Mitsui-Kobe Duqm DRI plant is a steel plant in Duqm, Al Wusta, Oman that operates direct reduced iron (DRI) technology.
Location
The map below shows the approximate location of the plant in Duqm, Al Wusta, Oman:
Location: Special Economic Zone Authority of Duqm (SEZAD), Duqm, Al Wusta, Oman
Coordinates (WGS 84 ): 19.529594, 57.61573 (approximate)
Background
The Mitsui-Kobe Duqm DRI plant aim to produce 5000 ttpa of DRI using MIDREX technologies. The plant aims to start production in 2027. Future plans include enhancing decarbonization by replacing methane with hydrogen while also increasing production capacity.[ 1]
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker , a project of Global Energy Monitor.
Low-emissions/green steelmaking
This steel plant is associated with a green steel project tracked in the Green Steel Tracker . Details about the project are included below.
Table 1: Green Steel Project Details
All references for the above data are available in the Green Steel Tracker .
Project 1
Project name
Kobe Steel Oman DRI Duqm
Company
Kobe Steel, Ltd.
Company has climate goals?
Yes
Location
Duqm, Oman
Project website
Not available
Project scale
Full scale
Project status
Announced
Technology to be used
NG-DRI
Technology details
MIDREX Flex™ technology using NG, compatible with hydrogen (but no timeline for transition)
Iron production capacity (million tonnes per year)
5
Steel production capacity (million tonnes per year)
Not applicable
CO2 capture (million tonnes CO2 per year)
Not stated
Hydrogen generation capacity (MW)
Not applicable
Investment size (m USD)
Not stated
Partners
Midrex, Mitsui & Co., Ltd.
Date of announcement
6/1/2023
Plant Details
Table 2: General Plant Details
Announced date
Start date
2023[ 2]
2027[ 3]
Table 3: Ownership and Parent Company Information
Parent company
Parent company PermID
Parent GEM entity ID
Owner
Owner company PermID
Owner GEM entity ID
Kobe Steel Ltd; Mitsui & Co Ltd
4295877348; 4295880574
E100000000647; E100000000651
Mitsui-Kobe Steel JV [100%][ 3]
unknown
E100001010358 [100%]
Table 4: Process and Products
Table 5: Plant-level Crude Iron Production Capacities (thousand tonnes per annum)
1 Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Capacity operating status1
Sponge iron/DRI capacity
Nominal iron capacity (total)
announced
5000[ 4]
5000[ 4]
Table 6: Upstream Products Production Capacities (thousand tonnes per annum)
Unit Details
Table 7: Direct Reduced Iron Furnace Details
Unit name
Status
Start date
Furnace manufacturer and model
Furnace type
Current capacity (ttpa)
unknown DRI (1)
announced[ 2] [ 5]
2027[ 6] [ 7]
Midrex Midrex Flex[ 8] [ 9]
shaft furnace
5000[ 4]
Table 8: Direct Reduced Iron Furnace Reductant Details
Unit name
Current or initial reductant
Gas reductant
Hydrogen reductant status
unknown DRI (1)
gas[ 8]
syngas (reformed methane)[ 8]
capable[ 6]
Articles and Resources
Additional data
To access additional data, including an interactive map of steel plants, a downloadable dataset, and summary data, please visit the Global Iron and Steel Tracker on the Global Energy Monitor website.
References
Resources