Guangxi LNG Terminal Transport Pipeline

From Global Energy Monitor
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor.
Sub-articles:
The diagram of Guangxi LNG Terminal Transport Pipeline.png

Guangxi LNG Terminal Transport Pipeline (北海LNG外输管线) is a natural gas pipeline under construction in China.[1]

Location

The pipeline runs from Beihai, to Hechi, Guangxi, China.[1]

Loading map...

Background

The source of the pipeline is the Beihai LNG Terminal. The pipeline contains one major pipeline and 6 branch lines.[2] The total length is 1332 kilometers. [3]

Due to the dynamic change of the market demand, the major pipeline segment Liuzhou-Hechi and four branches were cancelled. The trunk pipeline was shortened to 497 kilometers and the total length shrank to 731 kilometers.[3]

In July 2020, the ownership of the pipeline was transferred to PipeChina along with the Beihai LNG Terminal.[4]

Project details

  • Parent company: Sinopec[5]
  • Capacity: 4 bcm/year
  • Length: 684 km / 425.02 mi
  • Status: Operating
  • Start year: 2013, 2015[1], 2019

The pipeline is composed of multiple branches listed below.

Beihai-Maoming Branch 粤西支线 (北海-茂名)

Beihai–Maoming Branch, also known as Guangdong West Branch (粤西支线), was partially completed in 2019 with the Beihai–Zhanjiang segment.[6] The operating date of Zhanjiang-Maoming segment is unknown. By September 2020, the pipeline has passed the completion inspection.[7] The line was fully put into operation on August 8, 2020. The pipeline is an important natural gas energy channel that connects Guangdong and Guangxi and promotes the construction of the Guangdong-Hong Kong-Macao Greater Bay Area and the Hengqin Guangdong-Macao Deep Cooperation Zone.[8]

  • Operator:
  • Owner: Guangxi Natural Gas Pipeline Co., Ltd.[9]
  • Parent company:
  • Capacity: 3.3 bcm/y[8]
  • Length: 207 kilometers[3]
  • Diameter: 559 mm[9]
  • Status: Operating[8]
  • Start year: 2022[8]
  • Cost:
  • Financing:
  • Associated infrastructure:

Guigang–Yulin Branch 玉林支线 (贵港-玉林)

  • Parent company: Sinopec[5]
  • Capacity:
  • Length: 137.7 kilometers[3]
  • Status: Cancelled
  • Start year:

Qinzhou–Fangchenggang Branch 防城港支线 (钦州-防城港)

  • Parent company: Sinopec[5]
  • Capacity:
  • Length: 70.44 kilometers[3]
  • Status: Cancelled
  • Start year:

Liuzhou–Guilin Branch 桂林支线 (柳州-桂林)

Loading map...
  • Operator:
  • Owner: National Pipe Network Group Southwest Pipeline Co., Ltd.[10]
  • Parent company: Sinopec[5]
  • Capacity: 2.5 bcm/y[10]
  • Length: 155.7 kilometers[10]
  • Diameter: 813 mm[10]
  • Status: Operating (trail operating)[10]
  • Start year:2023[10]
  • Cost:
  • Financing:
  • Associated infrastructure:

Beihai LNG-Guigang Gas Pipeline 广西LNG外输管道复线(北海LNG贵港)

Loading map...
  • Operator:
  • Owner: National Pipe Network Group Southwest Pipeline Co., Ltd.[11]
  • Parent company: Sinopec[5]
  • Capacity:
  • Length:244 kilometers[11]
  • Diameter: 1016 mm[12]
  • Status: Proposed[11]
  • Start year:
  • Cost:
  • Financing:
  • Associated infrastructure: Beihai LNG Terminal[12]

Liuzhou Branch 柳州支线

  • Operating company:
  • Owner: Guangxi Natural Gas Pipeline Co., Ltd. 广西天然气管道有限责任公司[13]
  • Parent company: Sinopec[5]
  • Capacity:
  • Length: 27 kilometers[3]
  • Diameter: 610 mm[14]
  • Status: Operating
  • Start year: 2013

Guangxi LNG Terminal Transport Parallel Pipeline 广西北海LNG外输管道复线(百色-文山)又称桂汽入滇天然气管道

百色-文山输气管道总体走向示意图.png

广西 LNG 外输管道复线(百色—文山)工程起自西气东输二线南宁-百色支线工程(简称西二线南百支线)的百色末站(广西壮族自治区百色市右江区)外,止于云南省文山壮族苗族自治州砚山县。工程沿线途经广西壮族自治区百色市右江区、云南省文山州富宁县、广南县、砚山县共 4 个县区级行政区域,全长约344.4km,设4座站场,分别为百色首站、富宁分输清管站、广南分输清管站、砚山末站,14 座线路截断阀室,9 处山岭隧道,4 处水域大中型穿越。 管道设计输量 10×108m3/a,设计压力 10MPa,管径Φ508mm,管线材质L415M。工程总投资 29.41×108元。[15]

