Killingholme Power Station

From Global Energy Monitor
(Redirected from Killinholme Power Station)

Killingholme Power Station is an operating power station of at least 622-megawatts (MW) in Killingholme, Yorkshire, United Kingdom with multiple units, some of which are not currently operating. It is also known as C.GEN.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Killingholme Power Station Killingholme, Yorkshire, United Kingdom 53.657, -0.255 (approximate)

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year Retired year
Unit C.GEN North Power Project cancelled coal - bituminous, bioenergy - wood & other biomass (solids) 470 subcritical 2017
Unit T_KILLPG-1 operating[1] gas[1] 311[1] gas turbine[2] not found 1992[2]
Unit T_KILLPG-2 operating[1] gas[1] 311[1] gas turbine[2] not found 1992[2]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit C.GEN North Power Project C.GEN [100.0%]
Unit T_KILLPG-1 Uniper UK[2] Fortum Oyj [76.0%]; other [24.0%]
Unit T_KILLPG-2 Uniper UK[2] Fortum Oyj [76.0%]; other [24.0%]

Project-level coal details

  • Coal source(s): Will be fueled by gas or hydrogen?

Gas plants

Killingholme A

The 665 MW gas plant used three Alstom 145MW gas turbines in combined cycle,[3] and was owned by Centrica.[4]

The plant opened in 1994 and was operated by National Power until 2000 when it was bought by NRG Energy for £390 million. It was then purchased in 2003 by a consortium of twenty banks when NRG got into financial difficulty[5] and was then bought by Centrica in July 2004 for £142 million.[6]

In early 2014, Centrica began to seek buyers for a number of its gas power plants, including its South Humber and Killingholme plants,[7] and in early 2015 began discussion on the closure of the plant, having received no acceptable bids for the plant.[8]

In December 2015, Centrica confirmed that Killingholme power station would close on 1st March 2016.[9]

On 6 December 2016, C.GEN bought the mothballed Killingholme A and said it plans to use the land to develop its North Killingholme power station.[10] In November 2017, the site was demolished[11]. For more information see North Killingholme power station.

Killingholme B

The E.ON UK plant consists of two 450 MW Siemens V94.2 gas turbine modules operating originally in combined-cycle mode[12]. Gas is supplied from a 26 mile pipeline from Theddlethorpe.[13]

When it was built by Powergen (now called E.ON UK) and opened in April 1993 it was only the second gas-fired power station built in the UK. It was taken out of service in 2002 due to the lower price of electricity and was then restored to full service in August 2005,[14] with one of the 450 MW units returning to service in April 2005.

In June 2015, E.ON UK announced Killingholme B is to be closed.[15] This resulted in a partial closure in 2016, including conversion to open-cycle mode after March 2018, and full closure in 2019.[16]

In 2020 Uniper announced it had won contracts to provide grid stability from the Killingholme B site, which does not require power generation. It will repurpose two steam turbines with the help of Seimens.[17] Uniper is also exploring hydrogen projects at the site.[18]

According to the 2021 Digest of UK Energy Statistics and Uniper as of November 2021, 600 MW of capacity was still operation in 2021.[19][20]

Proposed power station

E.ON UK

A 450 megawatt coal gasification project proposed by E.ON UK was to be built at the site of the existing Killingholme Power Station.

In a March 2007 media release, E.ON referred to the company having a 3 billion pound investment plan including a "new £1bn cleaner coal-fired units" at Killingholme as well as a "feasibility study into a world-leading clean coal power station at Killingholme."[21] The month before, the company had stated that it was "carrying out a feasibility study into an integrated gasification combined cycle power station (where coal is gasified and hydrogen becomes the fuel used to generate electricity) at Killingholme."[22]

In 2008, the project was reported as being on hold.[23]

North Killingholme IGCC Project

The North Killingholme IGCC Project is a proposed carbon capture and storage power station by C.GEN to be built near the existing gas-fired Killingholme Power Station in Kent, England.

