Yellow River Delta power station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Yellow River Delta power station (滨化集团黄河三角洲滨州热电) is an operating power station of at least 450-megawatts (MW) in Huanghe East Road, Bincheng District, Binzhou, Shandong, China. It is also known as 滨州市东郊公共供热中心.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Yellow River Delta power station | Huanghe East Road, Bincheng District, Binzhou, Shandong, China | 37.37808, 118.079077 (exact) |
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2, Unit 3: 37.37808, 118.079077
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|---|
| Unit 1 | Operating | coal: unknown[1] | 50 | subcritical | yes | 2018 | False |
| Unit 2 | Operating | coal: unknown[1] | 50 | subcritical | yes | 2018 | False |
| Unit 3 | Operating | coal: unknown[1] | 350 | subcritical | yes | 2025 | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Unit 1 | Huanghe Sanjiaozhou (Binzhou) Thermal Power Co Ltd [100%] | unknown [68.1%]; China Development Bank Corp [21.8%]; Binzhou Heyi Industrial Investment Partnership LP [5.5%]; Befar Group Co Ltd [4.6%] |
| Unit 2 | Huanghe Sanjiaozhou (Binzhou) Thermal Power Co Ltd [100%] | unknown [68.1%]; China Development Bank Corp [21.8%]; Binzhou Heyi Industrial Investment Partnership LP [5.5%]; Befar Group Co Ltd [4.6%] |
| Unit 3 | Huanghe Sanjiaozhou (Binzhou) Thermal Power Co Ltd [100%] | unknown [68.1%]; China Development Bank Corp [21.8%]; Binzhou Heyi Industrial Investment Partnership LP [5.5%]; Befar Group Co Ltd [4.6%] |
Project-level captive use details
- Captive industry use (heat or power): both
- Captive industry: Aluminum
- Non-industry use: heat
Project-level coal details
- Coal source(s): domestic
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
BEFAR Group is constructing a 350 MW subcritical coal plant on Huanghe East Road in Bincheng District, with two 50 MW back-up units. It is planned for operation in 2017. The plant was originally developed by Weiqiao Group and later transferred to BEFAR Group.[2][3]
Construction was completed in 2018.[4]
A social stability risk assessment was publicized for a 1x350 MW unit at this station in March 2023[5]. In November 2024, the unit was connected to the grid[6]. In March 2025, the unit passed the 168-hour trial run[7].
Articles and Resources
References
- ↑ 1.0 1.1 1.2 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ "公司中标黄河三角洲热力公司“上大压小”热电联产工程," China Engineering Group, 2015-9-11
- ↑ "山东滨州热电项目正式破土动工," 中国电力化工网, 2015-10-13
- ↑ "滨化集团收购黄河三角洲热力公司股权的公告," 滨化集团公司, 2018-2-22
- ↑ "黄河三角洲(滨州)热力1×350MW项目社会稳定风险评估公示". 滨化集团. 2023-03-07. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "滨化集团热力中心大机组启动并网成功". 中国热电. 2024-11-21. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "黄河三角洲1×350MW超临界机组通过168小时试运行". 北极星电力网. 2025-03-07. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link)