Dumri Coal Mine

From Global Energy Monitor
This article is part of the
Global Coal Mine Tracker, a project of Global Energy Monitor.
Download full dataset
Report an error
Sub-articles:
Related-articles:

Dumri Coal Mine is a proposed coal mine in Chatti Bariatu, Hazaribagh, Jharkhand, India.

Location

Table 1: Project-level location details

Mine Name Location Coordinates (WGS 84)
Dumri Coal Mine Chatti Bariatu, Hazaribagh, Jharkhand, India 23.902661, 85.052562 (approximate)

The map below shows the approximate location of the coal mine:

Loading map...

Project Details

Table 2: Project status

Status Status Detail Project Type Opening Year Closing Year
Proposed[1] Permitted New 2027 (planned)[1] –

Table 3: Operation details

Note: The asterisk (*) signifies that the value is a GEM estimated figure.
Capacity (Mtpa) Production (Mtpa) Year of Production Mine Type Mining Method Mine Size (km2) Mine Depth (m) Workforce Size
0.9 – – Surface Open Pit – 50* –

Table 4: Coal resources and destination

Total Reserves (Mt) Year of Total Reserves Recorded Total Resources (Mt) Coalfield Coal Type Coal Grade Primary Consumer/ Destination
40.8 – 46 North Karanpura Lignite Thermal –

Table 5: Ownership and parent company

Note: To access more comprehensive data on energy ownership, please visit the Global Energy Ownership Tracker.
Owner Parent Company Headquarters
SM Steels and Power Ltd [100.0%][1] Aditya Birla Group India

Note: The above sections were automatically generated and are based on data from the Global Coal Mine Tracker August 2026 release.

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background on Mine

The mine was allotted jointly to Nilachal Iron & Power Ltd. for the company’s sponge iron plant and for M/s Bajrang Ispat Pvt. Ltd. The Project received the environment clearance on 23 December 2010. The Project involves R&R of 1737 PAPs and 534 PAFs consisting of land and homestead losers of 5 villages – Pagar (68 PAPs), Balia (74 PAPs),Tunda, Pandu (1435 PAPs), Chati-Bariatu (160 PAPs). Life of the mine at the rated capacity of 1 MTPA is 44 years. Public Hearing for the project was held on 7 September 2009.[2]. However, the mine was cancelled by Supreme Court in wake of the coalgate scam and further reallotted to HINDALCO Industries Limited by Ministry of Coal on 22 April 2015 and environment Clearance transferred on 28 October 2016.[3] As of today, the mine is still at the stage of getting various clearances.[4]

The mine was expected to become operational in March 2019, but it is unclear if it did so.[5]

Expansion Details

  • Status:
  • Size of Expansion:
  • Permits and Applications:

Articles and Resources

Additional data

To access additional data, including an interactive map of world coal mines, a downloadable dataset, and summary data, please visit the Global Coal Mine Tracker on the Global Energy Monitor website.

References

  1. ↑ 1.0 1.1 1.2 (PDF) https://coal.gov.in/sites/default/files/2023-06/MoM-09042025.pdf. {{cite web}}: Missing or empty |title= (help)
  2. ↑ Environemnt Clearance for Dumri Coal Mine, MoEF&CC India, 23 December 2010
  3. ↑ Environment Clearance Transfer to HINDALCO Industries Limited, MoEF&CC India, 28 October 2016
  4. ↑ Excerpts from the Chairman, Mr. Kumar Mangalam Birla’s address to shareholders at the 59th Annual General Meeting, 21 September 2018
  5. ↑ Dumri Captive Mine to be Operational by March 2019, Projects Today, September 28, 2018