Rudong LNG Terminal (Jiangsu Guoxin), also known as 国信LNG接收站, 国信如东LNG储运调峰站, and 江苏省液化天然气储运调峰项目, is an LNG import terminal in China with units that are in construction.
Location
Table 1: Location details
| Name | Location | Coordinates (WGS 84) |
|---|---|---|
| Phase 1 | Sunshine Island, Nantong, Jiangsu, China[1][2] | 32.526845, 121.412712 (exact) |
| Phase 2 | Sunshine Island, Nantong, Jiangsu, China[1][2] | 32.526845, 121.412712 (exact) |
The map below shows the exact location of the terminal:
Project Details
Table 2: Infrastructure details
| Name | Facility type | Status | Capacity | Total terminal capacity | Offshore | Associated infrastructure |
|---|---|---|---|---|---|---|
| Phase 1 | import[2] | construction[3][4] | 2.95 mtpa[1] | 6.0 mtpa | False | – |
| Phase 2 | import[2] | construction[5] | 3.05 mtpa[6] | 6.0 mtpa | False | – |
Table 3: Cost
| Name | Facility type | Cost | Total known terminal costs |
|---|---|---|---|
| Phase 1 | import[2] | US$832,000,000 (5,200,000,000 RMB)[4] | US$1,233,600,000 |
| Phase 2 | import[2] | US$401,600,000 (2,510,000,000 RMB)[3][4] | US$1,233,600,000 |
Financing
No financing data available.
Table 4: Project timeline
| Name | Facility type | Status | Proposal year | FID year | Construction year | Operating year | Inactive year |
|---|---|---|---|---|---|---|---|
| Phase 1 | import[2] | construction[3][4] | – | – | 2020[3][4] | 2025[3][4] | – |
| Phase 2 | import[2] | construction[5] | – | – | 2024[5] | –[4][4] | – |
Ownership
Table 5: Ownership
| Name | Facility type | Status | Owners | Parent companies | Operator |
|---|---|---|---|---|---|
| Phase 1 | import[2] | construction[3][4] | Jiangsu Guoxin LNG Co Ltd [100%][7] | Jiangsu Guoxin Group Co Ltd [51.0%]; Zhenhua Petroleum Holdings Co Ltd [34.0%]; other [10.0%]; Jiangsu Yangkou Port Co Ltd [5.0%] | – |
| Phase 2 | import[2] | construction[5] | Jiangsu Guoxin LNG Co Ltd [100%][7] | Jiangsu Guoxin Group Co Ltd [51.0%]; Zhenhua Petroleum Holdings Co Ltd [34.0%]; other [10.0%]; Jiangsu Yangkou Port Co Ltd [5.0%] | – |
Background
Rudong LNG Terminal (Jiangsu Guoxin) (国信如东LNG储运调峰站) is an LNG terminal under construction in Jiangsu, China. It planned operation by the end of 2025.[8]
Phase 1
Jiangsu Guoxin is developing an LNG terminal with 2.95 mtpa of receiving capacity in Rudong, Nantong, Jiangsu Province. The proposed LNG terminal located in the same artificial island offshore of the Rudong Port in Nantong as the Jiangsu LNG Terminal and proposed Rudong LNG Terminal.[9]
The terminal will include three 200,000 cubic meters of LNG storage tanks. The estimated investment is 5.2 billion yuan ($793.5 million).[9]
The construction began in November 2020[10], with completion aimed for 2023.[9][11]
Three storage tanks of the first phase completed in December 2023.[12]
Phase 1 is expected to commence operations in the first half of 2026.[13]
Phase 2
The second phase is planned to add another 200,000 cubic meters storage tank and a LNG receiving jetty with additional investment of 2.1 billion yuan and is expected to begin construction in November 2021.[11]
The Environmental Impact Assessment of the additional storage tank was asking for public review in January 2022.[14] By September 2022, the developer was in the process of obtaining the necessary governmental documents for the construction. According to these documents, after the new storage tank is built, the total receiving capacity will reach 6 mtpa.[14]
As of early 2023, there was no evidence that construction had begun for the second phase, and it was still considered proposed.
