Yiyang power station (陕煤化长安益阳发电厂) is an operating power station of at least 3920-megawatts (MW) in Lichanggang, Heshan, Yiyang, Hunan, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Yiyang power station Lichanggang, Heshan, Yiyang, Hunan, China 28.5966667, 112.2686111 (exact)
Loading map...

Unit-level coordinates (WGS 84):

  • Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4, Phase III Unit 5, Phase III Unit 6: 28.5966667, 112.2686111

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Emergency/Backup
Phase I Unit 1 Operating coal: anthracite[1] 330 subcritical 2000 False
Phase I Unit 2 Operating coal: anthracite[1] 330 subcritical 2001 False
Phase II Unit 3 Operating coal: anthracite[1] 630 supercritical 2007 False
Phase II Unit 4 Operating coal: anthracite[1] 630 supercritical 2008 False
Phase III Unit 5 Operating[2] coal: anthracite[1] 1000 ultra-supercritical 2025 False
Phase III Unit 6 Operating[3] coal: anthracite[1] 1000 ultra-supercritical 2025 False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase I Unit 1 Chang'an Yiyang Power Generation Co Ltd [100%] Shaanxi Coal and Chemical Industry Co Ltd [97.4%]; unknown [2.6%]
Phase I Unit 2 Chang'an Yiyang Power Generation Co Ltd [100%] Shaanxi Coal and Chemical Industry Co Ltd [97.4%]; unknown [2.6%]
Phase II Unit 3 Chang'an Yiyang Power Generation Co Ltd [100%] Shaanxi Coal and Chemical Industry Co Ltd [97.4%]; unknown [2.6%]
Phase II Unit 4 Chang'an Yiyang Power Generation Co Ltd [100%] Shaanxi Coal and Chemical Industry Co Ltd [97.4%]; unknown [2.6%]
Phase III Unit 5 Chang'an Yiyang Power Generation Co Ltd [100%] Shaanxi Coal and Chemical Industry Co Ltd [97.4%]; unknown [2.6%]
Phase III Unit 6 Chang'an Yiyang Power Generation Co Ltd [100%] Shaanxi Coal and Chemical Industry Co Ltd [97.4%]; unknown [2.6%]

Project-level coal details

  • Coal source(s): domestic

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

Yiyang power station was originally a four-unit coal-fired power plant with a total capacity of 1,920 MW. The plant was completed between 2000 and 2008, and is majority-owned by Shaanxi Coal and Chemical Industry Group.[4][5]

Expansion

In July 2019, it was reported that a 2 x 1,000 MW expansion at the power station was planned and included in the "14th Five-Year Plan for Electric Power Development" of Hunan Province (2021-2025). Pre-feasibility studies were underway.[6] 

According to a job announcement, the units were permitted on December 30, 2021.[7]

Construction reportedly began on July 25, 2022.[8]

Phase III Unit 5 saw construction progress in 2023, with the cooling tower V-shaped columns hoisted in July[9]. In 2024, the cooling tower was capped in May[10], the generator rotor was inserted in August[11], the plant power system was energized in October[12], and the unit was connected to the grid in December[13]. In February 2025, the unit passed the 168-hour trial[14].

Phase III Unit 6 had the boiler heating surface welded in December 2023[15]. In 2024, the low-pressure heater was hoisted in July[16], the generator stator was hoisted in October[17], the boiler hydraulic test passed in November[18], and the plant power system was energized in December[19]. In March 2025, flushing was completed[20], the unit was connected to the grid in April[21], and passed the 168-hour trial, entering commercial operation in May[22].

Articles and Resources

References

  1. ↑ 1.0 1.1 1.2 1.3 1.4 1.5 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker. {{cite web}}: Missing or empty |title= (help)
  2. ↑ https://news.bjx.com.cn/html/20250303/1429763.shtml. {{cite web}}: Missing or empty |title= (help)
  3. ↑ https://news.bjx.com.cn/html/20250523/1442925.shtml. {{cite web}}: Missing or empty |title= (help)
  4. ↑ Yiyang Powerplant, Enipedia, accessed Sept. 2015.
  5. ↑ "陕煤化集团顺利完成益阳发电公司产权管理权交接," Shaanxi Coal and Chemical Industry Group, 2014-01-09
  6. ↑ "2×1000MW+4×660MW!两个大型火电项目获湖南省能源局“路条”," 北极星电力网新闻中心, 2019/7/29
  7. ↑ 长安电力华中发电有限公司2022年招聘会, 长安电力华中发电有限公司, 2022-05-24
  8. ↑ 2×100万千瓦!益阳电厂三期正式开工, BJX, 2022-07-25
  9. ↑ "益阳电厂三期冷却塔V型钢柱首榀吊装就位". 微信公众平台. 2023-08-22. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  10. ↑ "长安益阳三期冷却塔顺利封顶". 北极星电力网. 2024-06-03. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  11. ↑ "长安益阳三期5号机组发电机转子穿装完成". 北极星电力网. 2024-08-27. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  12. ↑ "长安益阳三期5号机组厂用电受电一次成功". 微信公众平台. 2024-10-28. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  13. ↑ "长安益阳三期5号机组首次并网成功". 微信公众平台. 2025-01-10. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  14. ↑ "长安益阳三期5号机组通过168小时试运". 北极星电力网. 2025-03-03. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  15. ↑ "长安益阳项目6号机组锅炉受热面开焊". 微信公众平台. 2024-01-16. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  16. ↑ "长安益阳三期6号机组首台低压加热器吊装就位". 微信公众平台. 2024-08-08. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  17. ↑ "益阳项目6号机组发电机定子吊装就位". 北极星电力网. 2024-10-21. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  18. ↑ "长安益阳6号机组锅炉水压试验一次成功". 微信公众平台. 2024-11-19. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  19. ↑ "长安益阳6号机组厂用系统受电一次成功". 微信公众平台. 2024-12-19. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  20. ↑ "益阳项目6号机组点火吹管圆满完成". 微信公众平台. 2025-03-31. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  21. ↑ "益阳6号机组首次并网一次成功". 北极星电力网. 2025-04-23. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  22. ↑ "长安益阳6号机组通过168小时试运行". 北极星电力网. 2025-05-23. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)