Rudong LNG Terminal (PetroChina)
| Part of the Global Gas Infrastructure Tracker, a Global Energy Monitor project. |
Rudong LNG Terminal (PetroChina), also known as Jiangsu LNG Terminal, 中石油江苏如东LNG接收站, and 中石油江苏LNG接收站, is an LNG import terminal in China with units that are proposed and operating.
Location
Table 1: Location details
| Name | Location | Coordinates (WGS 84) |
|---|---|---|
| Phase 1 | Sunshine Island, Nantong, Jiangsu, China[1] | 32.528814, 121.428128 (exact) |
| Phase 2 | Sunshine Island, Nantong, Jiangsu, China[1] | 32.528814, 121.428128 (exact) |
| Phase 3 | Sunshine Island, Nantong, Jiangsu, China[1] | 32.528814, 121.428128 (exact) |
| Phase 4 | Sunshine Island, Nantong, Jiangsu, China[1] | 32.528814, 121.428128 (exact) |
The map below shows the exact location of the terminal:
Project Details
Table 2: Infrastructure details
| Name | Facility type | Status | Capacity | Total terminal capacity | Offshore | Associated infrastructure |
|---|---|---|---|---|---|---|
| Phase 1 | import[2][3] | operating[4][5][6] | 3.5 mtpa | 10.0 mtpa | False | – |
| Phase 2 | import[3] | operating[7] | 3 mtpa | 10.0 mtpa | False | – |
| Phase 3 | import[3] | operating[8][9] | 3.5 mtpa | 10.0 mtpa | False | – |
| Phase 4 | import[3] | proposed[6] | – | 10.0 mtpa | False | – |
Table 3: Cost
| Name | Facility type | Cost | Total known terminal costs |
|---|---|---|---|
| Phase 1 | import[2][3] | US$1,060,480,000 (6,628,000,000 RMB) | US$1,602,704,000 |
| Phase 2 | import[3] | US$294,864,000 (1,842,900,000 RMB) | US$1,602,704,000 |
| Phase 3 | import[3] | US$247,360,000 (1,546,000,000 RMB) | US$1,602,704,000 |
| Phase 4 | import[3] | – | US$1,602,704,000 |
Financing
No financing data available.
Table 4: Project timeline
| Name | Facility type | Status | Proposal year | FID year | Construction year | Operating year | Inactive year |
|---|---|---|---|---|---|---|---|
| Phase 1 | import[2][3] | operating[4][5][6] | – | – | 2008[1] | 2011[4][5][6] | – |
| Phase 2 | import[3] | operating[7] | – | – | 2014 | 2016[7] | – |
| Phase 3 | import[3] | operating[8][9] | – | – | 2018[10] | 2021[8][9] | – |
| Phase 4 | import[3] | proposed[6] | 2021[6] | – | – | – | – |
Ownership
Table 5: Ownership
| Name | Facility type | Status | Owners | Parent companies | Operator |
|---|---|---|---|---|---|
| Phase 1 | import[2][3] | operating[4][5][6] | PetroChina Jiangsu LNG Co Ltd [100%][11] | Kunlun Energy Co Ltd [55.0%]; Pacific Energy Ltd [35.0%]; Jiangsu Guoxin Investment Group Ltd [10.0%] | – |
| Phase 2 | import[3] | operating[7] | PetroChina Jiangsu LNG Co Ltd [100%][11] | Kunlun Energy Co Ltd [55.0%]; Pacific Energy Ltd [35.0%]; Jiangsu Guoxin Investment Group Ltd [10.0%] | – |
| Phase 3 | import[3] | operating[8][9] | PetroChina Jiangsu LNG Co Ltd [100%][11] | Kunlun Energy Co Ltd [55.0%]; Pacific Energy Ltd [35.0%]; Jiangsu Guoxin Investment Group Ltd [10.0%] | – |
| Phase 4 | import[3] | proposed[6] | PetroChina Jiangsu LNG Co Ltd [100%][11] | Kunlun Energy Co Ltd [55.0%]; Pacific Energy Ltd [35.0%]; Jiangsu Guoxin Investment Group Ltd [10.0%] | – |
Background
The LNG terminal project is built on a land-filled artificial island offshore of the city of Rudong. Two other LNG Terminals, Rudong LNG Terminal and Rudong LNG Terminal (Jiangsu Guoxin), are also located in this island named Yangguang Island or Sunshine Island.
Jiangsu LNG Terminal connects to the West-East Gas Pipeline which delivers gas to the central and eastern regions of China as well as to the Shaan-Jing pipeline delivering gas to Beijing and the provinces of Shanxi, Hebei, and Tianjin. Phase I began construction in 2008 and operations in November 2011.[12] It includes three 160,000 cubic meter storage tanks capable of receiving 3.5 mtpa of LNG.[13] Phase II started construction in 2014, and in 2015 this 3.5-mtpa capacity expansion was successfully put into operation.[14]
Phase 3 began construction in Nov 2018. It will build 2*200,000 cubic meter gas storage. The operating date was set at 2021.[15][16]
In September 2021, Phase 3 became operational.[17] The total receiving capacity exceeded 10 mpta.
