Jili Baikuang power station (吉利百矿集团有限公司清洁高效煤电项目) is a permitted power station in Toutang Town, Tianyang, Baise, Guangxi, China.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Jili Baikuang power station | Toutang Town, Tianyang, Baise, Guangxi, China | 23.7849583, 106.8202878 (approximate)[1] |
The map below shows the approximate location of the power station.
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Retired year |
---|---|---|---|---|---|---|
Unit 1 | permitted | coal - unknown | 660 | ultra-supercritical | 2025 | – |
Unit 2 | permitted | coal - unknown | 660 | ultra-supercritical | 2025 | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner |
---|---|
Unit 1 | Guangxi Baikuang Chaoyuan Power Generation Co Ltd [100.0%] |
Unit 2 | Guangxi Baikuang Chaoyuan Power Generation Co Ltd [100.0%] |
Project-level coal details
- Permit(s): December 28, 2022
Background
On August 3, 2022, the Development and Reform Commission of Guangxi Zhuang Autonomous Region issued an official document (桂发改电力〔2022〕829 号) regarding coal power projects for its provincial 14th Five-Year Plan for the energy sector. Baise Mining Group Co., Ltd.’s ‘suppress small to scale up big’ 2 x 660 MW coal power project is one of them. Guangxi Baikuang Chaoyuan Power Generation Co., Ltd. was set up to develop and run the construction and operation of the project.[2]
Echoing the National Development and Reform Commission's call that the new coal power adopts the principle of "establishing before reforming, ultra-supercritical, and not selecting new sites", Jili Baikuang power station was set to be built at the reserved expansion site of Baise Tianyang power station.[2]
The project was granted permission (桂发改电力〔2022〕1327号) to build on 28 December 2022 and it was also in 2023 Guangxi Energy Infrastructure Construction Work Plan. [3]
Articles and Resources
References
- ↑ https://web.archive.org/web/20240125084944/https://mp.weixin.qq.com/s/YblNsJQA7TvItC3gruyfKQ. Archived from the original on 25 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.0 2.1 "火电|总投资55.37亿元!!2×660MW!广西新增清洁高效煤电项目!". 能源电力新观察. 2023-06-25. Retrieved 2023-07-20.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 广西壮族自治区发展和改革委员会 (2023-04-03). "广西壮族自治区发展和改革委员会关于印发《广西能源基础设施建设2023年工作推进方案》的通知". 广西壮族自治区发展和改革委员会. Retrieved 2023-07-20.