Yichang Zhongji Thermal power station

From Global Energy Monitor
Part of the
Global Oil and Gas Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related categories:

Yichang Zhongji Thermal power station (京宜热电小溪塔项目, 中基宜昌小溪塔天然气热电联产项目, 小溪塔天然气热电联产项目, 宜昌市夷陵区中基热电厂) is an operating power station of at least 150-megawatts (MW) in Yiling District, Yichang, Hubei, China. It is also known as Zhongji Xiaoxita Natural gas power station.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Yichang Zhongji Thermal power station Yiling District, Yichang, Hubei, China 30.79063944984613, 111.35979065156 (approximate)[1][2]
Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year
1 Operating[3] fossil gas: natural gas[1][2] 75[1][2] combined cycle[1][2] yes[1][2] 2024[3]
2 Operating[4] fossil gas: natural gas[1][2] 75[1][2] combined cycle[1][2] yes[1][2] 2024[4]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
1 Yichang Yiling Zhongji Thermal Power Co Ltd [100%][5][6] Beijing Jingneng Clean Energy Co Ltd [90.0%]; China Primary Energy Holdings Ltd [10.0%]
2 Yichang Yiling Zhongji Thermal Power Co Ltd [100%][5][6] Beijing Jingneng Clean Energy Co Ltd [90.0%]; China Primary Energy Holdings Ltd [10.0%]

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

The energy-saving report for Yichang Zhongji Thermal power station (宜昌市夷陵区中基热电厂) was approved by the Yichang Municipal Development and Reform Commission on July 9, 2018.[7] An extension was applied for on May 1, 2021, and it was approved. [8]

Unit 1 commenced construction in June 2022 and started operations in October 2023. [9]Unit 2 is expected to commence production in the first half of 2024.[10]

Articles and Resources

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 https://web.archive.org/web/20220708201455/https://news.bjx.com.cn/html/20220324/1212480.shtml. Archived from the original on 2022-07-08. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 "祝贺!中基湖北宜昌市夷陵区小溪塔天然气热电联产总承包项目1号联合循环机组并网一次成功-国际电力网". mpower.in-en.com. 2023-12-28. Archived from the original on 2024-05-17. Retrieved 2024-05-16.
  3. 3.0 3.1 "京宜热电小溪塔项目1号机组投入运营 -三峡宜昌网". www.cn3x.com.cn. 2024-04-25. Archived from the original on 2024-05-17. Retrieved 2024-05-16.
  4. 4.0 4.1 https://m.bjx.com.cn/mnews/20240827/1397159.shtml. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 https://www.qcc.com/firm/95e0ad117851e158f71a1cfac6027587.html. {{cite web}}: Missing or empty |title= (help)
  6. 6.0 6.1 https://web.archive.org/web/20221003010041/http://fgw.hubei.gov.cn/fbjd/xxgkml/xkfw/xzxkjg/xmspqk/202105/t20210526_3757558.shtml. Archived from the original on 2022-10-03. {{cite web}}: Missing or empty |title= (help)
  7. "省发展改革委关于中基宜昌市夷陵区小溪塔天然气热电联产项目的节能审查意见". 2018-07-09. Retrieved 2023-11-13.{{cite web}}: CS1 maint: url-status (link)
  8. "省发改委关于中基宜昌市夷陵区小溪塔天然气热电联产项目节能审查意见延期的复函". 2021-05-01. Retrieved 2023-11-13.{{cite web}}: CS1 maint: url-status (link)
  9. "中基宜昌市夷陵区小溪塔天然气热电联产项目正式对外供热". 2023-10-31. Retrieved 2323-11-13. {{cite web}}: Check date values in: |access-date= (help)CS1 maint: url-status (link)
  10. ""蓝图"正在变为"实景" 中基热电项目开启"抢跑"模式". 2023-02-16. Retrieved 2023-11-13.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.