The second phase of Guoxin LNG terminal received permit for construction in September 2023.[15]By the end of 2023, the construction of the second phase has been ongoing. [12]
江苏国信如东LNG项目由国信集团所属江苏国信液化天然气有限公司负责建设运营,工程分两期实施,总投资约75亿元,其中,一期工程为江苏省液化天然气储运调峰项目,规划建成3座20万立方米LNG储罐及相应辅助公用工程设施,设计年接卸周转能力为295万吨,目前,3座储罐已基本建成。
获得核准的二期项目为液化天然气接收站工程,是一期项目的扩建工程,将建设1座LNG储罐及1座LNG专用码头。两期项目全面建成后,总罐容达80万立方米,最大储气能力为4.8亿立方米,最大日供气量可达6000万立方米,可保障全省全行业3天的用气量。项目配套的LNG专用接卸码头年装车能力为80万吨,年周转能力可达600万吨,对于服务全省天然气应急调峰和能源保供具有重要意义。[15]
On 20 January 2026, the project was included in the 2026 Major Project List of Jiangsu Province. [16]
Articles and Resources
Additional data
To access additional data, including an interactive map of LNG terminals, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.
References
- ↑ 1.0 1.1 1.2 https://www.sohu.com/a/431578212_99960224.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 http://www.rudong.gov.cn/rdxrmzf/tpxw/content/502370ee-cf77-49b4-8058-858d68fb2a6f.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.0 3.1 3.2 3.3 3.4 3.5 https://fzggw.jiangsu.gov.cn/art/2020/11/13/art_4591_9567925.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 https://www.rudong.gov.cn/rdxrmzf/tpxw/content/78866f48-e680-4f05-ac69-5a90191f5101.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 5.0 5.1 5.2 5.3 https://www.shpgx.com/html/xyzx/20241014/6886.html.
{{cite web}}: Missing or empty|title=(help) - ↑ http://zrzy.jiangsu.gov.cn/gggs/2022/09/13164735638589.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 7.0 7.1 https://www.qcc.com/firm/7b435867b40792a4f2082ed812c54a61.html.
{{cite web}}: Missing or empty|title=(help) - ↑ 陶玲莉 (2025-03-25). "国信LNG项目全速"冲刺跑" 确保在今年底全面建成-如东县人民政府". www.rudong.gov.cn.
{{cite web}}: CS1 maint: url-status (link) - ↑ 9.0 9.1 9.2 "江苏如东将新增LNG接收站". www.sohu.com. 2020-11-13. Retrieved 2021-04-09.
{{cite web}}: CS1 maint: url-status (link) - ↑ "江苏省液化天然气储运调峰工程开工 来源:如东县". 2020-11-11.
{{cite web}}: CS1 maint: url-status (link) - ↑ 11.0 11.1 LNG接收站专栏 (2020-11-12). "3座20万方LNG储罐!江苏国信如东LNG储运调峰工程开工". 商业新知网. Retrieved 2021-04-09.
- ↑ 12.0 12.1 "阳光岛四大LNG接收站重大能源项目加速推进-如东县人民政府". www.rudong.gov.cn. 2023-12-29.
{{cite web}}: CS1 maint: url-status (link) - ↑ "如东锚定"向海图强",引领全域向海发展——一片海与一座城的"双向奔赴"". 2026-03-20. Retrieved 2026-04-04.
{{cite web}}: CS1 maint: url-status (link) - ↑ 14.0 14.1 "江苏国信如东液化天然气接收站工程环境影响评价征求意见稿公示 - 公告公示". www.rudong.gov.cn. 2022-01-04.
{{cite web}}: CS1 maint: url-status (link) - ↑ 15.0 15.1 "江苏国信如东LNG二期项目获准 即将进入开工建设准备阶段 来源:南通日报". www.nantong.gov.cn. 2023-09-11.
{{cite web}}: line feed character in|title=at position 29 (help)CS1 maint: url-status (link) - ↑ "省重大项目和省民间投资重点产业项目清单出炉". 2026-01-20. Retrieved 2026-04-04.
{{cite web}}: CS1 maint: url-status (link)