Zhangjiagang LNG Terminal (张家港海进江LNG接收站项目,苏州LNG储备中心) is a proposed LNG import terminal in Jiangsu Province, China.

Location

The satellite image below shows the exact location where the terminal is proposed at Zhangjiagang Port on Yangtze River, Suzhou Municipality in Jiangsu Province, China.[1]

Loading map...

Project details

  • Owner: Jiangsu Huaxin Yongnan Energy Technology Co., Ltd. 江苏华鑫永南能源科技有限公司[2]
  • Parent company: Wing Chew Holdings Limited 永卓控股有限公司
  • Location: Jiangyin Port, Jiangsu Province, China[2]
  • Coordinates: 31.823502205729792, 120.82246078620071 (exact)
  • Capacity: 3 million tonnes per year[2]
  • Trains:
  • Status: Proposed
  • Type: Import
  • Start year:
  • Cost:
  • Financing:
  • FID Status:
  • Associated infrastructure:

Background

The terminal was proposed in 2018 together with four other inner river LNG terminal projects along the Yangzte River. [3]PetroChina was involved in this project. A joint venture company was established in June 2022 by PetroChina and Wing Chew Holdings. [4]However, in August 2023, when the Environmental Impact Assessment of the project was released for public review, the owner changed to Jiangsu Huaxin Yongnan Energy Technology Co., Ltd. a wholly owned subsidiary of Wing Chew Holdings Limited. PetroChina presumedly dropped the project. Wing Chew Holdings Limited is also the parent company of Jiangsu Yonggang Group, an iron & steel giant located in Zhangjiagang.[5]

According to its Environmental Impact Assessment for public review, Zhangjiagang LNG terminal includes a terminal with three storage tanks with 200,000 cubic meters each, a berth and a 6-kilometer transportation pipeline. The total cost is estimated around 5 billion RMB.[6]

建设内容:张家港海进江LNG接收站项目(苏州LNG储备中心)(以下简称“本项目”)位于张家港市南丰镇、现代农业示范园区,占地约528亩,项目总投资约50亿元,建设规模为300万吨/年,其中气化外输量220万吨/年,液态外输量80万吨/年。本项目主要包括接收站工程、码头工程和配套外输管线。[6]

接收站工程:拟建设3座22万方全容式混凝土储罐及LNG接卸和储存、气化外输计量、槽车液态充装、BOG处理、消防等工艺及设施,设计接收能力300万吨/年。

码头工程:拟建设张家港港区东沙作业区盛泰码头下游至福山塘段的两个4万方LNG泊位及配套设施,水工结构兼顾5万吨级,远期最大可停靠8万方LNG船舶,占用长江岸线606m,设计吞吐量330万吨/年,其中接卸量为300万吨/年,出口30万吨/年。

配套外输管线:本项目配套外输管线共两路,其中拟建设一路10.0Mpa、DN1000,总长度约6.3公里,至七干河设分输站一座,出分输站后接入沿海管网或国家管网。[6]

Articles and resources

References

  1. "张家港海进江LNG接收站项目(苏州LNG储备中心)环境影响评价第二次公示 - 张家港市南丰镇". www.zjg.gov.cn. 2023-08-04.{{cite web}}: CS1 maint: url-status (link)
  2. 2.0 2.1 2.2 "江苏张家港海进江LNG接收站项目环评报告全文本公示-国际燃气网". gas.in-en.com. 2023-06-09.{{cite web}}: CS1 maint: url-status (link)
  3. "【聚焦】50亿!中石化布局苏州长江接收站!船型受限内河接收站困局咋破_来源:天然气行业观察(ID:Dr-natural-gas)". www.sohu.com. 2022-05-17.{{cite web}}: CS1 maint: url-status (link)
  4. "中石化张家港海进江LNG接收站项目合资公司成立(附股东结构)". chinalng.cc. 2022-05-17.{{cite web}}: CS1 maint: url-status (link)
  5. "2023年12月1日新华日报《永卓控股有限公司提升发展"含新量""含绿量""含金量" 搏击新型工业化浪潮》--来源:新华日报". www.zjgonline.com.cn. 2023-12-01.{{cite web}}: CS1 maint: url-status (link)
  6. 6.0 6.1 6.2 "张家港海进江LNG接收站项目(苏州LNG储备中心)环境影响评价信息首次公开 - 张家港市南丰镇". www.zjg.gov.cn. 2022-04-07.{{cite web}}: CS1 maint: url-status (link)