Connecting Pipeline Between Ordos-Anping-Cangzhou Gas Pipeline and Beijing-Shijianzhuang-Handan gas pipeline ( 鄂安沧输气管道与京邯输气管道连接线) is an operating natural gas pipeline in Hebei province, China.[1]

Location

The trunk pipeline runs from Guantao Distribution Station of Ordos-Anping-Cangzhou Gas Pipeline, Guantao County, Handan, to Handan Terminal Station of Beijing–Shijiazhuang–Handan Gas Pipeline, Economic and Technological Development Zone, Handan.[2]

Project Details

  • Owner: Hebei NATURAL Gas Company Limited[2]
  • Parent Company:
  • Current Capacity: 5 bcm/year(the trunk line); 2.5 bcm/year(the branch line)[2]
  • Length: 86.4 km(the trunk line); 28.9 km(the branch line)[2]
  • Diameter:1016 mm(the trunk line)[1]
  • Status: Operating[1]
  • Start Year: 2021[1]
  • Cost: 1224.5611 million RMB[2]

Background

The pipeline has 3 stations, 4 valve chambers, and 2 stations for reconstruction. The pipeline has realized interconnection with national pipelines, opened up the southernmost high-pressure gas pipeline in Hebei, greatly improved the gas supply pattern of the Beijing-Handan Gas Pipeline.[1]