Jindal Shadeed Iron & Steel Duqm plant
| This article is part of the Global Iron and Steel Tracker, a project of Global Energy Monitor. |
| Sub-articles: |
Jindal Shadeed Iron & Steel Duqm plant (جندال شديد للحديد و الصلب), also known as Vulcan Green Steel, is a steel plant in Duqm, Al Wusta, Oman that operates direct reduced iron (DRI) and electric arc furnace (EAF) technology.
Location
The map below shows the approximate location of the plant in Duqm, Al Wusta, Oman:
- Location: Special Economic Zone, Duqm (Sezad), Oman
- Coordinates (WGS 84): 19.640299, 57.677866 (approximate)
Background
Jindal Shadeed Iron & Steel is a steel manufacturing company based in the Special Economic Zone in Duqum of the Sultanate of Oman. It is the largest privately-owned integrated steel producer in the Persian Gulf region. Jindal Shadeed has made commitments to foster socio-economic growth and support Oman's transition to a green, circular economy. The Duqum plant will be a hydrogen-ready green steel complex.[1]
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Low-emissions/green steelmaking
This steel plant is associated with a green steel project tracked in the Green Steel Tracker. Details about the project are included below.
Table 1: Green Steel Project Details
| Project 1 | |
|---|---|
| Project name | Jindal Steel and Power DRI Duqm |
| Company | Jindal Steel and Power Ltd (JSPL) |
| Company has climate goals? | Yes |
| Location | Duqm, Oman |
| Project website | Site |
| Project scale | Full scale |
| Project status | Construction |
| Year to be online | 2026 |
| Technology to be used | H-DRI |
| Technology details | ENERGIRON ready for transition from NG to 100% H2 + EAD |
| Iron production capacity (million tonnes per year) | 2 |
| Steel production capacity (million tonnes per year) | 5 |
| CO2 capture (million tonnes CO2 per year) | Not applicable |
| Hydrogen generation capacity (MW) | Not applicable |
| Investment size (m USD) | 3000 |
| Partners | Tenova |
| Date of announcement | 11/27/2023 |
Plant Details
Table 2: General Plant Details
| Announced date | Construction date | Start date | Power source |
|---|---|---|---|
| 2022[2] | 2023[3] | 2026[3] | Plan to use renewable energy sources from Marafiq (centralised utility provider); 600 MW solar plant[3][4] |
Table 3: Ownership and Parent Company Information
| Parent company | Parent company PermID | Parent GEM entity ID | Owner | Owner company PermID | Owner GEM entity ID |
|---|---|---|---|---|---|
| Templar Investments Ltd | 5073981194 | E100001010331 | Jindal Shadeed Iron & Steel LLC [100%][2] | 4297115884 | E100001010329 [100%] |
Table 4: Process and Products
| Steel products | Steel sector end users | Main production equipment |
|---|---|---|
| HBI[5] | automotive, energy[6] | DRI; EAF |
Table 5: Plant-level Crude Steel Production Capacities (thousand tonnes per annum)
| Capacity operating status1 | Electric arc furnace steelmaking capacity | Nominal crude steel capacity (total) |
|---|---|---|
| construction | 5000[3][2] | 5000[3][2] |
Table 6: Plant-level Crude Iron Production Capacities (thousand tonnes per annum)
| Capacity operating status1 | Sponge iron/DRI capacity | Nominal iron capacity (total) |
|---|---|---|
| construction | 4750[7][8] | 4750[7][8] |
Table 7: Upstream Products Production Capacities (thousand tonnes per annum)
| Ferronickel | Sinter | Pellets |
|---|---|---|
| NF | NF | NF |
Unit Details
Table 8: Direct Reduced Iron Furnace Details
| Unit name | Status | Announced date | Construction date | Start date | Furnace manufacturer and model | Furnace type | Current capacity (ttpa) |
|---|---|---|---|---|---|---|---|
| DRI 1 | construction[9][10] | 2022[9] | 2023[9] | 2026[9] | Tenova and Danieli Energiron[11][7] | shaft furnace[7] | 2250[8] |
| DRI 2 | construction[8][9] | 2022[9] | – | 2027[3] | Tenova and Danieli Energiron Zero-Reformer[12][7] | shaft furnace[7] | 2500[7] |
Table 9: Direct Reduced Iron Furnace Reductant Details
| Unit name | Current or initial reductant |
|---|---|
| DRI 1 | gas[10] |
| DRI 2 | gas[7] |
Table 10: Electric Arc Furnace Details
| Unit name | Status | Start date | Current capacity (ttpa) |
|---|---|---|---|
| unknown EAF (1) | construction[3][9][2] | 2027[3] | 2500[3][2] |
| unknown EAF (2) | construction[3][9][2] | 2026[3] | 2500[3][2] |
Table 11: Electric Arc Furnace Feedstock Details
| Unit name | Scrap-based | % scrap | % DRI | % HBI | % sponge iron (unknown if DRI or HBI) |
|---|---|---|---|---|---|
| unknown EAF (1) | no[13] | 0[13] | >0[13][14] | >0[13][14] | 100.00[13][14] |
| unknown EAF (2) | no[13] | 0[13] | >0[13][14] | >0[13][14] | 100.00[13][14] |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel plants, a downloadable dataset, and summary data, please visit the Global Iron and Steel Tracker on the Global Energy Monitor website.
