Tongde Aluminum power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Tongde Aluminum power station (晋能控股同德铝业自备电厂) is a cancelled power station in Yangjiawan Town, Baode, Xinzhou, Shanxi, China.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Tongde Aluminum power station | Yangjiawan Town, Baode, Xinzhou, Shanxi, China | 38.984454, 111.024381 (exact) |
Unit-level coordinates (WGS 84):
- Unit 3, Unit 4: 38.984454, 111.024381
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology |
---|---|---|---|---|
Unit 3 | Cancelled | coal: unknown | 600 | unknown |
Unit 4 | Cancelled | coal: unknown | 600 | unknown |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 3 | Shanxi Tongde Aluminum Industry Co Ltd [100%] | Chiping Xinyou Enterprise Management Co Ltd [45.0%]; Shanxi State-Owned Capital Investment and Operation Co Ltd [22.0%]; Dongfang Energy (Hong Kong) International Trading [15.0%]; China Cinda Asset Management Co Ltd [13.0%]; unknown [2.5%]; Yangquan Coal Industry (Group) Co Ltd [2.2%]; Shanxi Coking Coal Group Co Ltd [0.2%] |
Unit 4 | Shanxi Tongde Aluminum Industry Co Ltd [100%] | Chiping Xinyou Enterprise Management Co Ltd [45.0%]; Shanxi State-Owned Capital Investment and Operation Co Ltd [22.0%]; Dongfang Energy (Hong Kong) International Trading [15.0%]; China Cinda Asset Management Co Ltd [13.0%]; unknown [2.5%]; Yangquan Coal Industry (Group) Co Ltd [2.2%]; Shanxi Coking Coal Group Co Ltd [0.2%] |
Background on Project
Tongde Aluminum is constructing a 2 x 25 MW captive coal plant to support its aluminum production in Baode County, Xinzhou Prefecture.[1][2] It is under construction, and may eventually be expanded to 650 MW total.[3]
Proposed expansion
In November 2016 it was reported the plant would add an additional 2 x 600 MW units.[4]
2016: Nationwide Restrictions Imposed on Development of Coal-Fired Power Capacity
Due to new restrictions announced during 2016 by the National Energy Administration and the National Development and Reform Commission, further capacity expansions at this location appear to be on hold or cancelled. For details, see China's 2016 Restrictions on Development of Coal-Fired Power Capacity.
With no developments since 2016, the expansion project appears to be abandoned.
Project Details of expansion
- Sponsor: Tongde Aluminum
- Parent company: Datong Coal Mining Group
- Location: Huojialiang Village, Yangjiawan Town, Baode County, Xinzhou Prefecture, Shanxi Province, China
- Coordinates: 38.984454, 111.024381 (exact)
- Status: Cancelled
- Gross capacity: 1,200 MW (Units 3 & 4: 600 MW)
- Type:
- Projected in service:
- Coal type:
- Coal source:
- Source of financing:
Articles and Resources
References
- ↑ "山西同德铝业公司保德氧化铝项目开工奠," 2011/8/15
- ↑ "我县举行山西同德铝业有限公司保德氧化铝项目奠基仪式," Baode County government, 2011-12-31
- ↑ "同德铝业保德氧化铝项目国庆前后试产," 中国耐火材料网, 2014年09月04日
- ↑ "我县就同德氧化铝项目与信发集团洽谈对接," 保德新闻网, 2016-11-14
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.