Fujian Luoyuan Minguang Iron and Steel Co Ltd

From Global Energy Monitor

Fujian Luoyuan Minguang Iron and Steel Co., Ltd. (福建罗源闽光钢铁有限责任公司) is a 1800 thousand tonnes per annum (TTPA) blast furnace (BF) and basic oxygen furnace (BOF) steel plant operating in Fuzhou, Fujian, China.

Location

The map below shows the location of the steel plant in Fuzhou, Fujian, China.

Loading map...
  • Location: Zone 1, Jingang Industrial Zone, Luoyuanwan Development Zone, Luoyuan County, Fuzhou City, Fujian Province[1]
  • Coordinates (WGS 84): 26.483815, 119.671050 (exact)

Background

The Sansteel Group's Luoyuan Minguang project, along with its supporting facilities, and the construction of a 1.3 million tons per year H-beam production line will be carried out in two phases. Main construction contents of Phase One: 1* 1280m3 blast furnace( into production in May 2022.[2][3]), 1 × 200m2 sintering production line, 3 × 600t/d twin-chamber kilns, 1 × 80,000m3 converter gas holder, a 50,000m3/d water treatment station, a 30,000m3/d wastewater treatment (with water recycling) station, implementing ultra-low emission transformation, and phasing out the existing 500m3 and 660m3 blast furnaces(discontinued in April 2021[4]), one each, and the existing 96m2 and 117m2 sintering production lines, as well as 6 × 180m3 and 1 × 550m3 lime kilns, with no additional production capacity.

Phase Two construction includes: 1*1250m3 blast furnace (into production in January 2021[5] ), 1 × 200m2 sintering production line supporting the production system, 1 × 120-ton BOF(into production in May 2022[6]), a set of 5-machine 5-strand continuous casting machines for irregular shapes, Phase Two of the integrated raw material yard, facilities for steel slag and water slag treatment, railway, pipeline, and other auxiliary systems.

At the same time, a 1.3 million tons per year H-beam production line will be built, adopting domestically advanced production processes and developing internationally advanced varieties of H-beam to achieve high-performance and high-quality products. Upon completion of the project, it will have an ironmaking capacity of 2.33 million tons and a steelmaking capacity of 2.65 million tons, with an annual output value of up to 15 billion yuan and a profit of 1 billion yuan.

According to the announcement of capacity replacement in October 2021, it is planned to build 1x110-tonne BOF and remove 2x50-tonne BOF.[7]



Plant Details

Table 1: General Plant Details

Plant status Start date Workforce size
operating[8] 2014[8] 2499[1]

Table 2: Ownership and Parent Company Information

State-owned entity status State-owned entity department Parent company Parent company PermID Owner Owner company PermID
partial[9] Fujian Province State-owned Assets Supervision and Administration Commission 52.206%[9] Sansteel Minguang Co Ltd Fujian [100%][9] 4295864964 [100%] Fujian Luoyuan Minguang Steel Co Ltd[1] 5067510136

Table 3: Process and Products

Steel product category Steel products Main production equipment Detailed production equipment
semi-finished; finished rolled[8] hot rolled smooth round steel bar, hot rolled ribbed steel bar, continuous casting billet[8] blast furnace (BF) and basic oxygen furnace (BOF)[10] 2 BOF (2x50-tonne)[11]

Table 4: Crude Steel Production Capacities (thousand tonnes per annum):

Basic oxygen furnace steelmaking capacity Nominal crude steel capacity (total)
1800 TTPA[8] 1800 TTPA

Table 5: Upstream Products Production Capacities (thousand tonnes per annum)

Coke
2230 TTPA[12]

Table 6: Actual Crude Steel Production by Year (thousand tonnes per annum):

Year BOF Production EAF Production OHF Production Total (all routes)
2020 1994 TTPA[12] 1994 TTPA

Table 7: Actual Crude Iron Production by Year (thousand tonnes per annum):

Year BF Production DRI Production Total (all routes)
2020 1699 TTPA[12] 1699 TTPA


Blast Furnace Details

Table 8: Blast Furnace Details:

Unit name Status Stop date Current size Current capacity
unknown retired[11] April 2021 500 m³[10] 600 TTPA[11]
unknown retired[11] April 2021 660 m³[10] 734 TTPA[11]

Articles and Resources

Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker and Global Blast Furnace Tracker on the Global Energy Monitor website.

  1. 1.0 1.1 1.2 https://web.archive.org/web/20220110202046/https://www.qcc.com/firm/3af95b5600fac0a4792e66ca847c860e.html. Archived from the original on 2022-01-10. {{cite web}}: Missing or empty |title= (help)
  2. 马春林 (2022-05-16). "罗源闽光钢铁2#高炉点火投产" (in 中文). Retrieved 2022-09-28. {{cite web}}: Text "中冶集团" ignored (help)CS1 maint: url-status (link)
  3. 企业简介, 福建罗源闽光钢铁有限责任公司网站, Accessed July 2021
  4. "福建三钢闽光股份有限公司产能置换(罗源闽光部分)及配套项目环境影响报告书" (PDF). 2022年2月. {{cite news}}: Check date values in: |date= (help)
  5. "中冶华天总承包罗源闽光钢铁1号高炉顺行、低耗、高产 - 中冶华天工程技术有限公司". www.mcc-ht.com. 2021-10-26. Retrieved 2023-01-25.{{cite web}}: CS1 maint: url-status (link)
  6. "深耕"绿色+智造" 罗源湾钢铁基地加速跑". 金台资讯. 2022-08-05.
  7. 福建三钢闽光股份有限公司产能置换方案公告,福建省工业和信息化厅,October 26, 2021
  8. 8.0 8.1 8.2 8.3 8.4 https://web.archive.org/web/20220121111423/http://www.sgmgnet.com/lymg/index.htm. Archived from the original on 2022-01-21. {{cite web}}: Missing or empty |title= (help)
  9. 9.0 9.1 9.2 https://web.archive.org/web/20211205145327/https://www.qcc.com/firm/7d583050b1d8dab55fa59f8d480c2c43.html. Archived from the original on 2021-12-05. {{cite web}}: Missing or empty |title= (help)
  10. 10.0 10.1 10.2 https://web.archive.org/web/20220207192044/https://finance.sina.com.cn/money/future/indu/2020-03-02/doc-iimxxstf5776330.shtml. Archived from the original on 2022-02-07. {{cite web}}: Missing or empty |title= (help)
  11. 11.0 11.1 11.2 11.3 11.4 (PDF) http://sthjt.fujian.gov.cn/zwgk/gsgg/202202/P020220208597265737540.pdf. {{cite web}}: Missing or empty |title= (help)
  12. 12.0 12.1 12.2 https://web.archive.org/web/20220318111259/http://lymgsbjy.com/extranet/article?contId=16709. Archived from the original on 2022-03-18. {{cite web}}: Missing or empty |title= (help)