As of September 30, 2022, Rudong LNG Terminal has received and unloaded 565 LNG ships, with a total of 47.106 million tons (66.19 billion cubic meters). The export of natural gas exceeded 62 billion cubic meters, equivalent to 13 years of civil gas supply in Jiangsu Province. Since its operation in 2011, Jiangsu LNG Terminal has received LNG resource from 25 countries and regions such as Qatar, Australia and Russia on the "Belt and Road".[18]
截至2022年9月30日,如东LNG接收站累计接卸565船LNG,接收总量累计达4710.6万吨(661.9亿立方米)。外输天然气超620亿方,相当于江苏省13年的民用燃气供应量。从2011年投运至今,十一年来,江苏LNG接收站先后与“一带一路”上的卡塔尔、澳大利亚、俄罗斯等25个国家和地区的LNG资源地建立通航关系。[18]
Jiangsu LNG terminal is planning the fourth phase of the project, including another LNG storage tank. The supplying capability will increase by 30% if phase 4 built.[19]
该站还在加紧推进四期工程,计划再建一座LNG储罐及相应的配套工艺设施,实现天然气供应保障能力提升30%,接卸、储存、气化、外输能力均达到1000万吨级。[19]
Articles and Resources
Additional data
To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.
References
- ↑ 1.0 1.1 1.2 1.3 1.4 https://www.shangyexinzhi.com/article/1900128.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.0 2.1 2.2 2.3 https://www.petrochina.com.cn/petrochina/mtbd/201403/0377264d1917463e9e4ff47f62cce3ba.shtml.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.00 3.01 3.02 3.03 3.04 3.05 3.06 3.07 3.08 3.09 3.10 3.11 3.12 3.13 3.14 3.15 https://www.nantong.gov.cn/ntsrmzf/sxcz/content/093032bd-36cf-4150-adc1-6fea2102edc7.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 4.0 4.1 4.2 4.3 http://www.cnpcgas.com/news_info.php?cid=1024.
{{cite web}}: Missing or empty|title=(help) - ↑ 5.0 5.1 5.2 5.3 https://www.ndrc.gov.cn/xwdt/ztzl/nybzgzzl/gnjnybz/202103/t20210315_1269514.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 6.0 6.1 6.2 6.3 6.4 6.5 6.6 6.7 https://www.jiangsu.gov.cn/art/2023/7/24/art_84324_10969549.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 7.0 7.1 7.2 7.3 https://www.ndrc.gov.cn/xwdt/ztzl/nybzgzzl/2016trqdd/201611/t20161129_1190035.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 8.0 8.1 8.2 8.3 https://www.kunlun.com.hk/s1/n170/c1167/content.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 9.0 9.1 9.2 9.3 https://www.rudong.gov.cn/rdxrmzf/tpxw/content/2d35aadb-4508-46ec-bad7-7e74da3c4cb7.html.
{{cite web}}: Missing or empty|title=(help) - ↑ http://www.cigia.org.cn/v/xxsc/xmxx/3061.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 11.0 11.1 11.2 11.3 https://www.qcc.com/firm/3285ec442af83672377fd791aa141dd1.html.
{{cite web}}: Missing or empty|title=(help) - ↑ LNG接收站专栏 (2020-05-25). "江苏如东LNG接收站——LNG接收站介绍(05)". 商业新知网 (in 中文(中国大陆)). Retrieved 2021-03-30.
- ↑ Jiangsu Liquefied Natural Gas (LNG) Project, China Hyrdocarbons-Technology, accessed June 24, 2017
- ↑ Jiangsu LNG Terminal CNPC, accessed June 24 2017
- ↑ The third phase of Jiangsu Rudong LNG receiving station was officially opened! The second phase of the new Austrian Zhoushan LNG reception was approved! Sohu, accessed April 16 2019
- ↑ "中国石油江苏如东LNG接收站扩建工程(三期)最新进展_储罐". www.sohu.com. 2019-12-25. Retrieved 2021-03-29.
- ↑ "中石油江苏LNG接收站三期扩建工程在如东投产---来源:人民网". www.cpnn.com.cn. 2021-09-28.
{{cite web}}: CS1 maint: url-status (link) - ↑ 18.0 18.1 "悠悠岁月 赤子情怀——如东LNG接收站纪实 - 中华全国归国华侨联合会". www.chinaql.org. 2022-10-13.
{{cite web}}: CS1 maint: url-status (link) - ↑ 19.0 19.1 "如东县4个LNG项目全部启动 全面建成后可满足全省天然气需求 来源:如东县". https://www.nantong.gov.cn. 2023-07-07.
{{cite web}}: External link in(help); line feed character in|website=|title=at position 31 (help)CS1 maint: url-status (link)