Baise-Tianlin Branch 百色-田林天然气支线管道

Loading map...
  • Operating company:
  • Owner: Guangxi Guangtou Natural Gas Pipeline Network Co., Ltd.[16]
  • Parent company:
  • Capacity: 0.364 bcm/year[16]
  • Length: 92 kilometers[16]
  • Diameter: 323.9 mm[16]
  • Status: Proposed[17]
  • Start year:
  • Cost: 364.2162 million RMB[16]
  • Financing:
  • Associated infrastructure:

Fusui-Chongzuo Branch 扶绥-崇左天然气支线管道

Loading map...
  • Operating company:
  • Owner: Guangxi Guangtou Natural Gas Pipeline Network Co., Ltd.[18]
  • Parent company:
  • Capacity: 0.848 bcm/year[18]
  • Length: 83 kilometersr[18]
  • Diameter: 355.60 mm[18]
  • Status: Construction[19]
  • Start year:
  • Cost: 289.7411 million RMB[18]
  • Financing: 40% own funds, 60% commercial bank loans[18]
  • Associated infrastructure: Nanning-Fusui Branch[18]

Guilin-Lingchuan-Xing'an Branch 桂林-灵川-兴安天然气支线管道

Loading map...
  • Operating company:
  • Owner: Guangxi Guangtou Natural Gas Pipeline Network Co., Ltd.[20]
  • Parent company:
  • Capacity: 0.22 bcm/year[20]
  • Length: 100 kilometersr[20]
  • Diameter: 273.10 mm[20]
  • Status: Proposed[21]
  • Start year:
  • Cost: 361.4814 million RMB[20]
  • Financing: 40% own funds, 60% commercial bank loans[20]

Guilin-Yangshuo-Lipu Branch 桂东北天然气环网桂林-阳朔-荔浦段

Loading map...
  • Operating company:
  • Owner: Nanning Oil and Gas Transmission Branch of Southwest Oil and Gas Pipeline Co., Ltd. of National Pipe Network Group[22]
  • Parent company:
  • Capacity: 0.84 bcm/year[22]
  • Length: 106 kilometers[22]
  • Diameter: 406.4 mm[22]
  • Status: Proposed[23]
  • Start year:
  • Cost: 584.85 million RMB[22]
  • Financing: 30% own funds, 70% commercial bank loans[22]
  • Associated infrastructure: Guangxi LNG Terminal Transport Pipeline[22]

Hepu-Bobai-Pubei Branch Pipeline 合浦-博白-浦北天然气支线管道

Loading map...
  • Operating company:
  • Owner: Guangxi Guangtou Natural Gas Pipeline Network Co., Ltd.[24]
  • Parent company:
  • Capacity: 0.943 bcm/year[24]
  • Length: 162 kilometers[24]
  • Diameter: 355.6/273.1 mm[24]
  • Status: Proposed[25]
  • Start year:
  • Cost: 578.64 million RMB[24]
  • Financing: 40% own funds, 60% commercial bank loans[24]
  • Associated infrastructure:

Laibin Branch (Wuxuan-Xiangzhou-Jinxiu Segment) 来宾天然气支线管道 (武宣-象州-金秀段)

Loading map...
  • Operating company:
  • Owner: Guangxi Guangtou Natural Gas Pipeline Network Co., Ltd.[26]
  • Parent company:
  • Capacity: 0.19 bcm/year[26]
  • Length: 148 kilometers[26]
  • Diameter: 273.10 mm[26]
  • Status: Proposed[27]
  • Start year:
  • Cost: 478.7447 million RMB[26]
  • Financing: 40% own funds, 60% commercial bank loans[26]
  • Associated infrastructure:

Tiandong-Debao-Jingxi Branch Pipeline 田东-德保-靖西天然气支线管道

Loading map...
  • Operating company:
  • Owner: Guangxi Guangtou Natural Gas Pipeline Network Co., Ltd.[28]
  • Parent company:
  • Capacity: 0.45 bcm/year[28]
  • Length: 120 kilometers[28]
  • Diameter: 355.60 mm[28]
  • Status: Construction[29]
  • Start year:
  • Cost: 421.4935 million RMB[28]
  • Financing: 40% own funds, 60% commercial bank loans[28]
  • Associated infrastructure: Tiandong Branch[28]

