text was provided for refs named:2 - ↑ Cheniere Marketing and Central El Campesino Sign 20-Year LNG Sale and Purchase Agreement, Cheniere Energy, INC., July 30, 2015
- ↑ Chile’s Penco LNG project delayed by 12-18 months, LNG World News, May 24, 2017
- ↑ "Suprema revoca permiso ambiental del proyecto Terminal GNL Penco Lirquén". La Tercera. January 31, 2017.
{{cite web}}: CS1 maint: url-status (link) - ↑ Tras 6 años aprueban proyecto gasífero Terminal GNL Penco, Diario Concepcion, Aug. 30, 2019
- ↑ "Paralización de GNL Penco: las arremetidas legales de las comunidades indígenas locales". Electricidad. February 11, 2020.
{{cite web}}: CS1 maint: url-status (link) - ↑ 19.0 19.1 "Organizaciones socioambientales presentan reclamaciones contra GNL Penco-Lirquén". Resumen. January 21, 2020.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Triunfo mapuche: comunidades del Bío Bío logran detener por segunda vez proyecto GNL Penco". Diario y Radio Universidad Chile. February 13, 2020.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Comunidades logran interponer reclamos contra proyecto Terminal GNL Penco-Lirquén". Resumen. May 5, 2021.
{{cite web}}: CS1 maint: url-status (link) - ↑ 22.0 22.1 "Sponsors seek debt for Chilean gas-fired, solar portfolio (pp 1, 10)". Power Finance and Risk. May 10, 2021.
{{cite web}}: CS1 maint: url-status (link) - ↑ Valencia, Jean (2023-10-25). "Tras 9 años: Comité de Ministros aprueba cuestionado proyecto terminal marítimo GNL Penco Lirquén". BioBioChile.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Sorpresa en el Biobío: Comité de Ministros aprobó resistido proyecto GNL Penco-Lirquén". Fundación Terram. 2023-10-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Penco estudia vía jurídica para impedir proyecto de gasoducto". Diario Concepción. 2023-10-27.
{{cite web}}: CS1 maint: url-status (link) - ↑ Cite error: Invalid
<ref>tag; no text was provided for refs named:12222 - ↑ Cite error: Invalid
<ref>tag; no text was provided for refs named:4 - ↑ "Gobierno prioriza proyecto GNL Penco Lirquén, pero compañía no confirma su ejecución en corto plazo". biobiochile.cl. 26 September 2024.
{{cite web}}: CS1 maint: url-status (link) - ↑ "GNL Penco".
{{cite web}}: CS1 maint: url-status (link) - ↑ Cite error: Invalid
<ref>tag; no text was provided for refs namedIJG - ↑ The Fight Against the Octopus in Chile, Earth First! Journal, Summer 2016
- ↑ Chile Revokes LNG Terminal Environmental Permit, BNamericas, accessed August 2017
- ↑ "Municipio de Penco se hace parte como tercero independiente en causa contra proyecto GNL". biobiochile.cl. July 7, 2025.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Se realizó audiencia por reclamaciones en contra de proyecto "Terminal GNL Penco-Lirquén"". 3ta.cl (in español). Retrieved 2025-08-05.
- ↑ "Penco Lanza Acciones Legales contra GNL Penco-Lirquén Ante el III Tribunal Ambiental de Valdivia". Hora12 (in español). Retrieved 2025-08-05.
