Zhejiang Ningbo LNG Terminal

From Global Energy Monitor
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor.
Sub-articles:

Zhejiang Ningbo LNG Terminal (中海油浙江宁波LNG接收站) is an LNG terminal in Baifeng Town, Beilun District, Ningbo Prefecture, Zhejiang, China.

Location

Loading map...

The undated satellite image shows the exact location of the Zhejiang Ningbo LNG terminal with phase I & II on the left and phase III on the right.

Project details

Phase 1

  • Owner: CNOOC Zhejiang Ningbo Lng Co., Ltd. 中海浙江宁波液化天然气有限公司[1]
  • Parent company: CNOOC Gas and Electricity Group Co., Ltd. 51%, Zhejiang Energy and Natural Gas Group Co., Ltd. 29%, Ningbo Development Investment Group Co., Ltd. 20%.
中海石油气电集团有限责任公司 51%
浙江能源天然气集团有限公司 29%
宁波开发投资集团有限公司 20%
  • Location: Beilun, Ningbo, Zhejiang, China
  • Coordinates: 29.893989, 122.091771 (exact)
  • Capacity: 3 mtpa[2]
  • Status: Operating
  • Type: Import
  • Start year: 2012

Phase 2

  • Owner: CNOOC Zhejiang Ningbo Lng Co., Ltd. 中海浙江宁波液化天然气有 限公司[1]
  • Parent company: CNOOC Gas and Electricity Group Co., Ltd. 51%, Zhejiang Energy and Natural Gas Group Co., Ltd. 29%, Ningbo Development Investment Group Co., Ltd. 20%.
中海石油气电集团有限责任公司 51%
浙江能源天然气集团有限公司 29%
宁波开发投资集团有限公司 20%
  • Location: Beilun, Ningbo, Zhejiang, China
  • Coordinates: 29.893989, 122.091771 (exact)
  • Capacity: 3 mtpa[3]
  • Status: Operating
  • Type: Import
  • Start year: 2020

Phase 3

  • Owner: CNOOC Green Energy Port Zhejiang Ningbo Energy Co., Ltd 中海油绿能港浙江宁波能源有限公司[4]
  • Parent company: CNOOC Gas and Electricity Group Co., Ltd. 40%, Zhejiang Energy and Natural Gas Group Co., Ltd. 40%, Ningbo Development Investment Group Co., Ltd. 20%.
中海石油气电集团有限责任公司 40%
浙江能源天然气集团有限公司 40%
宁波开发投资集团有限公司 20%
  • Location: Beilun, Ningbo, Zhejiang, China
  • Coordinates: 29.893989, 122.091771 (exact)
  • Capacity: 6 mtpa
  • Status: Construction
  • Type: Import
  • Start year: 2025

Background

Phase 1

Zhejiang Ningbo LNG Terminal is an LNG terminal in Zhejiang, China.[5]

Zhejiang Ningbo LNG Terminal Phase 1 began construction in December 2009,[6] and was commissioned in 2012 with LNG imported from Qatar. This phase included three 160,000 cubic meter tanks and a receiving capacity of 3 mtpa.[7][8]

Phase 2

Phase 2 began construction in June 2018. The proposed operating date was 2020, and the capacity would be an additional 3 mtpa.[9]

The first storage tank of Phase 2 went operation in November 30, 2020, receiving the first load of imported LNG.[10]

Phase 3

Phase 3 was listed in 2021 in Zhejiang Province's 14th Five-Year Plan for coal, oil and nutural gas.[11][12][13] A new sponsor company for phase 3 was formed in May 2022. [14] Its EIA report was approved by Ningbo Environmental Protection Bureau in June 2022.[15]

The construction of phase II began in 2022 and by November 2023, the foundation construction has been completed.[16]Phase III will build six 270,000 -cubic-meter storage tanks, adding 6 mtpa of capacity to the existing LNG terminal. The completion date is set in 2025. [17]

Articles and resources

References

  1. 1.0 1.1 "中海浙江宁波液化天然气有限公司". www.qcc.com.{{cite web}}: CS1 maint: url-status (link)
  2. "中海油浙江LNG日供气1100万方---本报记者 吴莉《 中国能源报 》(第 15 版)". paper.people.com.cn. 2013-08-12.{{cite web}}: CS1 maint: url-status (link)
  3. "全省最大液化天然气接收站扩容--浙江在线". mepaper.zjol.com.cn. 2018-06-28.{{cite web}}: CS1 maint: url-status (link)
  4. "中海油绿能港浙江宁波能源有限公司2023年招聘简章-高校人才网". www.gaoxiaojob.com. 2023-11-27.{{cite web}}: CS1 maint: url-status (link)
  5. Zhejiang Ningbo LNG Terminal, A Barrel Full, accessed April 2017
  6. "浙江LNG项目接收站和港口工程开工建设-LNG,接收站,白峰镇,港口工程,开工典礼,液化天然气-中国宁波网-新闻中心". news.cnnb.com.cn. 2009-12-21.{{cite web}}: CS1 maint: url-status (link)
  7. CNOOC's Zhejiang Ningbo LNG terminal gets Qatari commissioning cargo, Platts, September 24, 2017
  8. "浙江LNG接收站成功接卸第100船液化天然气"people.cn, 2017-4-18
  9. Expansion of the largest LNG receiving station in Zhejiang, CNE Energy, April 16, 2019
  10. 中海浙江LNG接收站二期项目首座储罐顺利投用 Sohu News, 12-03-2020
  11. "省发展改革委 省能源局关于印发《浙江省煤炭石油天然气发展"十四五"规划》的通知". www.ningbo.gov.cn. Retrieved 2022-06-28.
  12. "2021年浙江省LNG接收站市场现状及发展前景分析 2025年全省接收能力达3000万吨以上_行业研究报告 - 前瞻网". www.qianzhan.com. Retrieved 2022-06-28.
  13. "2021年浙江省LNG接收站市场现状及发展前景分析 2025年全省接收能力达3000万吨以上_行业研究报告 - 前瞻网". www.qianzhan.com. Retrieved 2022-06-28.
  14. "中海油绿能港浙江宁波能源有限公司重组落地----中海石油气电集团有限责任公司 基层动态". webcache.googleusercontent.com. 2022-06-10.{{cite web}}: CS1 maint: url-status (link)
  15. "关于中海油绿能港浙江宁波能源有限公司浙江LNG三期项目接收站工程环境影响报告书的批复". www.bl.gov.cn. 2022-06-16.{{cite web}}: CS1 maint: url-status (link)
  16. "宁波"绿能港"三期建设加速跑,千万吨级LNG储运基地呼之欲出!--来源:潮新闻". zjnews.zjol.com.cn. 2023-11-14.{{cite web}}: CS1 maint: url-status (link)
  17. "千万吨级储运基地,宁波"绿能港"谋哪条新路? - 国际在线移动版--来源:潮新闻". news.cri.cn. 2023-11-22.{{cite web}}: CS1 maint: url-status (link)

Related GEM.wiki articles

External resources

External articles