Amasra B Coal Mine is an operating coal mine in Amasra, Bartin, Türkiye.

Location

Table 1: Project-level location details

Mine Name Location Coordinates (WGS 84)
Amasra B Coal Mine Amasra, Bartin, Türkiye[1] 41.721848, 32.349063 (approximate)

The map below shows the approximate location of the coal mine:

Loading map...

Project Details

Table 2: Project status

Status Status Detail Opening Year Closing Year
Operating[2]

Table 3: Operation details

Note: The asterisk (*) signifies that the value is a GEM estimated figure.
Capacity (Mtpa) Production (Mtpa) Year of Production Mine Type Mining Method Mine Size (km2) Mine Depth (m) Workforce Size
6 1.6[2] 2025[2] Underground[3] Longwall[3] 494.0* 650.0[2]

Table 4: Coal resources and destination

Total Reserves (Mt) Year of Total Reserves Recorded Total Resources (Mt) Coalfield Coal Type Coal Grade Primary Consumer/ Destination
549.0[4] 2024[4] Lignite Thermal Coal Plant

Table 5: Ownership and parent company

Note: To access more comprehensive data on energy ownership, please visit the Global Energy Ownership Tracker.
Owner Parent Company Headquarters
Hema Enerji[2] Hattat Holding AŞ Turkey

Note: The above sections were automatically generated and are based on data from the Global Coal Mine Tracker May 2026 release.

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

The Amasra B coal mine is a proposed opencast mine, by Hema Enerji, a subsidiary of Hattat Holdings Energy Group, producing 10 million tonnes per annum, near Amasra, Bartin, Turkey. The mine would power the HEMA Amasra power station.[5]

As of 2021, the HEMA power station that if would fuel is cancelled. The mine project is likewise presumed cancelled. The Amasra B coal mine is operated by Hema Enerji, a subsidiary of Hattat Holdings Energy Group. The project has been subject to a significant amount of local controversy.

  • Owner: Hema Enerji
  • Parent company: Hattat Holdings Energy Group
  • Location: Amasra, Bartin, Turkey[5]
  • GPS coordinates:41.721848, 32.349063 (approximate)[5]
  • Mine status: proposed[5]
  • Start year:
  • Mineable reserves: 56MT[5]
  • Coal type: hard coal
  • Mine size:
  • Mine type: surface
  • Production: 10 MTPA[5]

Articles and Resources

Additional data

To access additional data, including an interactive map of world coal mines, a downloadable dataset, and summary data, please visit the Global Coal Mine Tracker on the Global Energy Monitor website.

References

  1. "Hakkımızda - Türkiye Taşkömürü Kurumu". www.taskomuru.gov.tr. Archived from the original on 2024-04-09. Retrieved 2024-06-14.
  2. 2.0 2.1 2.2 2.3 2.4 https://www.sozcu.com.tr/ttk-nin-kapanmasi-hatta-a-yaradi-p295915. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 https://www.hemaenerji.com/amasra-tas-komuru-projesi/proje-hakkinda. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 https://www.taskomuru.gov.tr/ttk/2024-yili-faaliyet-raporu/. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 5.2 5.3 5.4 5.5 Bank Track, Amasra coal mine and power plant, March 13, 2017