Xinjiang Changdong power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Xinjiang Changdong power station (新疆昌东2×66万千瓦煤电项目) is an operating power station of at least 660-megawatts (MW) in Wucaiwan Town, Jimsar, Changji, Xinjiang, China with multiple units, some of which are not currently operating.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Xinjiang Changdong power station | Wucaiwan Town, Jimsar, Changji, Xinjiang, China | 44.851472, 89.02888 (approximate)[1] |
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|
| Unit 1 | Operating[2][3][4] | coal: unknown[5][1] | 660[1] | ultra-supercritical[1] | 2026[4] | False |
| Unit 2 | Construction[3][6] | coal: unknown[5][1] | 660[1] | ultra-supercritical[1] | – | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Unit 1 | Xinjiang Changdong Power Generation Co., Ltd. [100%][1] | Xinjiang Changdong Power Generation Co., Ltd. [100.0%] |
| Unit 2 | Xinjiang Changdong Power Generation Co., Ltd. [100%][1] | Xinjiang Changdong Power Generation Co., Ltd. [100.0%] |
Project-level coal details
- Coal source(s): domestic
Background
Both units are under construction. In 2024, Unit 1 was actively being built, with Unit 2's construction commencing in March.[7]
In 2025, Unit 1 reached the turbine rotation stage and was connected to the grid in December.[8][9]
Unit 1 passed its 168-hour trial in January 2026, while Unit 2 was progressing toward commissioning by the end of the year.[10]
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Articles and Resources
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 https://web.archive.org/web/20240125124819/https://news.bjx.com.cn/html/20230823/1327644.shtml. Archived from the original on 2024-01-25.
{{cite web}}: Missing or empty|title=(help) - ↑ "昌东2×66万千瓦煤电项目项目获批_工作动态_新疆维吾尔自治区发展和改革委员会". xjdrc.xinjiang.gov.cn. 2023-08-18. Archived from the original on 2024-01-25. Retrieved 2023-10-25.
- ↑ 3.0 3.1 MP Weixin https://web.archive.org/web/20240125124923/https://mp.weixin.qq.com/s/EeQymsUsSZojLiIalbgxhw. Archived from the original on 2024-01-25.
{{cite web}}: Missing or empty|title=(help) - ↑ 4.0 4.1 http://www.tech.ceec.net.cn/art/2026/1/14/art_22527_2519799.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 5.0 5.1 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ MP Weixin https://web.archive.org/web/20240125125039/https://mp.weixin.qq.com/s/1isnHonf2vVWK6pPlz_6vA. Archived from the original on 2024-01-25.
{{cite web}}: Missing or empty|title=(help) - ↑ "新疆昌东发电2×660兆瓦超超临界(2号机组)工程项目正式开工". 北极星电力网. 2024-03-13. Retrieved 2026-07-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "新疆昌东发电1号机组进入汽轮机首次冲转阶段". 微信公众号. 2025-05-25. Retrieved 2026-07-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "新疆昌东发电2x660MW超超临界机组1号机组并网一次成功". 北极星电力网. 2025-12-22. Retrieved 2026-07-30.
{{cite web}}: CS1 maint: url-status (link) - ↑ "新疆昌东发电有限公司2×660兆瓦超超临界机组项目工程1号机组168小时满负荷试运圆满完成". 中国能建华中电力试研院. 2026-01-14. Retrieved 2026-07-30.
{{cite web}}: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.