Xiangtou International Yongzhou power station

From Global Energy Monitor
Part of the
Global Oil and Gas Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related categories:

Xiangtou International Yongzhou power station (零陵2×500MW级燃机调峰发电项目, 湘投国际永州燃气发电项目, 湖南永州零陵区2×500MW级燃机调峰发电项目) is a power station in pre-construction in Jielüqiao, Lingling District, Yongzhou, Hunan, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Xiangtou International Yongzhou power station Jielüqiao, Lingling District, Yongzhou, Hunan, China 26.2627694, 111.7041344 (approximate)[1]

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year
1 Pre-construction[1][2] fossil gas: natural gas[1][3][4] 500[1] combined cycle[1] not found 2025 (planned)[1][3]
2 Pre-construction[1][2] fossil gas: natural gas[1] 500[1] combined cycle[1] not found 2025 (planned)[1]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
1 Hunan Xiangtou International Investment Co Ltd [100%][1] Meiya Xiangtou Power Co Ltd [50.0%]; Hunan Xiangtou Holding Group Co Ltd [42.3%]; Hunan Xingxiang Investment Holding Group Co Ltd [4.7%]; Hunan Caixin Financial Holding Group Co Ltd [3.1%]
2 Hunan Xiangtou International Investment Co Ltd [100%][1] Meiya Xiangtou Power Co Ltd [50.0%]; Hunan Xiangtou Holding Group Co Ltd [42.3%]; Hunan Xingxiang Investment Holding Group Co Ltd [4.7%]; Hunan Caixin Financial Holding Group Co Ltd [3.1%]

Articles and Resources

References

  1. 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 "零陵2×500MW级燃机调峰发电项目获批复,预计2025年建成投产_图片新闻_零陵永州市零陵区政府门户". www.cnll.gov.cn. 2024-01-16. Archived from the original on 2024-05-06. Retrieved 2024-05-17.
  2. 2.0 2.1 http://fgw.hunan.gov.cn/fgw/xxgk_70899/xzzfgs11/shgk11/sp11/202411/t20241126_33511539.html. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 "湖南永州零陵区2×500MW级燃机调峰发电项目获批复-北极星电力新闻网". m.bjx.com.cn. 2024-01-23. Archived from the original on 2024-05-20. Retrieved 2024-05-17.
  4. "2024年省重点建设项目公布,株洲有这些". 2024-04-12. Archived from the original on 2024-05-20. Retrieved 024-05-17. {{cite web}}: Check date values in: |access-date= (help)