Xinjiang Changdong power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Xinjiang Changdong power station (新疆昌东2×66万千瓦煤电项目) is an operating power station of at least 660-megawatts (MW) in Wucaiwan Town, Jimsar, Changji, Xinjiang, China with multiple units, some of which are not currently operating.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Xinjiang Changdong power station Wucaiwan Town, Jimsar, Changji, Xinjiang, China 44.851472, 89.02888 (approximate)[1]
Loading map...

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Emergency/Backup
Unit 1 Operating[2][3][4] coal: unknown[5][1] 660[1] ultra-supercritical[1] 2026[4] False
Unit 2 Construction[3][6] coal: unknown[5][1] 660[1] ultra-supercritical[1] – False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Xinjiang Changdong Power Generation Co., Ltd. [100%][1] Xinjiang Changdong Power Generation Co., Ltd. [100.0%]
Unit 2 Xinjiang Changdong Power Generation Co., Ltd. [100%][1] Xinjiang Changdong Power Generation Co., Ltd. [100.0%]

Project-level coal details

  • Coal source(s): domestic

Background

Both units are under construction. In 2024, Unit 1 was actively being built, with Unit 2's construction commencing in March.[7]

In 2025, Unit 1 reached the turbine rotation stage and was connected to the grid in December.[8][9]

Unit 1 passed its 168-hour trial in January 2026, while Unit 2 was progressing toward commissioning by the end of the year.[10]

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Articles and Resources

References

  1. ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 https://web.archive.org/web/20240125124819/https://news.bjx.com.cn/html/20230823/1327644.shtml. Archived from the original on 2024-01-25. {{cite web}}: Missing or empty |title= (help)
  2. ↑ "昌东2×66万千瓦煤电项目项目获批_工作动态_新疆维吾尔自治区发展和改革委员会". xjdrc.xinjiang.gov.cn. 2023-08-18. Archived from the original on 2024-01-25. Retrieved 2023-10-25.
  3. ↑ 3.0 3.1 MP Weixin https://web.archive.org/web/20240125124923/https://mp.weixin.qq.com/s/EeQymsUsSZojLiIalbgxhw. Archived from the original on 2024-01-25. {{cite web}}: Missing or empty |title= (help)
  4. ↑ 4.0 4.1 http://www.tech.ceec.net.cn/art/2026/1/14/art_22527_2519799.html. {{cite web}}: Missing or empty |title= (help)
  5. ↑ 5.0 5.1 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker. {{cite web}}: Missing or empty |title= (help)
  6. ↑ MP Weixin https://web.archive.org/web/20240125125039/https://mp.weixin.qq.com/s/1isnHonf2vVWK6pPlz_6vA. Archived from the original on 2024-01-25. {{cite web}}: Missing or empty |title= (help)
  7. ↑ "新疆昌东发电2×660兆瓦超超临界(2号机组)工程项目正式开工". 北极星电力网. 2024-03-13. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  8. ↑ "新疆昌东发电1号机组进入汽轮机首次冲转阶段". 微信公众号. 2025-05-25. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  9. ↑ "新疆昌东发电2x660MW超超临界机组1号机组并网一次成功". 北极星电力网. 2025-12-22. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)
  10. ↑ "新疆昌东发电有限公司2×660兆瓦超超临界机组项目工程1号机组168小时满负荷试运圆满完成". 中国能建华中电力试研院. 2026-01-14. Retrieved 2026-07-30.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.