Aceros Arequipa Pisco steel plant
This article is part of the Global Steel Plant Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Aceros Arequipa Pisco steel plant (Planta siderúrgica de Pisco (Spanish)) is a 850 thousand tonnes per annum (TTPA) direct reduced iron (DRI) and electric arc furnace (EAF) idled steel plant in Pisco, Ica, Peru.
Location
The map below shows the location of the steel plant in Pisco, Ica, Peru.
- Location: Carretera Panamericana Sur Km 241. Paracas. Pisco - Ica, Peru[1]
- Coordinates (WGS 84): -13.788622, -76.168172 (exact)
Background
Founded in 1964, Aceros Arequipa is Peru's largest steel maker. The company began producing finished steel products for the Peruvian market in 1966 with the opening of its new rolling mill in the city of Arequipa.[2] A second lamination facility was launched in Pisco in 1983, and the company began producing its own crude steel in 1987 following a merger with Laminadora del Pacífico.[2] In 1996, DRI operations were added at the Pisco plant, and a year later the company incorporated itself as Aceros Arequipa S.A. following the acquisition of another competitor, Aceros Calibrados S.A.[2] In 2015, Aceros Arequipa consolidated its position as Peru's market leader with the opening of a second rolling mill at Pisco.[2] A year later, the company shut down its original plant in Arequipa, signaling its intention to concentrate future operations at the Pisco location.[3]
2021 capacity expansion
In July 2021, Aceros Arequipa Pisco raised its steel production capacity from 850 ttpa (thousand tonnes per annum) to 2.1 million tpa with the inauguration of a new SMS electric arc furnace.[2][4] As of early 2022, the plant's older Danieli EAF had been deactivated and remained on standby pending an increase in domestic or international steel demand.[5]
Plant Details
Table 1: General Plant Details
Plant status | Start date | Closed date | Workforce size |
---|---|---|---|
mothballed[6][1] | 1987[7] | 2022[8] | 1060[8] |
Table 2: Ownership and Parent Company Information
Parent company | Parent company PermID | Owner | Owner company PermID |
---|---|---|---|
Corporacion Aceros Arequipa SA [100%][9][10][11] | 4295886029 [100%] | Corporacion Aceros Arequipa SA[12][13][14] | 4295886029 |
Table 3: Process and Products
Steel product category | Steel products | Steel sector end users | ISO 14001 | Main production equipment | Detailed production equipment |
---|---|---|---|---|---|
finished rolled[13] | corrugated bars, structures, wire rods, angles, U channels plates, tees, square bars, round bars, helical rounds[13] | building and infrastructure; tools and machinery; transport[15] | 2022[16] | direct reduced iron (DRI) and electric arc furnace (EAF)[17][8][13] | 1 Danieli EAF (80-tonne, 2004); 2 SIIL rotary kiln DRI plants (1996)[18][1][19][20][13] |
Table 4: Crude Steel Production Capacities (thousand tonnes per annum):
Electric arc furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|
850 TTPA[21][22][12][8][14] | 850 TTPA[21][22][23][12][8][6][14] |
Table 5: Crude Iron Production Capacities (thousand tonnes per annum):
Sponge iron/DRI capacity | Nominal iron capacity (total) |
---|---|
80 TTPA[17] | 80 TTPA |
Table 6: Actual Crude Steel Production by Year (thousand tonnes per annum):
Year | BOF Production | EAF Production | OHF Production | Total (all routes) |
---|---|---|---|---|
2020 | – | 388 TTPA | – | 388 TTPA[24][12] |
2021 | – | 850 TTPA[25] | – | 850 TTPA[25] |
Articles and Resources
References
- ↑ 1.0 1.1 1.2 https://web.archive.org/web/20220112204403/https://www.acerosarequipa.com/conocenos. Archived from the original on 2022-01-12.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.0 2.1 2.2 2.3 2.4 Conócenos, Aceros Arequipa, Retrieved on: 2022-02-09
- ↑ "Aceros Arequipa cierra su planta en Arequipa y concentra sus operaciones en Pisco". Gato Encerrado. July 25, 2016.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Primera colada en la nueva acería de Aceros Arequipa". Energiminas. July 26, 2021.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Memoria Anual 2020 (pp 24, 47 & 67)" (PDF). Aceros Arequipa. February 2021.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 6.0 6.1 (PDF) https://investors.acerosarequipa.com/storage/memoriasintegradas/April2022/NOzbrfRtKEmp84DjfqmJ.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220318144951/https://www.acerosarequipa.com/en/conocenos. Archived from the original on 2022-03-18.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 8.0 8.1 8.2 8.3 8.4 (PDF) https://www.smv.gob.pe/ConsultasP8/temp/Memoria%20Integrada%20CAASA%202021.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220318224306/https://www.gatoencerrado.net/store/noticias/57/57689/detalle.htm. Archived from the original on 2022-03-18.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220318140444/https://www.gatoencerrado.net/store/noticias/99/99726/detalle.htm. Archived from the original on 2022-03-18.
