Yichang Xiaoting power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Yichang Xiaoting power station (华润电力宜昌发电厂) is an operating power station of at least 700-megawatts (MW) in Xiaoting Industrial Park, Xiaoting, Yichang, Hubei, China with multiple units, some of which are not currently operating. It is also known as 华润猇亭热电联产项目.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Yichang Xiaoting power station Xiaoting Industrial Park, Xiaoting, Yichang, Hubei, China 30.496979, 111.441912 (exact)
Loading map...

Unit-level coordinates (WGS 84):

  • Phase II Unit 3, Unit 1, Unit 2: 30.496979, 111.441912

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year Emergency/Backup
Phase II Unit 3 Construction[1] coal: unknown[2][3] 350[3] unknown[3] yes[3] 2026 (planned) False
Unit 1 Operating coal: unknown[2] 350 supercritical yes 2014 False
Unit 2 Operating coal: unknown[2] 350 supercritical yes 2014 False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase II Unit 3 Cr Power (Yichang) Co Ltd [100%] China Resources Power Holdings Co Ltd [100.0%]
Unit 1 Cr Power (Yichang) Co Ltd [100%] China Resources Power Holdings Co Ltd [100.0%]
Unit 2 Cr Power (Yichang) Co Ltd [100%] China Resources Power Holdings Co Ltd [100.0%]

Project-level coal details

  • Coal source(s): domestic

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background on Project

China Resources proposed a two-unit coal-fired power plant with a total planned capacity of 700 MW in Hubei Province. The plant went online in 2014.[4]

Phase II Unit 3 was approved in March 2023[5] and a project management tender was issued in November[6]. In 2024, construction began in September[7], and various tenders were issued[8]. Significant construction progress was observed in satellite imagery through 2025[9].

In July 2026, the unit passed the 168-hour trial[10].

Articles and Resources

References

  1. ↑ https://mp.weixin.qq.com/s/YmhudcvM2BTNC5RH8ayftA. {{cite web}}: Missing or empty |title= (help)
  2. ↑ 2.0 2.1 2.2 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker. {{cite web}}: Missing or empty |title= (help)
  3. ↑ 3.0 3.1 3.2 3.3 https://mp.weixin.qq.com/s/LXVZ1rqr_7HA55vVhZPi6A. {{cite web}}: Missing or empty |title= (help)
  4. ↑ "华润宜昌热电项目全面投产", 华润(集团)有限公司, 来源:三峡日报, 2014-06-03
  5. ↑ "华润电力(宜昌)二期1×350MW项目核准" (PDF). 电力周刊. 2023-03-15. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  6. ↑ "华润宜昌二期1×350MW项目工程监理中标". 微信公众平台. 2024-01-08. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  7. ↑ "华润宜昌1×350MW项目主体安装施工招标". 北极星电力网. 2024-08-20. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  8. ↑ "华润宜昌二期项目14项中标公示". 北极星电力网. 2024-06-25. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  9. ↑ "宜昌火电二期项目施工进展显著". 北极星电力网. 2025-07-07. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  10. ↑ "华润宜昌热电联产二期3号机组通过168小时试运行". 北极星电力网. 2026-07-27. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)