Yuncheng Gunlü power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Yuncheng Gunlü power station (运城关铝热电) is an operating power station of at least 560-megawatts (MW) in Jiezhou Town, Yanhu District, Yuncheng, Shanxi, China. It is also known as 关铝集团运城关铝热电公司 (Unit 3, Unit 4), Yuncheng Guanlü power station (Unit 3, Unit 4).
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Yuncheng Gunlü power station | Jiezhou Town, Yanhu District, Yuncheng, Shanxi, China | 34.987796, 110.954242 (exact) |
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2, Unit 3, Unit 4: 34.987796, 110.954242
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | Operating | coal: unknown | 200 | subcritical | 2008 |
Unit 2 | Operating | coal: unknown | 200 | subcritical | 2008 |
Unit 3 | Operating | coal: unknown | 80 | subcritical | 2019 |
Unit 4 | Operating | coal: unknown | 80 | subcritical | 2019 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | Shanxi Guanlu Yuncheng Thermal Power Factory [100%] | Shanxi Guanlu Group Co Ltd [70.0%]; China Minmetals Corp [26.3%]; Hunan Xingxiang Investment Holding Group Co Ltd [2.6%]; unknown [0.9%]; Hunan Caixin Financial Holding Group Co Ltd [0.3%] |
Unit 2 | Shanxi Guanlu Yuncheng Thermal Power Factory [100%] | Shanxi Guanlu Group Co Ltd [70.0%]; China Minmetals Corp [26.3%]; Hunan Xingxiang Investment Holding Group Co Ltd [2.6%]; unknown [0.9%]; Hunan Caixin Financial Holding Group Co Ltd [0.3%] |
Unit 3 | Yuncheng Jinjian Thermal Power Co Ltd [100%] | Shanxi State-Owned Capital Investment and Operation Co Ltd [76.5%]; Yuncheng Urban Construction Investment Development Co Ltd [10.6%]; Shanxi Construction Investment Group Co Ltd [8.5%]; Yuncheng Yunda Asset Management Co Ltd [4.1%]; unknown [0.3%] |
Unit 4 | Yuncheng Jinjian Thermal Power Co Ltd [100%] | Shanxi State-Owned Capital Investment and Operation Co Ltd [76.5%]; Yuncheng Urban Construction Investment Development Co Ltd [10.6%]; Shanxi Construction Investment Group Co Ltd [8.5%]; Yuncheng Yunda Asset Management Co Ltd [4.1%]; unknown [0.3%] |
Project-level captive use details
- Captive industry use (heat or power): both
- Captive industry: Aluminum
Background
Yuncheng Gunlü power station is a 2 x 200 MW coal-fired power station built in 2008 and owned by Shanxi Guanlü Group.[1][2]
Expansion
In May 2017 Shanxi Guanlü Group was permitted to build two 80 MW coal-fired back-up units for the power station, units 3-4.[3]
Construction began in July 2017. Operation is planned for October 2018.[4]
Unit 3 was commissioned in March 2019.[5] Unit 4 was commissioned in 2019.[6]
Articles and Resources
References
- ↑ "运城关铝热电有限公司," Shanxi Guanlü Group, 2011-3-15
- ↑ "公司简介," Shanxi Guanlü Group, accessed Jan 2018
- ↑ "关于关铝热电有限公司2×80兆瓦背压机组热电项目核准的通知," Shanxi Province, 2017年05月17日
- ↑ "中心城区南同蒲铁路以北区域今冬供大暖," 黄河晨报, 2018年4月10日
- ↑ "中国能建山西院承建运城晋建热电3号机组通过试运," 赵亮宇, 2019-03-04
- ↑ "运城关铝热源厂2号机组启动 应对极寒天气保供暖," 山西新闻网微运城, 2019-12-23
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.