In March 2011, project sponsor C.GEN stated that the plant being studied would have an installed capacity of 520 megawatts with possible fuels varying from coal to a blend of "unconventional hard coal", petcoke and wood/biomass or as a pure gas-fired project. In a presentation on the project, C.GEN stated that it owns land adjoining the existing Killingholme power station. The company stated in early 2011 that Parsons-Brinkerhof "started permitting procedure 2010" and that in February 2011 it had filed an application to the European Union's New Entrant Reserve scheme for funding proposed CCS projects. The company claims that the project could be in "commercial operation" by 2015-2016.[24] In March 2011 a pre-feasibility study for the project was completed.[25]

As of 2014, the company describes the project as a 470 MW IGCC plant that would capture around 2.5 million tonnes per annum of carbon dioxide by 2019.[25] The project is currently being considered for a Development Consent Order, a process summarized by the company as follows:[26]

Under Section 31 of the Planning Act 2008 (PA 2008) a Development Consent Order is required to authorise a Nationally Significant Infrastructure Project (NSIP). In England, an onshore electricity generating station is considered to be a NSIP if the generating capacity is more than 50 MWe. North Killingholme Power Project is 470 MW, so it is a NSIP.
Development consent for a NSIP (and associated development) may only be granted by a DCO following an application under Section 37 of the PA 2008 (as amended by the Localism Act 2011). In certain circumstances an application for a DCO needs to be accompanied by an Environmental Statement. North Killingholme Power Project requires an Environmental Statement to accompany the DCO.

A recommendation was made in June 2014 to the Secretary of State for Energy and Climate Change, and a decision will be announced in September 2014.[26]

New plant with CCS approved

In September 2014, the UK Government approved C.GEN’s plans to build a 470MW power station, complete with CCS technology. C.GEN has yet to decide whether the plant will operate as a Combined Cycle Gas Turbine (CCGT) or as an Integrated Gasification Combined Cycle (IGCC) plant. The plant will use either natural gas or hydrogen rich gas as fuel and will comprise a gas turbine, a steam turbine, a heat recovery steam generator, and carbon capture equipment. The CO2 stream will be transported via a 130km onshore pipeline and a 90km offshore pipeline for storage in a saline aquifer in the Southern North Sea. C.GEN is targeting 2016-2017 for commercial operation to begin and 2020 for sequestration.[27][28]

C.GEN owns the land which the power plant will be built upon but C.GEN will need to acquire additional land to construct a connection to the gas supply network and the electricity transmission network. It will also require land for arrangements to secure the supply of fuel to the plant.[29]

CCS project shelved due to lack of funds

The Killingholme CCS project would use the CO2 pipeline proposed by National Grid for the White Rose CCS Project.[30] An investment decision on White Rose is expected in 2016.[31]

However, in November 2015, the UK Government confirmed that the £1 billion capital budget for the Carbon Capture and Storage (CCS) Competition was no longer available. White Rose finance director Richard Simon-Lewis said: "We are now in transition to closure mode."[32] In April 2016 UK energy secretary Amber Rudd refused development consent for the White Rose CCS project, as Capture Power had itself conceded there are “no contingent funds to cover the absence of these government-sourced funds” and that no alternative sources of funding had been identified.[33]

Plant to be fueled by gas

On 6 December 2016, C.GEN bought the neighboring Centrica Killingholme ‘A’ power station, which is situated on land adjacent to the C.GEN project site. C.GEN said it had obtained development consent to build a 470MW Combined Cycle Gas Turbine (CCGT) power station on the south bank of the Humber Estuary, and intends to bid the gas plant into the December 2017 Capacity Market auction.[34] The gas plant is planned for commissioning in 2021.[35]

Commitments to Decarbonization

Since the UK government's commitment to 5GW of "low-carbon" energy production, Uniper has announced that they hope to outfit this station with CCS technologies, as well as the ability to burn hydrogen as part of their fuel mix.[36]

See North Killingholme power station.

