Zhuhai LNG Terminal
Part of the Global Gas Infrastructure Tracker, a Global Energy Monitor project. |
Related categories: |
Zhuhai LNG Terminal (珠海LNG接收站, 珠海金湾LNG接收站) is a LNG terminal in Guangdong, China, with phases that are operating and under construction.
Location
Project Details
Phase 1
- Owner: Guangdong Zhuhai Golden Bay LNG Ltd. (广东珠海金湾液化天然气有限公司)[1]
- Parent company: CNOOC Gas and Electricity Group Co., Ltd. 30.00%, Guangzhou Development Gas Investment Co., Ltd. 25.00%, Guangdong Energy Group Natural Gas Co., Ltd. 25.00%, Guangdong Yue-Hong Kong Energy Development Co., Ltd. 8.00%, Jiangmen Urban Construction Group Co., Ltd. 3.00%, Zhuhai Special Economic Zone Electric Power Development Group Co., Ltd. 3.00%, Zhongshan Xingzhong Energy Development Co., Ltd. 3.00%, Foshan Huatuoneng Energy Investment Co., Ltd. 3.00%.
中海石油气电集团有限责任公司 | 30.00% |
广州发展燃气投资有限公司 | 25.00% |
广东能源集团天然气有限公司 | 25.00% |
广东粤港能源发展有限公司 | 8.00% |
江门市城建集团有限公司 | 3.00% |
珠海经济特区电力开发集团有限公司 | 3.00% |
中山兴中能源发展股份有限公司 | 3.00% |
佛山市华拓能能源投资有限公司 | 3.00% |
- Location: Gaolan Island, Zhuhai, Guangdong, China
- Coordinates: 21.90599, 113.219326 (exact)
- Capacity: 3.5 mtpa
- Status: Operating
- Type: Import
- Start year: 2013
Phase 2
- Owner: Guangdong Zhuhai Golden Bay LNG Ltd. (广东珠海金湾液化天然气有限公司)[1]
- Parent company: CNOOC Gas and Electricity Group Co., Ltd. 30.00%, Guangzhou Development Gas Investment Co., Ltd. 25.00%, Guangdong Energy Group Natural Gas Co., Ltd. 25.00%, Guangdong Yue-Hong Kong Energy Development Co., Ltd. 8.00%, Jiangmen Urban Construction Group Co., Ltd. 3.00%, Zhuhai Special Economic Zone Electric Power Development Group Co., Ltd. 3.00%, Zhongshan Xingzhong Energy Development Co., Ltd. 3.00%, Foshan Huatuoneng Energy Investment Co., Ltd. 3.00%.
- Location: Gaolan Island, Zhuhai, Guangdong, China
- Coordinates: 21.90599, 113.219326 (exact)
- Capacity: 3.5 mtpa
- Status: Construction
- Type: Import
- Start year: 2024[2]
- Originally 2023
Background
Zhuhai LNG Terminal is an LNG terminal in Guangdong, China.[3][4]
Phase I of the Zhuhai LNG Terminal began construction in October 2010,[5] and was completed in 2013 with three 160,000 cubic meter tanks and a receiving capacity of 3.5 mpta.[3] [6]The terminal will supply natural gas to the cities of Guangzhou, Foshan, Zhuhai, Zhongshan and Jiangmen.[7] A 3.5-mtpa Phase Two of the project was proposed.[8] In May 2020, Phase Two began the invitation to tender for the social stability risk assessment service, signaling the start of the second phase of the LNG terminal project.[9]
Phase 2 received permit for construction in May 2021.[10] It began construction in June 2021, including five storage tanks with 270,000 cubic meters each. The capacity of phase 2 is 3.5 mtpa.[11] The operating date was set at the end of 2023. By February 2023,[10] the construction is ongoing.[11]