{{cite web}}
: Missing or empty|title=
(help) - ↑ (PDF) https://web.archive.org/web/20220319101833/https://investors.acerosarequipa.com/storage/memorias/July2020/qNzo7znc6Bm30m8ev3J6.pdf. Archived from the original (PDF) on 2022-03-19.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 12.0 12.1 12.2 12.3 (PDF) https://web.archive.org/web/20220319005436/https://investors.acerosarequipa.com/storage/memorias/March2021/uth9Ucr0uLTxOJMjeVYl.pdf. Archived from the original (PDF) on 2022-03-19.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 13.0 13.1 13.2 13.3 13.4 https://web.archive.org/web/20220120111219/https://www.acerosarequipa.com/procesos-de-produccion. Archived from the original on 2022-01-20.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 14.0 14.1 14.2 (PDF) https://web.archive.org/web/20210807133859/http://www.oecd.org/industry/ind/latest-developments-in-steelmaking-capacity-2020.pdf. Archived from the original (PDF) on 2021-08-07.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220308140609/https://www.acerosarequipa.com/. Archived from the original on 2022-03-08.
{{cite web}}
: Missing or empty|title=
(help) - ↑ (PDF) https://www.acerosarequipa.com/sites/default/files/certificaciones/2022-11/57220Certificate29AGO2022page0001%202%20files%20merged.pdf?fv=KGyBdnrm.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 17.0 17.1 (PDF) https://web.archive.org/web/20221008040524/https://www.midrex.com/wp-content/uploads/MidrexSTATSBook2021.pdf. Archived from the original (PDF) on 2022-10-08.
{{cite web}}
: Missing or empty|title=
(help) - ↑ (PDF) https://web.archive.org/web/20220320142013/https://dspace.unitru.edu.pe/bitstream/handle/UNITRU/3422/ChambergoVargas_J.pdf?sequence. Archived from the original (PDF) on 2022-03-20.
{{cite web}}
: Missing or empty|title=
(help) - ↑ (PDF) https://web.archive.org/web/20211129195124/https://www.midrex.com/wp-content/uploads/Midrex-STATSbookprint-2020.Final_.pdf. Archived from the original (PDF) on 2021-11-29.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2022 AIST Electric Arc Furnace Roundup
- ↑ 21.0 21.1 (PDF) https://web.archive.org/web/20220320143237/https://repositorio.up.edu.pe/bitstream/handle/11354/2828/CastilloJhofeth_Tesis_maestria_2020.pdf?sequence. Archived from the original (PDF) on 2022-03-20.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 22.0 22.1 (PDF) https://web.archive.org/web/20220319103937/https://investors.acerosarequipa.com/storage/presentacion-inversionistas/November2019/Swez8xqEXnZtQvQzM7a7.pdf. Archived from the original (PDF) on 2022-03-19.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20220319015653/https://energiminas.com/primera-colada-en-la-nueva-aceria-de-aceros-arequipa. Archived from the original on 2022-03-19.
{{cite web}}
: Missing or empty|title=
(help) - ↑ (PDF) https://web.archive.org/web/20210810153606/https://www.alacero.org/sites/default/files/publicacion/america_latina_en_cifras_2020_es-en_09nov.pdf. Archived from the original (PDF) on 2021-08-10.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 25.0 25.1 (PDF) https://web.archive.org/web/20220621081540/https://investors.acerosarequipa.com/storage/memoriasintegradas/May2022/oMrjpG0K6GsRPXezQMN3.pdf. Archived from the original (PDF) on 2022-06-21.
{{cite web}}
: Missing or empty|title=
(help)