Xiantao power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Xiantao power station (华润电力仙桃发电厂) is an operating power station of at least 1320-megawatts (MW) in Changtangkou Town Zengjiatai Villege, Xiantao, Hubei, China with multiple units, some of which are not currently operating.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Xiantao power station Changtangkou Town Zengjiatai Villege, Xiantao, Hubei, China 30.371957, 113.567148 (exact)
Loading map...

Unit-level coordinates (WGS 84):

  • Phase II Unit 3, Phase II Unit 4, Unit 1, Unit 2: 30.371957, 113.567148

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Phase II Unit 3 Construction[1] coal: unknown 660[2] ultra-supercritical[2]
Phase II Unit 4 Construction[1] coal: unknown 660[1] ultra-supercritical[1]
Unit 1 Operating coal: unknown 660 ultra-supercritical 2022
Unit 2 Operating coal: unknown 660 ultra-supercritical 2022

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase II Unit 3 China Resources Power (Xiantao) Co Ltd [100%] China Resources Power Holdings Co Ltd [100.0%]
Phase II Unit 4 China Resources Power (Xiantao) Co Ltd [100%] China Resources Power Holdings Co Ltd [100.0%]
Unit 1 China Resources Power (Xiantao) Co Ltd [100%] China Resources Power Holdings Co Ltd [100.0%]
Unit 2 China Resources Power (Xiantao) Co Ltd [100%] China Resources Power Holdings Co Ltd [100.0%]

Background on Project

In 2015 China Resources Holding was permitted to build a 2 x 660 MW coal-fired power station in the city of Xiantao.[3][4]

The project was planned for completion in 2017,[5][6] but construction did not begin until March 2019.[7]

Unit 1 was connected to the grid by the end of June 2022,[8] and began operating July 10, 2022.[9]

Unit was connected to the grid on October 22, 2022,[10] and was operating by November 2022.[11]

In December 2022, a 2 x 660 MW Phase II expansion was announced at Xiantao power station.[12] In October 2023, Environmental Impact Assessment information was made available.[13] In November 2023, Phase II was reportedly preparing to start construction.[14]

Articles and Resources

References

  1. 1.0 1.1 1.2 1.3 https://hbj.xiantao.gov.cn/xwzx/gsgg/202310/t20231031_4920940.shtml. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 "计划投资53亿元!华润仙桃火电二期项目即将开工-北极星火力发电网". news.bjx.com.cn. 2023-11-20. Archived from the original on 2024-01-25. Retrieved 2023-12-01.
  3. "华润电力拟建湖北仙桃火电项目", BJX News, 2012-12-10
  4. "省发改委关于华润仙桃电厂新建工程项目核准的通知,” DRC of Hubei Province, 2015-10-16
  5. "湖北省2014-2015年大型火电项目建设选优评议结果公示," 能源局电力处, 2014-06-27
  6. "总投资51亿元 湖北华润仙桃电厂试桩开机"湖北日报, 2016/1/11
  7. "华润电力仙桃电厂新建2×660MW燃煤机组工程主体建筑开工," 河南省第二建筑工程发展有限公司, 2019/3/13
  8. 华润仙桃电厂2×660MW燃煤机组工程1号机组首次并网一次成功, china5e, 2022-06-27
  9. "仙桃电厂1号机组顺利通过168试运," CR Power, 2022-07-17
  10. "华润仙桃电厂2×660MW超超临界燃煤机组工程2号机组首次并网一次成功," BJX, 2022-10-20
  11. "2×660MW!湖北仙桃电厂项目实现“双投”," BJX, 2022-11-11
  12. 华润电力仙桃电厂——一期投产发电,二期稳步推进 news.hubeidaily.net, December 26, 2022
  13. 华润电力(仙桃)有限公司二期2×660MW超超临界燃煤发电机组工程环境影响评价信息公告-仙桃市人民政府 hbj.xiantao.gov, October 31, 2023
  14. 计划投资53亿元!华润仙桃火电二期项目即将开工 news.bjx.com, November 20, 2023