金湾绿能港(珠海LNG)二期项目于2021年6月开工建设,同时建设5座27万立方米液化天然气储罐及配套设施;2024年建成投产后,金湾绿能港(珠海LNG)二期项目将成为华南地区规模最大的天然气储运基地,年处理能力可达700万吨,折合气态天然气约100亿立方米。按照1户居民每月用气30立方米计算,100亿立方米天然气大约可供近3000万户居民使用1年。[11]
As of September 2023, the construction is still ongoing, and a new start year was reported as 2024.[2]
As of December 2023, 81.6% of the construction has been completed according to the local media.[12]
- Owner: Guangdong Zhuhai Golden Bay LNG Ltd. (广东珠海金湾液化天然气有限公司)[1]
- Parent company: CNOOC Gas and Electricity Group Co., Ltd. 30.00%, Guangzhou Development Gas Investment Co., Ltd. 25.00%, Guangdong Energy Group Natural Gas Co., Ltd. 25.00%, Guangdong Yue-Hong Kong Energy Development Co., Ltd. 8.00%, Jiangmen Urban Construction Group Co., Ltd. 3.00%, Zhuhai Special Economic Zone Electric Power Development Group Co., Ltd. 3.00%, Zhongshan Xingzhong Energy Development Co., Ltd. 3.00%, Foshan Huatuoneng Energy Investment Co., Ltd. 3.00%.
中海石油气电集团有限责任公司 | 30.00% |
广州发展燃气投资有限公司 | 25.00% |
广东能源集团天然气有限公司 | 25.00% |
广东粤港能源发展有限公司 | 8.00% |
江门市城建集团有限公司 | 3.00% |
珠海经济特区电力开发集团有限公司 | 3.00% |
中山兴中能源发展股份有限公司 | 3.00% |
佛山市华拓能能源投资有限公司 | 3.00% |
The 2025 GIIGNL Annual Report classifies this expansion project as operating, but as of June 2025 there is no evidence of this, and we still consider them under construction.
Articles and resources
References
- ↑ 1.0 1.1 1.2 广东珠海金湾液化天然气有限公司 QCC.com
- ↑ 2.0 2.1 "https://www.argusmedia.com/en/news/2404382-viewpoint-china-poised-to-remain-lng-demand-centre".
{{cite web}}
: External link in
(help)CS1 maint: url-status (link)|title=
- ↑ 3.0 3.1 Zhuhai LNG Terminal, A Barrel Full, accessed April 2017
- ↑ 中国海油珠海LNG项目一期工程 广东珠海金湾液化天然气有限公司 China Association of Construction Enterprise Mangement website
- ↑ 中国海油珠海LNG项目一期工程开工 source: sasac.gov.cn. 文章来源:中国海洋石油总公司, 2010-10-22.
- ↑ "中海油珠海LNG成功接卸首船气-新闻-能源资讯-中国能源网-来源:中国海洋石油报". www.china5e.com. 2013-11-01.
{{cite web}}
: CS1 maint: url-status (link) - ↑ CNOOC delays commission of Zhuhai LNG terminal to late October, Ricki Wang, ICIS, September 2013
- ↑ 中海油珠海LNG接收站 Zhuhai Government website, 11-06-2020
- ↑ "广东珠海LNG扩建项目二期工程社会稳定性风险评估服务公开询价公告_OILUP油气淘". www.oilup.com. 2020-05-21. Retrieved 2021-03-31.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 10.0 10.1 "珠海LNG扩建项目二期工程获批 计划6月动工--深圳特区报--新浪网". k.sina.com.cn. 2021-05-10.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 11.0 11.1 11.2 "粤港澳大湾区首座27万立方米 LNG 储罐外罐主体结构完工 设计建造技术国际领先--"珠海金湾"微信公众号". www.jinwan.gov.cn. 2023-02-08.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "珠海金湾"绿能港"二期项目完成81% 预计2024年建成投产--凤凰网广东珠海". gd.ifeng.com. 2023-12-16.
{{cite web}}
: CS1 maint: url-status (link)