Bac Lieu LNG Terminal is a proposed LNG import terminal in Vietnam.

Location

Table 1: Location details

Name Location Coordinates (WGS 84)
Bac Lieu LNG Terminal Hoa Binh, Bac Lieu, Vietnam[1] 9.294, 105.7216 (approximate)

The map below shows the approximate location of the terminal:

Loading map...

Project Details

Table 2: Infrastructure details

mtpa = million tonnes per year
Name Facility type Status Capacity Total terminal capacity Offshore Associated infrastructure
Bac Lieu LNG Terminal import[1] proposed[1][2] 2 mtpa[1] 2.0 mtpa False Bac Lieu Project Power Station[2]

Table 3: Cost

Name Facility type Cost Total known terminal costs
Bac Lieu LNG Terminal import[1] – –

Financing

No financing data available.

Table 4: Project timeline

FID = Final Investment Decision, used by some developers to indicate a project will move forward
Name Facility type Status Proposal year FID year Construction year Operating year Inactive year
Bac Lieu LNG Terminal import[1] proposed[1][2] 2019[1][2] – 2024[3] 2027[1][4] –

Ownership

Table 5: Ownership

Name Facility type Status Owners Parent companies Operator
Bac Lieu LNG Terminal import[1] proposed[1][2] Bac Lieu LNG Power Company Ltd [100%][5] Delta Offshore Energy Pte Ltd [100.0%] –

Background

The project was announced in September 2019 as part of a development that will include the gas-fired 3,200-MW Bac Lieu Project power station.[6]

Delta Offshore LNG (DeltaOE) is developing the Bac Lieu LNG-to-power project, which consists of a 2 MTPA floating LNG import terminal and a 3.2 GW combined-cycle power plant in the Mekong Delta, Bac Lieu, Vietnam.[7]

As of May 2023, the project was targeting 2024 for the start of construction.[8]

In August 2023, The Investor reported that the project was facing bottlenecks, including "a power purchase agreement that has not been finalized after several negotiation rounds and government guarantees for the project."[9]

The Bac Lieu LNG power project was listed in an Appendix of an amendment to Vietnam's eighth Power Development Plan (PDP8), released in April 2025, indicating the project is still actively in development, with a range of possible start years between 2025 and 2030.[10]

On March 10, 2026, Bac Lieu LNG Power Company (Delta Offshore Energy) and Vietnam's National Power Transmission Corporation (EVNNPT) signed the principal agreement on grid connection for the 3,200 MW Bac Lieu LNG-to-power project, covering evacuation via a 500 kV Bac Lieu-Thot Not line. Phased commercial operation is targeted for 2030 (Unit 1 March, Unit 2 June, Unit 3 September, Unit 4 December). The project, Vietnam's first fully privately financed integrated LNG-to-power scheme, remains pre-FID; construction, once planned for 2024, has not begun.[11][12]

Articles and Resources

Additional data

To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.

References

  1. ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 https://www.nsenergybusiness.com/projects/bac-lieu-lng-to-power-project/. {{cite web}}: Missing or empty |title= (help)
  2. ↑ 2.0 2.1 2.2 2.3 2.4 https://www.lnglimited.com.au/site/PDF/6306_1/LNGLDeltaOffshoreEnergyAgreeonSupplyDealtoVietnam. {{cite web}}: Missing or empty |title= (help)
  3. ↑ https://lngprime.com/lng-terminals/delta-plans-to-start-building-bac-lieu-lng-to-power-project-in-2024/82503/. {{cite web}}: Missing or empty |title= (help)
  4. ↑ https://theinvestor.vn/bac-lieu-province-proposes-solutions-for-problems-facing-4-bln-lng-to-power-project-d6144.html. {{cite web}}: Missing or empty |title= (help)
  5. ↑ https://web.archive.org/web/20221002194217/https://baclieulng.com/. Archived from the original on 2022-10-02. {{cite web}}: Missing or empty |title= (help)
  6. ↑ LNGL, DELTA OFFSHORE ENERGY AGREE ON SUPPLY DEAL TO VIETNAM, LNG Limited, Sep. 16, 2019
  7. ↑ GIIGNL. The LNG Industry: GIIGNL Annual Report 2021. Accessed July 21, 2026.
  8. ↑ Staff, LNG Prime (2023-05-26). "Delta plans to start building Bac Lieu LNG-to-power project in 2024". LNG Prime. Retrieved 2024-07-16.
  9. ↑ theinvestor.vn. "Bac Lieu province proposes solutions for problems facing $4 bln LNG-to-power project". theinvestor.vn. Retrieved 2024-07-16.
  10. ↑ https://vepg.vn/wp-content/uploads/2025/06/768_QD-TTg_658055.pdf
  11. ↑ "https://lngprime.com/asia/deltas-bac-lieu-lng-inks-grid-connection-deal/180775/". {{cite web}}: External link in |title= (help)CS1 maint: url-status (link)
  12. ↑ "EVNNPT And Bac Lieu LNG Power Company Limited Sign Principle Grid Connection Agreement For  3,200 MW Bac Lieu LNG-to-Power Plant In Vietnam - Delta Offshore Energy". deltaoffshoreenergy.com. Retrieved 2026-07-08. {{cite web}}: no-break space character in |title= at position 91 (help)