Wuzhou-Cexi pipleline 桂东南环网梧州-岑溪段天然气管道

Loading map...
  • Operating company:
  • Owner: Nanning Oil and Gas Transportation Branch of State Pipe Network Group Southwest Pipeline Co., Ltd.[30]
  • Parent company:
  • Capacity: 0.59 bcm/year[30]
  • Length: 60 kilometers[30]
  • Diameter: 406.40 mm[30]
  • Status: Construction[29]
  • Start year:
  • Cost: 299.16 million RMB[30]
  • Financing: 30% own funds, 70% commercial bank loans[30]
  • Associated infrastructure: West-East Gas Pipeline 2 Guangzhou-Nanning Branch[30]

Nanning-Pingxiang Branch Pipeline(Nanning-Chongzuo Segment) 南宁-凭祥支线(南宁-崇左段)

Loading map...
  • Operating company:
  • Owner: Nanning Oil and Gas Transportation Branch of State Pipe Network Group Southwest Pipeline Co., Ltd.[31]
  • Parent company:
  • Capacity: 0.7 bcm/year[31]
  • Length: 125 kilometers[31]
  • Diameter: 457 mm[31]
  • Status: Proposed[32]
  • Start year:
  • Cost: 689.36 million RMB[31]
  • Financing: 30% own funds, 70% commercial bank loans[31]
  • Associated infrastructure: West-East Gas Pipeline 2 Baise Branch Pipeline[31]

Hechi-Nandan Branch Pipeline 河池-南丹天然气支线管道

Loading map...
  • Operating company:
  • Owner: Guangxi Guangtou Natural Gas Pipeline Network Co., Ltd.[33]
  • Parent company:
  • Capacity: 0.515 bcm/year[33]
  • Length: 113.56 kilometers[33]
  • Diameter: 300/250 mm[33]
  • Status: Operating (Daren Section)[34]
  • Start year: 2022[34]
  • Cost: 413.46 million RMB[33]
  • Financing: 40% own funds, 60% commercial bank loans[33]
  • Associated infrastructure: Guangxi Gas Pipeline Network Hechi Branch[35]

