Mustika Indah Permai coal mine

From Global Energy Monitor

The Mustika Indah Permai (MIP) coal mine is a proposed project, operated by Pt Mustika Indah Permai, a subsidary of Adaro Energy, with a potential capacity of 1 million tonnes per annum, in the Lahat regency, South Sumatra province, Indonesia.[1]

Location

The map below shows the approximate location of Mustika Indah Permai within Kabupaten, Lahat, South Sumatra, Indonesia near "critical infrastructure such as the state highway and railway."[1][2]

Loading map...

Background

MIP's majority owner, Adaro Energy, states on its website that it "plans to commence operations from MIP in the later part of 2019, depending on market situation."[3]

In 2012, MIP's majority owner, Adaro Energy, stated "MIP has completed a detailed 30 year mine plan and set up offices in Lahat in 2011. Adaro Energy plans to produce coal at MIP, using an open-pit mining method, by the end of 2012. Coal production will be ramped up to three to four million tonnes per year by 2014. Adaro Energy plans to boost MIP's production up to ten million tonnes per annum five years from the time operations commence."[4]

MIP is on a 20 year IUP concession granted in 2010.[2]

Project Details

  • Owner: PT Mustika lndah Permai (MIP)[1]
  • Parent company: Adaro Energy[2]
  • Location: Kabupaten, Lahat regency, South Sumatra province, Indonesia[2][4]
  • GPS coordinates: -3.800844, 103.407830 (approximate)[2]
  • Mine status: proposed
  • Start year:’
  • Capacity: 1 MTPA [4]
  • Additional proposed production: 10 million tons per annum[4]
  • Mineable reserves:254 MT[3]
  • Coal type: subbituminous[3]
  • Mine size: 2,000 hectares[2]
  • Number of employees:

Articles and resources

References

  1. 1.0 1.1 1.2 Alexander Ginting (Publisher), Robert Sihotang (Project Leader), Reiner Simanjuntak, Johannes Simbolon, Tyasno Hery, Rudi Simangunsong, Adianto Simamora, Godang Sitompul, Romel S., Yuda Prihatna, Abdul Karim, lpunk AF [Paper Copy, Indonesian Coal Book 2020/2021] Petromindo.Com, May 2016 Release
  2. 2.0 2.1 2.2 2.3 2.4 2.5 Wood Macenzie Mustika Indah Permai coal mine Asset Report, August 27, 2019
  3. 3.0 3.1 3.2 Adaro Adaro Mining Organizational Site, accessed Dec 14, 2019
  4. 4.0 4.1 4.2 4.3 Devindra Ratzarwin Adaro Energy Completes JORC Report for Mustika Indah Permai Coal Reserves Estimated at 272.6 Million Tonnes South Sumatra Investments Will Soon Commence Operations and Generate Cash, Adaro Energy Press Release, Market Screener, March 22, 2012

Related GEM.wiki articles

External resources

External articles