Nanning-Pingxiang Gas Pipeline
| Part of the Global Gas Infrastructure Tracker, a Global Energy Monitor project. |
Nanning-Pingxiang Gas Pipeline (南宁-凭祥支线) is a gas pipeline in Guangxi, China with segments that are operating and proposed. It is classified as part of the Guangxi Provincial Gas Network.
See all Chinese pipeline network groupings here.
Location
Table 1: Route details
| Route | Segment | Start/end | Countries/areas |
|---|---|---|---|
| Nanning-Chongzuo Segment | Start: Mu Village, Jiangxi Town, Jiangnan District, Guangxi [1]End: Busong Village, Jiangzhou Town, Jiangzhou District, Guangxi
|
China | |
| Chongzuo-Pingxiang segment | Start: Guangxi [2]End: Guangxi
|
China |
2 of 2 segments have a mapped route in the database.
■ Operating ■ Proposed
Project details
Table 2: Pipeline details
| Segment | Status | Fuel | Capacity | Length | Diameter | Pressure |
|---|---|---|---|---|---|---|
| Nanning-Chongzuo Segment | operating[3] | gas[3] | 0.7 bcm/y[3] | 125 km[3] | 457 mm[3] | 6.30 MPa[3] |
| Chongzuo-Pingxiang segment | proposed[2] | gas[2] | 0.5 bcm/y[2] | 100.1 km[2] | 406.4 mm[2] | 6.3 MPa[2] |
Table 3: Project timeline
| Segment | Proposal year | FID | Construction year | Start year |
|---|---|---|---|---|
| Nanning-Chongzuo Segment | 2022[4] | – | – | 2025[3] |
| Chongzuo-Pingxiang segment | 2025[2] | – | – | – |
Table 4: Cost
| Segment | Cost |
|---|---|
| Nanning-Chongzuo Segment | CNY 689.36 million (US$110.3 million)[4] |
| Chongzuo-Pingxiang segment | – |
Table 5: Ownership
| Segment | Operator | Owner | Parent |
|---|---|---|---|
| Nanning-Chongzuo Segment | – | Nanning Oil and Gas Transportation Branch of State Pipe Network Group Southwest Pipeline Co Ltd (100%) | – |
| Chongzuo-Pingxiang segment | – | – | – |
Background
The Nanning-Pingxiang Gas Pipeline is a branch line of the Guangxi Gas Pipeline Network. It runs west from Nanning toward Pingxiang, a city on the border with Vietnam, and is planned in two segments. The Guangxi Development and Reform Commission approved the Nanning-Chongzuo segment in September 2022.[4] The Guangxi regional government approved the construction land for its Chongzuo section in May 2024.[5] That segment began operating in 2025.[3] The Chongzuo-Pingxiang segment was proposed in 2025.[2]
Articles and resources
References
- ↑ "sthjt.gxzf.gov.cn/zfxxgk/zfxxgkgl/fdzdgknr/hjjccf/xzxk/npzxm/P020220624356740936889.pdf" (PDF). sthjt.gxzf.gov.cn. Retrieved 2026-11-10.
- ↑ 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 "iscm.pipechina.com.cn:8443/detail.html?pageType=5&tab=1&index=1389269434581721089". iscm.pipechina.com.cn:8443. Retrieved 2026-11-10.
- ↑ 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 "gx.xinhuanet.com/20250606/032105f0711e4633a1f26693d3eba852/c.html". gx.xinhuanet.com. Retrieved 2026-11-10.
- ↑ 4.0 4.1 4.2 "fgw.gxzf.gov.cn/zfxxgkzl/wjzx/xmpf/xiangmuhezhunpifu/t14899151.shtml". fgw.gxzf.gov.cn. Retrieved 2026-11-10.
- ↑ 广西壮族自治区人民政府关于南宁-凭祥支线(南宁-崇左段)(崇左段)项目 建设用地的批复, 广西壮族自治区人民政府, 2024-05-27
Additional data
To access additional data, including an interactive map of gas pipelines, a downloadable dataset, and summary data, please visit the Global Gas Infrastructure Tracker on the Global Energy Monitor website.