Zhangping power station (华电漳平发电厂) is an operating power station of at least 600-megawatts (MW) in Jingcheng, Zhangping, Longyan, Fujian, China with multiple units, some of which are not currently operating.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Zhangping power station Jingcheng, Zhangping, Longyan, Fujian, China 25.28422, 117.39892 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Phase I Unit 3, Phase I Unit 4, Phase II Unit 5, Phase II Unit 6, Phase III Unit 7, Phase III Unit 8: 25.28422, 117.39892

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Phase I Unit 3 retired coal - anthracite 100 subcritical 1986 2009
Phase I Unit 4 retired coal - anthracite 100 subcritical 1987 2009
Phase II Unit 5 retired coal - anthracite 100 subcritical 1994 2009
Phase II Unit 6 retired coal - anthracite 100 subcritical 1994 2009
Phase III Unit 7 operating coal - anthracite 300 subcritical 2011
Phase III Unit 8 operating coal - anthracite 300 subcritical 2012

Table 3: Unit-level ownership and operator details

Unit name Owner
Phase I Unit 3 Fujian Huadian Zhangping Thermal Power Co Ltd [100.0%]
Phase I Unit 4 Fujian Huadian Zhangping Thermal Power Co Ltd [100.0%]
Phase II Unit 5 Fujian Huadian Zhangping Thermal Power Co Ltd [100.0%]
Phase II Unit 6 Fujian Huadian Zhangping Thermal Power Co Ltd [100.0%]
Phase III Unit 7 Fujian Huadian Zhangping Thermal Power Co Ltd [100.0%]
Phase III Unit 8 Fujian Huadian Zhangping Thermal Power Co Ltd [100.0%]

Project-level coal details

  • Permit(s): July 31, 2009

Background

Zhangping power station was founded in 1985. The first phase of 2 units with 100MW each were brought online in 1986 and 1987. The second phase was completed in 1994, adding two units with 100MW each to the power plant. The 4 units were shut down before 2008, to meet the requirement for developing additional 2 units. The unit 5 and 6, known as phase III, totaling 600 MW, received the permit for construction from NDRC in 2009, and were completed in 2011 and 2012. The plant is owned by China Huadian.[1][2][3] In 2017, the power station received the permit from Fujian Provincial DRC to upgrade the two 300MW units to CHP units, supplying heat to the Zhangping Industrial Park besides generating electricity. [4]