Ennore SEZ Super Critical Thermal Power Project (Vayalur)

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Ennore SEZ Super Critical Thermal Power Project (Vayalur) is a power station under construction in Vayalur, Ponneri, Thiruvallur, Tamil Nadu, India.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Ennore SEZ Super Critical Thermal Power Project (Vayalur) Vayalur, Ponneri, Thiruvallur, Tamil Nadu, India 13.291667, 80.309722 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: 13.291667, 80.309722

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 1 construction coal - unknown 660 supercritical 2025
Unit 2 construction coal - unknown 660 supercritical 2025

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 Tamil Nadu Generation and Distribution Co Ltd (TANGEDCO) [100.0%]
Unit 2 Tamil Nadu Generation and Distribution Co Ltd (TANGEDCO) [100.0%]

Project-level coal details

  • Coal source(s): Indonesia
  • Permit(s): January 7, 2014 – Environmental Clearance; Extensions: 2019, 2020; Tamil Nadu clearances; NGT Committee Report 2021

Background

TANGEDCO has proposed to build two supercritical 800MW units on a reclaimed ash disposal area of the North Chennai Thermal Power Station. The plant is proposed to be built on 500 acres of land owned by the Tamil Nadu Electricity Board near the village of Vayalur, Tiruvallur district, Tamil Nadu, India.[1][2]

The project received environmental clearance for a 2 x 800 MW coal plant in 2014.[3] The capacity of each unit was, however, reduced to 660MW while calling engineering, construction, and procurement (EPC) tenders for the project in the same year.[4]

According to the India government (March 2016), the project was under construction with a planned commissioning of 2018-2019. The EPC contract was awarded to Bharat Heavy Electricals (BHEL).[5]

In December 2016 the India government reported that work at the site was held up from October 2015 onwards due to a court case filed against TANGEDCO by one of the EPC bidders. On October 18, 2016, the court ruled in favor of TANGEDCO and work on the site reportedly resumed on November 2, 2016.[6]

Planet satellite photos show construction did not substantially begin until June 2018, and then advanced through October 2018.

In 2019, TANGEDCO got a two year extension from the government to finish construction of two slow-moving thermal power plants at Ennore with a combined capacity of 1,980 MW. [7] In 2020, a second extension was granted for the project until 2024.[8]

According to the government's Broad Status Report in October 2020, the power station was planned for commissioning in 2022.[9] By November 2021, the date was pushed back to 2023.[10] By 2022, it was delayed to 2024.[11][12]

In the May 2023 Broad Status Report, the power plant was estimated to be commissioned in 2025.[13] While the report did not include the Ennore SEZ power plant in its list of "on hold" power projects, it appeared that the last active construction work on the project had taken place in 2021, with the next construction steps to resume in 2024. The following were listed as critical issues to the power plant's further progress:

  • " Slow progress in civil works of CWP , Fire Protection, CHP,AHP (non performance by contractor, hence re-tendering of some package )
  • Delay in readiness of Chimney due to delay in supply of borosilicate lining materials.
  • Inadequate manpower of BHEL at site
  • External Conveyor package work held up due to NGT issues
  • FGD work is yet to be awarded." [13]


In October 2023, TANGEDCO sought an amendment to their Environmental Clearance for "a revised route alignment of seawater pipelines and coal pipe conveyance system."[14] Later that month, the recently reconstituted EAC returned the proposed amendment in its 'present form' due to construction violations committed without prior EAC approval.[15] Further details of the construction violations and proceedings are available below (See: Violations, opposition & permitting developments).

Violations, opposition & permitting developments

A suo moto case (No.162/2021) was registered by the National Green Tribunal against various projects including the Ennore SEZ project based on news published in Times of India dated July 1, 2021.[16][17] The NGT (Southern Zone, Chennai) constituted a committee and instructed it to look into the issues and submit a report. Accordingly, the NGT Committee recommended that "TANGEDCO shall resume the activities pertaining to NCTPS Stage-III and Ennore SEZ power plants within [Coastal Regulation Zone (CRZ)] area in Kosasthalaiyar River/Buckingham Canal/Backwaters only after obtaining amendment to the existing CRZ clearance from MoEF&CC."[18][19]

In April 2022, an Op-Ed made the case that with two power plants under construction and two in the pre-licensing stage, the predominantly working class Ennore-Manali industrial area remains a site of structural environmental and social discrimination.[20]

According to reporting from September 2023, amid local opposition, TANGEDCO had allotted nearly Rs 18 crore to carry out various infrastructure projects in the thirteen local panchayats around the power station.[21]

EC issues following violations (2023)

As detailed in the October 2023 Meeting Minutes of the Expert Appraisal Committee, an application by TANGEDCO for amendments to the Ennore SEZ power station's EC had been returned due to the company's years-long violations of its existing EC.[15] According to the EAC deliberations, the owners had "changed seawater pipelines and coal pipe conveyance system without obtaining necessary clearance/ amendments from the Ministry and started construction since 2017 [sic]."[15] The construction violations had previously been brought before the NGT in 2021, after which the owners were instructed to obtain new EC for the change in construction plans. In the October 2023 EAC meeting, the committee instructed TANGEDCO to submit a new Terms of Reference for the project under the 'violations category.'[15]

