The Mavromati-Larymna Gas Pipeline is a proposed gas pipeline in Greece.[1]
Location
The pipeline runs from Mavromati to Larymna.[1]
Project details
Main Line
- Operator:
- Owner:
- Parent company:
- Capacity:
- Length: 36 km[1]
- Diameter: 10 in[1]
- Status: Proposed[1]
- Start Year:
- Cost: €19 million[1]
- Financing:
- Associated infrastructure:
Background
The pipeline was first proposed in 2013. In 2022 the pipeline was estimated to cost €17 million, this increased to €19 million in 2024.[2] Although included in the 2024 development plan it is not part of the 'three year plan' and no date for commissioning has been made public.[1]
Articles and resources
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 "Draft Ten-Year Development Plan (TYDP) 2024–2033" (PDF). DESFA. Hellenic Gas Transmission System Operator (DESFA) S.A. 2025-02-27. Retrieved 2025-09-16.
- ↑ "Development Plan of the National Natural Gas System 2023–2032" (PDF). Wayback Machine. Internet Archive; original publisher: Hellenic Gas Transmission System Operator (DESFA) S.A. 2023-06. Retrieved 2025-09-16.
{{cite web}}
: Check date values in:|date=
(help)