References
- ↑ "Zero-Carbon Target: Oman's Jindal Shadeed to start full production of green steel in 2027– CEO". Retrieved 2023-09-29.
- ↑ 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 https://www.steelorbis.com/steel-news/latest-news/oman-based-jindal-shadeed-to-build-green-steel-plant-1270273.htm?searchKey=oman&sc=article.
{{cite web}}: Missing or empty|title=(help) - ↑ 3.00 3.01 3.02 3.03 3.04 3.05 3.06 3.07 3.08 3.09 3.10 3.11 https://web.archive.org/web/20230317110426/https://www.zawya.com/en/projects/industry/zero-carbon-target-omans-jindal-shadeed-to-start-full-production-of-green-steel-in-2027-ceo-twpaxpm7. Archived from the original on 2023-03-17.
{{cite web}}: Missing or empty|title=(help) - ↑ https://web.archive.org/web/20240905173609/https://www.mining-technology.com/news/jindal-green-steel-oman/. Archived from the original on 2024-09-05.
{{cite web}}: Missing or empty|title=(help) - ↑ https://aisusteel.org/35848/.
{{cite web}}: Missing or empty|title=(help) - ↑ https://www.steelorbis.com/steel-news/latest-news/omans-vulcan-green-steel-to-supply-low-emission-steel-to-volkswagen-1344629.htm.
{{cite web}}: Missing or empty|title=(help) - ↑ 7.0 7.1 7.2 7.3 7.4 7.5 7.6 7.7 https://www.danieli.com/en/news-media/news/Jindal-Steel-orders-second-hydrogen-ready-DRI-plant-in-Oman_37_997.htm.
{{cite web}}: Missing or empty|title=(help) - ↑ 8.0 8.1 8.2 8.3 https://web.archive.org/web/20221207120927/https://www.zawya.com/en/projects/industry/jindal-shadeed-to-invest-4bln-in-new-green-steel-projects-in-oman-xohmsqe9. Archived from the original on 2022-12-07.
{{cite web}}: Missing or empty|title=(help) - ↑ 9.0 9.1 9.2 9.3 9.4 9.5 9.6 9.7 https://web.archive.org/web/20240124204126/https://renewablesnow.com/news/construction-of-jindals-green-steel-plant-in-oman-to-begin-in-oct-832774/. Archived from the original on 2024-01-24.
{{cite web}}: Missing or empty|title=(help) - ↑ 10.0 10.1 https://web.archive.org/web/20240126184231/https://gmk.center/en/news/oman-begins-construction-of-key-green-steel-plant/. Archived from the original on 2024-01-26.
{{cite web}}: Missing or empty|title=(help) - ↑ https://web.archive.org/web/20240909191324/https://www.aist.org/404. Archived from the original on 2024-09-09.
{{cite web}}: Missing or empty|title=(help) - ↑ https://www.steelorbis.com/steel-news/latest-news/oman-based-vulcan-green-steel-orders-dri-plant-from-danieli-and-tenova-1318328.htm.
{{cite web}}: Missing or empty|title=(help) - ↑ 13.0 13.1 13.2 13.3 13.4 13.5 13.6 13.7 13.8 13.9 https://web.archive.org/web/20240809185452/https://www.zawya.com/en/press-release/companies-news/jindal-shadeed-iron-and-steel-leads-industry-initiatives-on-decarbonisation-wt0hpgdd. Archived from the original on 2024-08-09.
{{cite web}}: Missing or empty|title=(help) - ↑ 14.0 14.1 14.2 14.3 14.4 14.5 https://web.archive.org/web/20220318112640/https://jindalshadeed.com/our-facilities.html. Archived from the original on 2022-03-18.
{{cite web}}: Missing or empty|title=(help)