Mukand Sumi Special Steel Hospet steel plant
| This article is part of the Global Iron and Steel Tracker, a project of Global Energy Monitor. |
| Sub-articles: |
Mukand Sumi Special Steel Hospet steel plant is a steel plant in Kanakapur, Ginigera, Koppal, Karnataka, India that operates blast furnace (BF) and steelmaking technology.
Location
The map below shows the exact location of the plant in Kanakapur, Ginigera, Koppal, Karnataka, India:
- Location: Hospet
- Coordinates (WGS 84): 15.328976, 76.258613 (exact)
Background
In August 2021, Mukand Sumi Special Steel Limited (MSSSL) shifted its manufacturing activities entirely to Hospet (Karnataka) by commissioning a new 400 ttpa facility. MSSSL was earlier operating from its 500 ttpa Kalwe unit in Thane (Maharashtra). From August 2022, the alloy steel business of Mukand Sumi Metal Processing Limited (MSMPL) was merged into MSSSL.[1]
MSSL announced that it will invest INR 2,345 crore to set up a greenfield project in Hospet, which will increase its production capacity to 700 ttpa.[2]
MSSSL has placed an order with Danieli for a new blooming mill, which will be installed at its Hospet plant in September 2025. It is expected to be operational by the end of 2026.[3]
Plant Details
Table 1: General Plant Details
| Start date |
|---|
| 2021-08[4] |
Table 2: Ownership and Parent Company Information
| Parent company | Parent company PermID | Parent GEM entity ID | Owner | Owner company PermID | Owner GEM entity ID |
|---|---|---|---|---|---|
| Jamnalal Sons Pvt Ltd [51.0%]; Sumitomo Corp [49.0%] | 5037050765 [51.0%]; 5000000997 [49.0%] | E100002007558 [51.0%]; E100000000657 [49.0%] | Mukand Sumi Special Steel Ltd [100%][5] | 5064525055 | E100002019744 [100%] |
Table 3: Process and Products
| Steel product category | Steel products | ISO 14001 | ISO 50001 | Main production equipment |
|---|---|---|---|---|
| finished rolled[6] | bars, wire rod[7][6] | yes[8] | no[8] | BF; Steel other/unspecified |
Table 4: Plant-level Crude Steel Production Capacities (thousand tonnes per annum)
| Capacity operating status1 | Other/unspecified steelmaking capacity | Nominal crude steel capacity (total) |
|---|---|---|
| announced | 250[9] | 250[9] |
| operating | 450[10] | 450[10] |
Table 5: Plant-level Crude Iron Production Capacities (thousand tonnes per annum)
| Capacity operating status1 | Blast furnace capacity | Nominal iron capacity (total) |
|---|---|---|
| operating | 450[6][10] | 450[6][10] |
Table 6: Actual Plant-level Crude Steel Production by Year (thousand tonnes per annum)
| Year | Other/unknown steel production | Total (all routes) |
|---|---|---|
| 2022 | unknown[11] | –[11] |
| 2023 | 358[11] | 358[11] |
| 2024 | 350[8] | 350[8] |
Table 7: Actual Plant-level Crude Iron Production by Year (thousand tonnes per annum)
| Year | BF production |
|---|---|
| 2022 | unknown |
| 2023 | unknown |
| 2024 | unknown |
Unit Details
Table 8: Blast Furnace Details
| Unit name | Status | Furnace manufacturer and model | Current size | Current capacity (ttpa) |
|---|---|---|---|---|
| unknown BF (1) | operating[6] | Mini blast furnace[6] | 250.0[6] | 132[6][10] |
| unknown BF (2) | operating[6] | Mini blast furnace[6] | 250.0[6] | 132[6][10] |
| unknown BF (3) | operating[6] | Mini blast furnace[6] | 350.0[6] | 186[6][10] |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel plants, a downloadable dataset, and summary data, please visit the Global Iron and Steel Tracker on the Global Energy Monitor website.
References
- ↑ "Mukand Sumi Special Steel Limited: Rating upgraded; rated amount enhanced". ICRA Ratings. 2024-01-05. Retrieved 2025-11-05.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Mukand Sumi Special Steel to invest Rs 2,300 cr in greenfield project in Karnataka". The Economic Times. Retrieved 2025-11-05.
- ↑ "Danieli". www.danieli.com. Retrieved 2025-11-05.
- ↑ https://www.icra.in/Rating/ShowRationalReportFilePdf/124674.
{{cite web}}: Missing or empty|title=(help) - ↑ https://www.steelorbis.com/steel-news/latest-news/indias-msssl-plans-agreenfield-special-steel-production-facility-in-karnataka-1407714.htm.
{{cite web}}: Missing or empty|title=(help) - ↑ 6.00 6.01 6.02 6.03 6.04 6.05 6.06 6.07 6.08 6.09 6.10 6.11 6.12 6.13 6.14 6.15 https://www.mukandsumi.com/manufacturing-processes/.
{{cite web}}: Missing or empty|title=(help) - ↑ (PDF) https://www.mukandsumi.com/wp-content/uploads/2025/09/Press_Note_MSSSL_Expansion_Project.pdf.
{{cite web}}: Missing or empty|title=(help) - ↑ 8.0 8.1 8.2 8.3 (PDF) https://www.mukand.com/wp-content/uploads/2025/07/Mukand-Limited_Final-low-2025.pdf.
{{cite web}}: Missing or empty|title=(help) - ↑ 9.0 9.1 https://economictimes.indiatimes.com/industry/indl-goods/svs/steel/mukand-sumi-special-steel-to-invest-rs-2300-cr-in-greenfield-project-in-karnataka/articleshow/123636640.cms?from=mdr.
{{cite web}}: Missing or empty|title=(help) - ↑ 10.0 10.1 10.2 10.3 10.4 10.5 10.6 https://www.mukandsumi.com/alloy-manufacturing-plant-india/.
{{cite web}}: Missing or empty|title=(help) - ↑ 11.0 11.1 11.2 11.3 https://www.mukand.com/investors/financial-performance/.
{{cite web}}: Missing or empty|title=(help)