West Delta LNG Deepwater Port Terminal
Part of the Global Gas Infrastructure Tracker, a Global Energy Monitor project. |
West Delta LNG Deepwater Port Terminal, also known as West Delta LNG Terminal, is a proposed LNG terminal in Louisiana, United States.
Location
Project Details
- Owner: West Delta LNG, LLC[1]
- Parent Company: LNG 21[1]
- Location: Plaquemines Parish, Louisiana, United States[1]
- Coordinates: 29.067, -89.656 (approximate)[2]
- Type: Export[1]
- Trains: 6
- Capacity: 6.1 MTPA
- Status: Proposed[1]
- Start Year: 2026[3]
- Formerly 2023-2024[4]
Note: mtpa = million tonnes per year; bcfd = billion cubic feet per day
Background
LNG 21, through its subsidiary, West Delta LNG, LLC, is developing the West Delta LNG Export Deepwater Port in federal waters offshore Plaquemines Parish, Louisiana. The project is based upon a new concept design, with a fixed-platform LNG production facility in uncongested open-waters with easy access for LNG carriers, free of the coastal footprint and inherent complications of shore-based facilities. The project will be stationed in the center of one of the US's top natural gas production basins, providing easy access to gas supplies.[1]
The project is designed to include six modular natural gas liquefaction trains, each with a nameplate capacity of 0.833 MTPA (million metric tonnes per annum) with the potential of up to 1.02 MTPA each, providing total optimal capacity of 6.1 MTPA of LNG.
In May of 2022, LNG 21 informed regulators that it was planning to shift the port's supply pipeline routes to another major pipeline, and the company was considering shifting its focus from Asian to European buyers.[5]
In February 2023, The Advocate reported that nearly two dozen environmental and grassroots organizations sent a letter to the U.S. Department of Transportation and its Maritime Administration (MARAD) requesting that the project's deepwater license be denied, with the developers having failed to meet several permitting deadlines.[5]
An April 2024 letter from the project sponsor to the United States Maritime Administration (MARAD) said that the company had, in December 2023, provided a status update and requested a further extension for its deepwater port license application review. The company was granted an extension through the end of December 2024 to provide an amended deepwater port application, and if it failed to do so, the application would be denied or indefinitely suspended.[6]
As of September 2025, West Delta LNG's application was still listed as pending on MARAD's site.[7] There is no evidence that the company submitted an amended deepwater port application, referenced in the April 2024 letter.
Articles and resources
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 West Delta LNG LNG 21 Group, accessed June 1, 2021
- ↑ Kristen Mosbrucker, Houston company looks to build floating LNG export facility near Plaquemines The Advocate, October 7, 2019
- ↑ "West Delta | LNG21". lng21group.com. Retrieved 2023-10-12.
- ↑ Maya Weber, West Delta LNG seeks MARAD approval for 6.1 million mt/year export facility offshore Louisiana, S&P Global, Sep. 27, 2019
- ↑ 5.0 5.1 ROBERT STEWART | Staff writer. "As deadline for delayed offshore LNG port looms, environmental groups call for permit denial". The Advocate. Retrieved 2023-09-06.
- ↑ https://downloads.regulations.gov/MARAD-2019-0095-0036/attachment_1.pdf
- ↑ https://www.maritime.dot.gov/ports/deepwater-ports-and-licensing/pending-applications