Yiyang power station (陕煤化长安益阳发电厂) is an operating power station of at least 3920-megawatts (MW) in Lichanggang, Heshan, Yiyang, Hunan, China.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Yiyang power station | Lichanggang, Heshan, Yiyang, Hunan, China | 28.5966667, 112.2686111 (exact) |
Unit-level coordinates (WGS 84):
- Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4, Phase III Unit 5, Phase III Unit 6: 28.5966667, 112.2686111
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|
| Phase I Unit 1 | Operating | coal: anthracite[1] | 330 | subcritical | 2000 | False |
| Phase I Unit 2 | Operating | coal: anthracite[1] | 330 | subcritical | 2001 | False |
| Phase II Unit 3 | Operating | coal: anthracite[1] | 630 | supercritical | 2007 | False |
| Phase II Unit 4 | Operating | coal: anthracite[1] | 630 | supercritical | 2008 | False |
| Phase III Unit 5 | Operating[2] | coal: anthracite[1] | 1000 | ultra-supercritical | 2025 | False |
| Phase III Unit 6 | Operating[3] | coal: anthracite[1] | 1000 | ultra-supercritical | 2025 | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Phase I Unit 1 | Chang'an Yiyang Power Generation Co Ltd [100%] | Shaanxi Coal and Chemical Industry Co Ltd [97.4%]; unknown [2.6%] |
| Phase I Unit 2 | Chang'an Yiyang Power Generation Co Ltd [100%] | Shaanxi Coal and Chemical Industry Co Ltd [97.4%]; unknown [2.6%] |
| Phase II Unit 3 | Chang'an Yiyang Power Generation Co Ltd [100%] | Shaanxi Coal and Chemical Industry Co Ltd [97.4%]; unknown [2.6%] |
| Phase II Unit 4 | Chang'an Yiyang Power Generation Co Ltd [100%] | Shaanxi Coal and Chemical Industry Co Ltd [97.4%]; unknown [2.6%] |
| Phase III Unit 5 | Chang'an Yiyang Power Generation Co Ltd [100%] | Shaanxi Coal and Chemical Industry Co Ltd [97.4%]; unknown [2.6%] |
| Phase III Unit 6 | Chang'an Yiyang Power Generation Co Ltd [100%] | Shaanxi Coal and Chemical Industry Co Ltd [97.4%]; unknown [2.6%] |
Project-level coal details
- Coal source(s): domestic
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
Yiyang power station was originally a four-unit coal-fired power plant with a total capacity of 1,920 MW. The plant was completed between 2000 and 2008, and is majority-owned by Shaanxi Coal and Chemical Industry Group.[4][5]
Expansion
In July 2019, it was reported that a 2 x 1,000 MW expansion at the power station was planned and included in the "14th Five-Year Plan for Electric Power Development" of Hunan Province (2021-2025). Pre-feasibility studies were underway.[6]
According to a job announcement, the units were permitted on December 30, 2021.[7]
Construction reportedly began on July 25, 2022.[8]
Phase III Unit 5 saw construction progress in 2023, with the cooling tower V-shaped columns hoisted in July[9]. In 2024, the cooling tower was capped in May[10], the generator rotor was inserted in August[11], the plant power system was energized in October[12], and the unit was connected to the grid in December[13]. In February 2025, the unit passed the 168-hour trial[14].
Phase III Unit 6 had the boiler heating surface welded in December 2023[15]. In 2024, the low-pressure heater was hoisted in July[16], the generator stator was hoisted in October[17], the boiler hydraulic test passed in November[18], and the plant power system was energized in December[19]. In March 2025, flushing was completed[20], the unit was connected to the grid in April[21], and passed the 168-hour trial, entering commercial operation in May[22].
Articles and Resources
References
- ↑ 1.0 1.1 1.2 1.3 1.4 1.5 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker.
{{cite web}}: Missing or empty|title=(help) - ↑ https://news.bjx.com.cn/html/20250303/1429763.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ https://news.bjx.com.cn/html/20250523/1442925.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ Yiyang Powerplant, Enipedia, accessed Sept. 2015.
- ↑ "陕煤化集团顺利完成益阳发电公司产权管理权交接," Shaanxi Coal and Chemical Industry Group, 2014-01-09
- ↑ "2×1000MW+4×660MW!两个大型火电项目获湖南省能源局“路条”," 北极星电力网新闻中心, 2019/7/29
- ↑ 长安电力华中发电有限公司2022年招聘会, 长安电力华中发电有限公司, 2022-05-24
- ↑ 2×100万千瓦!益阳电厂三期正式开工, BJX, 2022-07-25
- ↑ "益阳电厂三期冷却塔V型钢柱首榀吊装就位". 微信公众平台. 2023-08-22. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "长安益阳三期冷却塔顺利封顶". 北极星电力网. 2024-06-03. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "长安益阳三期5号机组发电机转子穿装完成". 北极星电力网. 2024-08-27. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "长安益阳三期5号机组厂用电受电一次成功". 微信公众平台. 2024-10-28. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "长安益阳三期5号机组首次并网成功". 微信公众平台. 2025-01-10. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "长安益阳三期5号机组通过168小时试运". 北极星电力网. 2025-03-03. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "长安益阳项目6号机组锅炉受热面开焊". 微信公众平台. 2024-01-16. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "长安益阳三期6号机组首台低压加热器吊装就位". 微信公众平台. 2024-08-08. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "益阳项目6号机组发电机定子吊装就位". 北极星电力网. 2024-10-21. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "长安益阳6号机组锅炉水压试验一次成功". 微信公众平台. 2024-11-19. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "长安益阳6号机组厂用系统受电一次成功". 微信公众平台. 2024-12-19. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "益阳项目6号机组点火吹管圆满完成". 微信公众平台. 2025-03-31. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "益阳6号机组首次并网一次成功". 北极星电力网. 2025-04-23. Retrieved 2026-07-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "长安益阳6号机组通过168小时试运行". 北极星电力网. 2025-05-23. Retrieved 2026-07-29.