Kamyshansky-West Coal Mine
This article is part of the Global Coal Mine Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Related-articles: |
Kamyshansky-West Coal Mine (Камышанский Западный разрез) is a shelved coal mine in Kotino, Prokopyevsk, Kemerovo, Russia.
Location
Table 1: Project-level location details
Mine Name | Location | Coordinates (WGS 84) |
---|---|---|
Kamyshansky-West Coal Mine | Kotino, Prokopyevsk, Kemerovo, Russia | 54.253994, 86.979961 (approximate) |
The map below shows the approximate location of the coal mine:
Project Details
Table 2: Project status
Status | Status Detail | Project Type | Opening Year | Closing Year |
---|---|---|---|---|
Shelved | Construction | New | 2023 | – |
Table 3: Operation details
Capacity (Mtpa) | Production (Mtpa) | Year of Production | Mine Type | Mining Method | Mine Size (km2) | Mine Depth (m) | Workforce Size |
---|---|---|---|---|---|---|---|
2 | – | – | Surface | – | – | 60* | * |
Table 4: Coal resources and destination
Total Reserves (Mt) | Year of Total Reserves Recorded | Total Resources (Mt) | Coalfield | Coal Type | Coal Grade | Primary Consumer/ Destination |
---|---|---|---|---|---|---|
100 | – | – | Taldinsky North | Bituminous | – | – |
Table 5: Ownership and parent company
Owner | Parent Company | Headquarters |
---|---|---|
Resurs LLC[1] | Resurs LLC [100%] | Russia |
Note: The above section was automatically generated and is based on data from the Global Coal Mine Tracker April 2024 release and the September supplement.
Background
The Kamyshansky-West coal mine or Kamyshansky-Zapadny coal mine (Камышанский-Западный разрез) is a proposed coal mine near Kiselyovsk, Prokopyevsk municipal district in Kemerovo region, Russia. The Kamyshansky-West coal mine is developed by Resurs LLC (OOO "Ресурс"). It appears that the land rights were acquired by Resurs LLC in 2015 in an auction.[2]
The project is part of the Russian Government's 'Programme for the Coal Industry Development to 2035', published in June 2020.[3] A full range of exploration work has been completed at the proposed mine site, according to the Programme. Additionally, a feasibility study was developed for permanent exploratory conditions; the permanent exploration conditions were approved; land lease was issued; construction of transport communications completed to the site as well as power supply facilities.[3] In August 2021 the project was approved by Glavgosekspertiza.[4]
As there were no updates on the progress of the project as of August 2022 and as of August 2023, the project was therefore considered Shelved. Likewise as of March 2025, there was no new on project progress.
Articles and Resources
Additional data
To access additional data, including an interactive map of world coal mines, a downloadable dataset, and summary data, please visit the Global Coal Mine Tracker on the Global Energy Monitor website.
References
- ↑ https://web.archive.org/web/20240904182652/https://gge.ru/press-center/news/glavgosekspertiza-odobrila-proekt-osvoeniya-uchastka-nedr-na-kuzbasse/. Archived from the original on 04 September 2024.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ "Три угольных участка в Кузбассе выставлены на торги 15 декабря". www.kommersant.ru/. 2015.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 3.0 3.1 ""Программa развития угольной промышленности России до 2035 года"". 14 June 2020.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Главгосэкспертиза одобрила проект освоения участка недр на Кузбассе". 23 August 2021.
{{cite web}}
: CS1 maint: url-status (link)