Unnamed South-Eastern Siberia power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Unnamed_South-Eastern Siberia power station (Забайскальская ТЭС, Забайкальская ГРЭС) is a power station in the pre-permit stage in Russia.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Unnamed_South-Eastern Siberia power station | Russia | 52.5868158214866, 116.58421115524644 (approximate) |
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|
| Unit 1 | Pre-permit[1] | coal: bituminous[1][2] | 350[1] | unknown | 2031 (planned)[1] | False |
| Unit 2 | Pre-permit[1] | coal: bituminous[1][2] | 350[1] | unknown | 2031 (planned)[1] | False |
| Unit 3 | Pre-permit[1] | coal: bituminous[1][2] | 350[1] | unknown | 2031 (planned)[1] | False |
Table 3: Unit-level ownership and operator details
| Unit name | Operator | Owner | Parent |
|---|---|---|---|
| Unit 1 | En+ Generatsiya[1] | En+ Generatsiya JSC [100%][1] | En+ Group PJSC [100.0%] |
| Unit 2 | En+ Generatsiya[1] | En+ Generatsiya JSC [100%][1] | En+ Group PJSC [100.0%] |
| Unit 3 | En+ Generatsiya[1] | En+ Generatsiya JSC [100%][1] | En+ Group PJSC [100.0%] |
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
In January 2026, En+ Group announced that its subsidiary JSC En+ Generation had won a competitive capacity auction for new generating facilities held on December 29-30, 2025.[3] The company said it would build a new 1,050 MW thermal power plant to serve Zabaykalsky Krai and the Republic of Buryatia.[3]
According to the company, the plant would consist of three 350 MW units.[3] The first unit was planned to enter operation on July 1, 2031, and the plant was expected to reach its full installed capacity of 1,050 MW by December 1, 2031.[3]
The plant was referred to in press reports and company announcements as Zabaykalskaya TES (Забайкальская ТЭС) or Zabaykalskaya GRES. En+ registered a subsidiary, Zabaykalskaya GRES LLC, to manage electricity generation at the new facility.[4] Capital expenditure for the plant was estimated at over 400 billion rubles (approximately $5.4 billion at January 2026 exchange rates), though En+ initially disclosed a figure of over 300 billion rubles.[5]
The plant was expected to address a projected power deficit of up to 2,074 MW in the south-eastern part of the Siberian Unified Energy System by 2031.[6] The plant was planned to run on coal from the Zashulansky deposit in the Krasnochikoysky district of Zabaykalsky Krai, which is being developed by Razrezugol LLC, a joint venture between En+ and China's CHN Energy.[7] As of May 2026, two potential sites were under consideration: Krasnochikoysky district, close to the coal deposit, and Khiloksky district.[8]
Financing
The project was selected through Russia's competitive capacity auction for new generating facilities (KOM NGO), a mechanism that guarantees the winning developer elevated wholesale market capacity payments for 15 years following commissioning.[3]
Articles and Resources
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 https://enplusgroup.com/ru/media/news/press/strategicheskiy-proekt-en-dlya-zabaykalya-i-buryatii-postroyat-tes-moshchnostyu-1-gvt/.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.0 2.1 2.2 https://www.chita.ru/text/economics/2026/02/08/76254424/.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 3.2 3.3 3.4 Cite error: Invalid
<ref>tag; no text was provided for refs named:1 - ↑ "Строительство Забайкальской ТЭС мощностью 1050 мегаватт могут начать в Хилокском округе". chita.ru. February 2026.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Генерация вполцены". peretok.ru. January 2026.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Стратегический проект Эн+: для Забайкалья и Бурятии построят ТЭС мощностью 1 ГВт". enplusgroup.com. January 2026.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Строительство Забайкальской ТЭС мощностью 1050 мегаватт могут начать в Хилокском округе". chita.ru. February 2026.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Красночикойский округ может стать одним из флагманов экономического развития Забайкалья". hilok.ru. May 2026.
{{cite web}}: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.