Zhunda power station (蒙能准大发电厂) is an operating power station of at least 600-megawatts (MW) in Ordos City, Junggar, Ordos, Inner Mongolia, China with multiple units, some of which are not currently operating. It is also known as 内蒙古能源集团准大电厂2×100万千瓦煤电一体化扩建项目 (Unit 3).

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Zhunda power station Ordos City, Junggar, Ordos, Inner Mongolia, China 39.784943, 111.159283 (exact)
Loading map...

Unit-level coordinates (WGS 84):

  • Phase II Unit 1, Phase II Unit 2, Unit 1, Unit 2: 39.784943, 111.159283

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Emergency/Backup
Phase II Unit 1 Construction[1] coal: unknown[2][3] 1000[2] ultra-supercritical[2] 2025 (planned)[2] False
Phase II Unit 2 Construction[1] coal: unknown[2][3] 1000[2] ultra-supercritical[2] 2025 (planned)[2] False
Unit 1 Operating coal: bituminous[3] 300 subcritical 2006 False
Unit 2 Operating coal: bituminous[3] 300 subcritical 2006 False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase II Unit 1 Zhundai No.2 Thermal Power Branch of Inner Mongolia Energy Group Co Ltd [100%][2] Inner Mongolia Energy Power Generation Investment Group Co Ltd [90.0%]; Inner Mongolia State Owned Capital Operation Co Ltd [10.0%]
Phase II Unit 2 Zhundai No.2 Thermal Power Branch of Inner Mongolia Energy Group Co Ltd [100%][2] Inner Mongolia Energy Power Generation Investment Group Co Ltd [90.0%]; Inner Mongolia State Owned Capital Operation Co Ltd [10.0%]
Unit 1 Inner Mongolia Energy Power Generation Zhundai Power Generation Co Ltd [100%] Inner Mongolia Energy Power Generation Investment Group Co Ltd [45.9%]; Huaihe Energy Holding Group Co Ltd [40.6%]; Inner Mongolia State Owned Capital Operation Co Ltd [5.1%]; unknown [4.3%]; China Cinda Asset Management Co Ltd [4.1%]
Unit 2 Inner Mongolia Energy Power Generation Zhundai Power Generation Co Ltd [100%] Inner Mongolia Energy Power Generation Investment Group Co Ltd [45.9%]; Huaihe Energy Holding Group Co Ltd [40.6%]; Inner Mongolia State Owned Capital Operation Co Ltd [5.1%]; unknown [4.3%]; China Cinda Asset Management Co Ltd [4.1%]

Project-level coal details

  • Coal source(s): domestic

Background

Zhunda power station is a two-unit coal-fired power plant with a total capacity of 600 MW. The plant was completed in 2006, and is owned by Inner Mongolia Asset Management Bureau.[4]

In 2022, based on tender bid numbers (e.g. HNZB2022-12-3-280), an additional 2 x 1,000 MW appeared under consideration at the site. The project reportedly started construction on March 18, 2023, and was scheduled to be put into operation by 2025.[5][6][7][8] Permitting details were unknown.

Construction of Phase II Unit 1 began in late 2023 with the first concrete pour and boiler steel hoisting.[9][10]

Throughout 2024 and 2025, the project progressed through major milestones, including turbine base, boiler, and cooling tower construction.[11][12] The main building and chimney structures were topped out in late 2024.[13] In 2025, the unit achieved first fire and a successful boiler water pressure test.[14]

Construction of Phase II Unit 2 progressed in 2024 and 2025, with the first boiler steel and cooling tower completed.[15][16] In 2026, the boiler water pressure test was completed.[17]

Articles and Resources

References

  1. ↑ 1.0 1.1 https://mp.weixin.qq.com/s/JtviU8fLbGW4sje4O2hNoQ. {{cite web}}: Missing or empty |title= (help)
  2. ↑ 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 https://news.bjx.com.cn/html/20240522/1378564.shtml. {{cite web}}: Missing or empty |title= (help)
  3. ↑ 3.0 3.1 3.2 3.3 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker. {{cite web}}: Missing or empty |title= (help)
  4. ↑ Zhunda Powerplant, Enipedia, accessed Sept. 2015.
  5. ↑ 内蒙古能源集团准大电厂2x100万千瓦煤电一体化扩建项目开工建设, ordos.gov.cn, 2023-03-22
  6. ↑ 【开标】火电|2×100万千瓦!内蒙古能源集团准大电厂煤电一体化扩建项目三大主机设备中标结果, Weixin, 2023-04-13
  7. ↑ 2×1000MW!内蒙古能源集团准大电厂煤电一体化扩建项目相关2项中标结果公示, BJX, 2023-04-14
  8. ↑ 金山热电厂2×100万千瓦煤电联营扩建、准大电厂2×100万千瓦煤电一体化扩建项目相关3项中标候选人, BJX, 2023-06-06
  9. ↑ "内蒙古能源集团准大电厂2×100万千瓦煤电一体化扩建项目1号锅炉基础浇筑". WeChat. 2023-10-28. Retrieved 2026-05-30.{{cite web}}: CS1 maint: url-status (link)
  10. ↑ "准大电厂2×100万千瓦煤电一体化扩建项目1号锅炉首根钢架结构顺利完成吊装". BeiJiXing (BJX) News. 2023-12-19. Retrieved 2026-05-30.{{cite web}}: CS1 maint: url-status (link)
  11. ↑ "准大电厂2×1000MW项目1号汽机基座底板大体积混凝土浇筑完成". BeiJiXing (BJX) News. 2024-04-22. Retrieved 2026-05-30.{{cite web}}: CS1 maint: url-status (link)
  12. ↑ "准大电厂2×100万千瓦煤电一体化扩建项目1号机组锅炉首根大板梁顺利吊装就位". WeChat. 2024-08-06. Retrieved 2026-05-30.{{cite web}}: CS1 maint: url-status (link)
  13. ↑ "准大电厂2×100万千瓦煤电一体化扩建项目1号机组主厂房结构和烟囱结构先后顺利封顶". BeiJiXing (BJX) News. 2024-11-12. Retrieved 2026-05-30.{{cite web}}: CS1 maint: url-status (link)
  14. ↑ "准大电厂2×100万千瓦煤电一体化扩建项目1号锅炉水压试验一次成功". WeChat. 2025-09-14. Retrieved 2026-05-30.{{cite web}}: CS1 maint: url-status (link)
  15. ↑ "内蒙古能源集团准大电厂2×100万千瓦煤电一体化扩建项目2号机组锅炉钢架吊装圆满完成". WeChat. 2024-03-25. Retrieved 2026-05-30.{{cite web}}: CS1 maint: url-status (link)
  16. ↑ "蒙能准大电厂2×100万千瓦煤电一体化扩建项目2号间冷塔顺利到顶". WeChat. 2025-07-10. Retrieved 2026-05-30.{{cite web}}: CS1 maint: url-status (link)
  17. ↑ "电建集团承建的内蒙古能源集团准大电厂2×100万千瓦煤电一体化扩建项目2号机组锅炉整体水压试验一次成功". WeChat. 2026-06-09. Retrieved 2026-07-03.{{cite web}}: CS1 maint: url-status (link)