Wuxi West Zone Gas Thermal power station

From Global Energy Monitor
Part of the
Global Oil and Gas Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related categories:

Wuxi West Zone Gas Thermal power station (无锡西区燃机热电联产项目, 无锡西区燃气热电二期扩建项目) is an operating power station of at least 850-megawatts (MW) in Huishan District, Wuxi, Jiangsu, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Wuxi West Zone Gas Thermal power station Huishan District, Wuxi, Jiangsu, China 31.634457, 120.232722 (exact)[1]
Loading map...

Unit-level coordinates (WGS 84):

  • 1, 2: 31.634457, 120.232722

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year Equipment Emergency/Backup
1 Operating[2] fossil gas: natural gas[2] 400[3] combined cycle[4] yes[4] 2016[2] Siemens Energy: SGT5-4000F[5] no
2 Operating[6] fossil gas: natural gas[7][8][9] 450[8] combined cycle[8] yes[8] 2024[6] not found no

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
1 Wuxi Western Gas Thermoelectric Co Ltd [100%][7] Wuxi Municipal Public Utilities Industry Group Co Ltd [90.0%]; Kunlun Energy Company Limited Co Ltd [10.0%]
2 Wuxi Western Gas Thermoelectric Co Ltd [100%][7] Wuxi Municipal Public Utilities Industry Group Co Ltd [90.0%]; Kunlun Energy Company Limited Co Ltd [10.0%]

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

Unit 2 received approval from the Jiangsu Provincial Development and Reform Commission in March 2022. [10]Construction began on October 28, 2022. It is anticipated to commence operation in 2024.[11]

Articles and Resources

References

  1. "江苏省发展和改革委员会 行政许可 省发展改革委关于无锡西区燃气热电有限公司二期扩建项目节能报告的审查意见". fzggw.jiangsu.gov.cn. 2023-04-21. Archived from the original on 2024-05-23. Retrieved 2024-05-20.
  2. 2.0 2.1 2.2 https://web.archive.org/web/20210614231236/http://js.ifeng.com/a/20161130/5191077_0.shtml. Archived from the original on 2021-06-14. {{cite web}}: Missing or empty |title= (help)
  3. https://web.archive.org/web/20210117085437/http://www.wxxqrd.com/gsgk.jhtml. Archived from the original on 2021-01-17. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 https://web.archive.org/web/20220109163742/http://jcec.cn/cont.php?cid=293. Archived from the original on 2022-01-09. {{cite web}}: Missing or empty |title= (help)
  5. "【电力】江苏省38家燃机发电、热电联产、分布式项目汇总". www.hqhunt.com. 2018-09-27. Archived from the original on 2024-05-23. Retrieved 2024-05-20.
  6. 6.0 6.1 https://www.wxszjt.com/index.php?s=/article/detail/id/1542.html. {{cite web}}: Missing or empty |title= (help)
  7. 7.0 7.1 7.2 "无锡西区燃气热电有限公司二期扩建项目监理". 2022-07-26. Archived from the original on 2024-05-23.
  8. 8.0 8.1 8.2 8.3 https://web.archive.org/web/20220708200554/https://news.bjx.com.cn/html/20220321/1211482.shtml. Archived from the original on 2022-07-08. {{cite web}}: Missing or empty |title= (help)
  9. "获批!西区燃气热电二期项目即将开工!_扩建_无锡_能源". www.sohu.com. 2022-03-18. Archived from the original on 2024-05-23. Retrieved 2024-05-20.
  10. "江苏无锡西区燃气热电有限公司二期项目获批". 2022-03-21. Retrieved 2023-11-15.{{cite web}}: CS1 maint: url-status (link)
  11. "西区热电二期扩建项目正式开工". Retrieved 2023-11-15.{{cite web}}: CS1 maint: url-status (link)