Articles and resources

References

  1. 1.0 1.1 1.2 Zhang Xiao Fu Rakhine 广西液化天然气项目进展顺利 正式建成投产后,两广16地市将用上优质的天然气 Beihai Daily Web, 7/14/2015
  2. 中石化广西管道输气站粤西支线闸口至湛江段投产 湛江日报 Oct 9, 2019
  3. 3.0 3.1 3.2 3.3 3.4 3.5 "广西液化天然气(LNG)项目水土保持方案变更报告" (PDF). mwr.org. 2017-10-01.{{cite web}}: CS1 maint: url-status (link)
  4. "北海LNG接收站着火致5人死亡,系中石化移交国家管网集团刚满一月|界面新闻". www.jiemian.com (in 中文). 2020-11-03. Retrieved 2021-10-08.{{cite web}}: CS1 maint: url-status (link)
  5. 5.0 5.1 5.2 5.3 5.4 5.5 广西液化天然气(LNG)项目环境影响评价 广西新闻网, Dec 1, 2011
  6. "中石化广西管道输气站粤西支线闸口至湛江段投产-新闻-能源资讯-中国能源网". www.china5e.com. 2019-10-09. Retrieved 2021-10-08.{{cite web}}: CS1 maint: url-status (link)
  7. "广西液化天然气(LNG)三期扩建项目 环境影响评价第一次公示". Beihai City Government Website. 2021-03-26.{{cite web}}: CS1 maint: url-status (link)
  8. 8.0 8.1 8.2 8.3 广西管道公司粤西支线全面实现商业运营 保障湛江市管道沿线天然气供应, 湛江云媒, 2022-08-09
  9. 9.0 9.1 液化天然气(LNG)输气管道工程粤西支线EPC总承包资格招标公告, 采招网, 2013-08-15
  10. 10.0 10.1 10.2 10.3 10.4 10.5 广西管道桂林支线启动投产试运, 管道保护, 2023-09-13
  11. 11.0 11.1 11.2 广西LNG外输管道复线(北海LNG-贵港)项目, 电力招标网,2023-03-08
  12. 12.0 12.1 北海LNG外输管道复线项目可行性研究报告及项目申请报告编制技术服务, 采招网,2021-08-12
  13. "广西液化天然气(LNG)项目输气管道工程竣工环境保护验收调查报告" (PDF). 2020-09. {{cite web}}: Check date values in: |date= (help)CS1 maint: url-status (link)
  14. 广西天然气管道有限责任公司2020年度管道沿线风险隐患治理项目施工总承包(框架协议)二标段招标公告, 采招网, 2020-07-09
  15. 15.0 15.1 15.2 15.3 15.4 15.5 15.6 "广西 LNG 外输管道复线(百色—文山)工程环境影响报告书" (PDF). April 2022.
  16. 16.0 16.1 16.2 16.3 16.4 广西壮族自治区发展和改革委员会关于广西天然气支线管网项目百色—田林天然气支线管道工程项目核准的批复, 能源局, 2019-07-17
  17. 百政办发〔2023〕35号 关于印发广西百色重点开发开放试验区建设2023年工作要点的通知, 百色市重点开发开放试验区工作办公室和综合服务中心, 2023-07-04
  18. 18.0 18.1 18.2 18.3 18.4 18.5 18.6 广西壮族自治区发展和改革委员会关于广西天然气支线管网项目扶绥-崇左天然气支线管道工程项目核准的批复(桂发改能源〔2019〕169号), 能源局, 2019-03-01
  19. 政府工作报告—2023年2月9日在扶绥县第十七届人民代表大会第三次会议上, 扶绥县人民政府办公室, 2023-02-14
  20. 20.0 20.1 20.2 20.3 20.4 20.5 广西壮族自治区发展和改革委员会关于广西天然气支线管网项目桂林-灵川-兴安天然气支线管道工程项目核准的批复(桂发改能源[20181484号)], 能源局, 2018-12-25
  21. 桂林市发展和改革委员会2021年部门预算说明, 桂林市发改委, 2021-07-22
  22. 22.0 22.1 22.2 22.3 22.4 22.5 22.6 广西壮族自治区发展和改革委员会关于桂东北天然气环网桂林-阳朔-荔浦段天然气管道项目核准的批复, 广西壮族自治区发展和改革委员会, 2022-06-15
  23. 金宝乡:一线监督 为征地拆迁拉好警戒线, 金宝乡纪委, 2022-11-23
  24. 24.0 24.1 24.2 24.3 24.4 24.5 广西壮族自治区发展和改革委员会关于广西天然气支线管网项目合浦-博白-浦北天然气支线管道工程项目核准的批复, 广西壮族自治区发展和改革委员会, 2022-06-15
  25. 浦北县人民政府征地补偿安置方案公告 浦政通〔2023〕40号, 浦北县自然资源局, 2023-04-11
  26. 26.0 26.1 26.2 26.3 26.4 26.5 广西壮族自治区发展和改革委员会关于广西天然气支线管网项目来宾天然气支线管道工程(武宣-象州-金秀段)项目核准的批复, 广西壮族自治区发展和改革委员会, 2022-08-24
  27. 来宾市兴宾区人民政府拟征收土地启动公告〔2023〕24号, 来宾市兴宾区人民政府, 2023-08-03
  28. 28.0 28.1 28.2 28.3 28.4 28.5 28.6 广西壮族自治区发展和改革委员会关于广西天然气支线管网项目田东-德保-靖西天然气支线管道工程项目核准的批复_(桂发改能源〔2018〕334号), 广西壮族自治区发展和改革委员会, 2018-03-30
  29. 29.0 29.1 协调解决天然气支线管道工程项目建设困难和问题,右江日报, 2023-02-08
  30. 30.0 30.1 30.2 30.3 30.4 30.5 30.6 广西壮族自治区发展和改革委员会关于桂东南环网梧州—岑溪段天然气管道项目核准的批复, 广西壮族自治区发展和改革委员会, 2022-04-14
  31. 31.0 31.1 31.2 31.3 31.4 31.5 31.6 广西壮族自治区发展和改革委员会关于南宁-凭祥支线(南宁-崇左段)项目核准的批复, 广西壮族自治区发展和改革委员会, 2022-09-12
  32. 江府征预〔2023〕20号 南宁市江南区人民政府关于南宁-凭祥支线(南宁-崇左段)江南区段项目土地征收预公告,江南区人民政府 , 2023-06-22
  33. 33.0 33.1 33.2 33.3 33.4 33.5 广西壮族自治区发展和改革委员会关于广西天然气支线管网项目河池-南丹天然气支线管道工程项目核准的批复, 广西壮族自治区发展和改革委员会, 2022-09-12
  34. 34.0 34.1 大任产业园管输天然气正式通气, 河池日报, 2022-09-14
  35. 广西天然气支线管网项目河池-南丹天然气支线管道工程环境影响报告书(公示本), 广西燃气集团有限公司, 2021-01