Articles and Resources

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 https://web.archive.org/web/20221128185847/https://remit-uniper.energy/Umm. Archived from the original on 28 November 2022. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 2.3 2.4 2.5 https://web.archive.org/web/20230108191432/https://www.gov.uk/government/statistics/electricity-chapter-5-digest-of-united-kingdom-energy-statistics-dukes. Archived from the original on 08 January 2023. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  3. "Killingholme" (PDF). Centrica. Archived from the original (PDF) on 2012-04-06.
  4. "Centrica boosts generation capacity with Killingholme acquisition". Centrica.
  5. "Gas Turbine and Combined-Cycle Power Plants in East England & the Midlands".
  6. "Power station sold in £142m deal". BBC News. 2004-06-08. Retrieved 2010-05-07.
  7. "Centrica selling off two South Humber power stations". Scunthorpe Telegraph. 8 May 2014. Retrieved 8 August 2015.
  8. "Third jobs bombshell: Centrica describes closure of two power stations as 'difficult decision'". Grimsby Telegraph. 20 February 2015. Retrieved 8 August 2015.
  9. "Centrica confirms closure date for Killingholme power station," Centrica, Dec 14, 2015
  10. "North Killingholme Power Project," C.GEN, accessed May 2017
  11. Watch as Killingholme Power Station towers tumble after demolition team set off 50kg of high explosives, Grimsby Telegraph, Nov 22, 2017
  12. [https://www.ofgem.gov.uk/ofgem-publications/79012/review-energy-sources-power-stations-submission-dges-30-04.pdf REVIEW OF ENERGY SOURCES FOR POWER STATIONS], UK Office of Electricity Generation, Apr 1998
  13. "Killingholme". E.ON UK. Archived from the original on 2010-01-03.
  14. "E.ON UK's Killingholme Power Station returns to full service in world first". E.ON UK. Archived from the original on 2008-10-29.
  15. "E.ON UK announces closure of Killingholme Power Station". E.ON UK. Retrieved 8 August 2015.
  16. Digest of United Kingdom Energy Statistics (DUKES) 2020: main chapters and annexes A to D, United Kingdom National Statistics, Jul 30, 2020
  17. Uniper appoints Siemens Energy to deliver grid stability technology at UK power station sites, Energy Central, Dec 8, 2020
  18. Uniper’s Killingholme: the right place, the right time, the right plans…, Uniper, Mar 22, 2021
  19. "Digest of UK Energy Statistics (DUKES): electricity". Gov.UK. July 29, 2021. Retrieved November 17, 2021.{{cite web}}: CS1 maint: url-status (link)
  20. "Urgent Market Messages - UK". remit-uniper.energy. Retrieved 2021-11-17.
  21. E.ON UK, "E.ON and Lunar Energy to build one of the world’s largest tidal stream power stations", Media Release, March 15, 2007.
  22. E.ON Uk, "E.ON UK researches future of coal at Nottinghamshire test facility", Media Release, February 15, 2007.
  23. James Richens, "King coal promises to clean up", ENDS Report 396, January 2008, pp 26-29.
  24. C.GEN, "C.GEN North Killingholme Power Project", accessed March 15, 2011.
  25. 25.0 25.1 C.GEN, "Project Killingholme", CGEN website, accessed September 2014.
  26. 26.0 26.1 "Planning," C.GEN website, accessed July 2014
  27. "Green light for North Killingholme power plant," EIC, 19 September, 2014
  28. "C.GEN North Killingholme Power Project," Global CCS Institute, updated 9/7/2014
  29. "Killingholme Project Fact Sheet: Carbon Dioxide Capture and Storage Project," CCST, MIT, updated Jan 25, 2016
  30. "Killingholme Project Fact Sheet: Carbon Dioxide Capture and Storage Project," CCST, MIT, updated Jan 5, 2015
  31. "White Rose CCS Project," Global CCS Institute, updated 7/5/2015
  32. "CCS SCHEME CLOSURE NEARS," Insider Media, 22 Jan 2016
  33. "Energy secretary refuses planning consent for White Rose CCS scheme," Utility Week, 19/04/2016
  34. "North Killingholme Power Project," C.GEN, accessed May 2017
  35. "£250m new power station at North Killingholme aims to generate in 2021," Grimsby Telegraph, March 24, 2017
  36. "Killingholme Power station". Uniper. March 22nd, 2021. Retrieved April 24th, 2022. {{cite web}}: Check date values in: |access-date= and |date= (help)CS1 maint: url-status (link)

Additional data

To access additional data, including interactive maps of the power stations, downloadable datases, and summary data, please visit the Global Coal Plant Tracker and the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.