Financing

It was reported in 2019 that the Power Finance Corporation is funding the project, at an estimated total investment of Rs98bn (£1.07bn).[22] As of December 2020, 55% of financing had been secured.[23]

Coal supply

TANGEDCO has stated that coal for the project would be 30% imported coal and 70% domestic through Ennore Port.[1] TANGEDCO states that the project would require 5.46 million tonnes per annum of coal. TANGEDCO proposes that 3.82 million tonnes per annum be sourced from the Kalinga Block, Talcher, Mahanadhi and IB Valley and 1.64 million tonnes per annum from unspecified overseas sources.[24]

The 2014 environmental clearance stated coal for the power station would be imported.[25]

In January 2022, with Ennore SEZ and other coal projects set to take off with a generating capacity of 5,700 MW, Tangedco bid for two coal blocks – Meenakshi coal block in IB Valley and Bankhui coal block in Talcher – to meet the growing needs of the state.[26]

Articles and Resources

References

  1. 1.0 1.1 Tamil Nadu Pollution Control Board, "Proceedings of the Public meeting held on February 23, 2011,", Tamil Nadu Pollution Control Board website, June 2011.
  2. "Ennore SEZ STPP (2x660 MW)," TANGEDCO website, accessed Sep 2015
  3. Environmental clearance, India MoEF, Jan 7, 2014.
  4. "Ennore SEZ Supercritical Thermal Power Project - NS Energy". NS Energy. Retrieved 2021-01-05.{{cite web}}: CS1 maint: url-status (link)
  5. "Monthly Report on Broad Status of Thermal Power Projects in the Country," Government of India Ministry of Power, March 2016
  6. "MONTHLY REPORT ON BROAD STATUS OF THERMAL POWER PROJECTS IN THE COUNTRY," Ministry of Power, December 2016.
  7. "TANGEDCO gets reprieve for two power projects at Ennore," The New Indian Express, April 15, 2019
  8. "Tangedco gets another extension till 2024 to commission Ennore SEZ thermal power plant," The New Indian Express, December 7, 2020
  9. Broad Status of Thermal Power Plants, India Central Electricity Authority, October 2020
  10. “Broad Status Report,” Thermal Project Monitoring Division, Central Electricity Authority, November 2021
  11. “Broad Status Report of Under Construction Thermal Power Projects,” Central Electricity Authority, May 2022
  12. “Broad Status Report of Under Construction Thermal Power Projects,” India Central Electricity Authority, November 2022
  13. 13.0 13.1 Broad Status Report of Under Construction Thermal Power Projects, Central Electricity Authority, Government of India, May 2023
  14. "Agenda for 01st Meeting of the Re-Constituted Expert Appraisal Committee (EAC)," India Ministry of Environment, Forest and Climate Change, October 4, 2023
  15. 15.0 15.1 15.2 15.3 Minutes of 01st Meeting of the Re-Constituted Expert Appraisal Committee (EAC) meeting; Thermal Projects held from 16/10/2023 to 16/10/2023, MoEFCC, Oct. 31, 2023
  16. Presumed to be "Chennai: Another pipeline leak at Ennore power plant," Times of India, July 1, 2021
  17. "TANGEDCO violations: NGT takes suo moto cognizance," The New Indian Express, August 4, 2021
  18. "Minutes of the 17th Meeting of the Re-Constituted Expert Appraisal Committee (EAC) on Environmental Impact Assessment (EIA) of Thermal Power Projects Held on 30th November, 2021," Expert Appraisal Committee, November 30, 2021
  19. "Report of Joint Committee," Submitted to NGT (SZ) Chennai, September 2021
  20. "Tamil Nadu’s Ennore is a case study in climate recklessness and environmental casteism," The News Minute, April 8, 2022
  21. "Amid opposition, Tangedco plans to develop areas near Ennore TPS," DT Next, September 29, 2023
  22. Jun 20, B. Sivakumar / TNN /; 2019; Ist, 10:08. "Chennai: Tangedco to add 2,100MW thermal capacity in 2 years | Chennai News - Times of India". The Times of India. Retrieved 2020-09-30.{{cite web}}: CS1 maint: numeric names: authors list (link)
  23. COVID-19, cyclones delayed Ennore Thermal Plant, Tangedco says, The Hindu, Dec. 9, 2020
  24. Tamil Nadu Electricity Board, "Executive Summary of EIA for proposed Ennore SEZ Thermal Power Project (2X800) MW at Vayalur Village, Ambathur Taluk, Thiruvallur District, Tamil Nadu", Tamil Nadu Electricity Board, December 2010, page E-III.
  25. Environmental clearance, India MoEF, January 7, 2014
  26. "Tangedco bids for 2 Odisha coal blocks," Times of India, January 12, 2022

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.