OMK Ecolant steel plant (Металлургический завод Эколант (Russian)), also known as OMK Vyksa, is a 1800 thousand tonnes per annum (TTPA) direct reduced iron (DRI) and electric arc furnace (EAF) steel plant under construction in Vyksa, Nizhny Novgorod, Russia.

Location

The map below shows the location of the steel plant in Vyksa, Nizhny Novgorod, Russia.

Loading map...
  • Location: Vyksa, Nizhny Novgorod Oblast, Russia[1][2]
  • Coordinates (WGS 84): 55.323946, 42.150702 (approximate)

Background

The plant might supply some of its steel to the OMK Vyksa Casting and Rolling Complex.[3][4]

In January 2023, OMK was looking into buying the Prioskolskoye iron ore deposit as it did not have its own source of iron ore for the Ecolant steel plant.[5]

As of October 2023, the construction is ongoing, however, it is unclear what company will be supplying equipment for the project on the background of sanctions imposed as a result of the Russia's invasion of Ukraine.[6] Previously, Italian company Danieli had been contracted for the job.[7]

Plant Details

Table 1: General Plant Details

Plant status Construction date Start date Workforce size
construction[8][2][9] 2020[10] 2025[11][12][9][8][13] 700[14]

Table 2: Ownership and Parent Company Information

Parent company Parent company PermID Owner Owner company PermID
Obyedinennaya Metallurgicheskaya Kompaniya AO [100%][8][15] 5000073496 [100%] OOO Ecolant[15][16][2] GEM0000171

Table 3: Process and Products

Steel product category Steel products Steel sector end users Main production equipment Detailed production equipment
semi-finished[8][17] slab; round billet[8][17] building and infrastructure; energy; transport[8][17] direct reduced iron (DRI) and electric arc furnace (EAF)[8] A DRI unit based on ENERGIRON technology, a system for feeding hot pellets into an EAF, a 1.8 mt EAF (180-ton) , a ladle furnace, a vacuum degasser, a gas cleaning system and a continuous casting machine; supplied by Italian engineering company Danieli[8][10]

Table 4: Crude Steel Production Capacities (thousand tonnes per annum):

Electric arc furnace steelmaking capacity Nominal crude steel capacity (total)
1800 TTPA[12][18][19][20] 1800 TTPA

Table 5: Crude Iron Production Capacities (thousand tonnes per annum):

Sponge iron/DRI capacity Nominal iron capacity (total)
2500 TTPA[21][20] 2500 TTPA

Articles and Resources

References

  1. https://web.archive.org/web/20211129025949/https://ecolant.net/news/kommersant-ekolant-v-vykse-budut-stroit-na-usloviyakh-spetsialnogo-investkontrakta/. Archived from the original on 2021-11-29. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 https://web.archive.org/web/20220320172305/https://www.kommersant.ru/doc/4829311. Archived from the original on 2022-03-20. {{cite web}}: Missing or empty |title= (help)
  3. "Ecolant (About the project)". Ecolant. Retrieved Feb 2, 2022.{{cite web}}: CS1 maint: url-status (link)
  4. "OMK to build complex to make steel in DRI pellet-fed electric arc furnace". S&P Global. Sep 2, 2020. Retrieved Feb 2, 2022.{{cite web}}: CS1 maint: url-status (link)
  5. "ОМК окопается в Белгороде (Russian)". Коммерсант. January 17, 2023. Retrieved October 10, 2023.{{cite web}}: CS1 maint: url-status (link)
  6. "ОМК: по дороге в «санкционный клуб»? (Russian)". ФИНАМ. February 28, 2023. Retrieved October 10, 2023.{{cite web}}: CS1 maint: url-status (link)
  7. "Danieli to supply EAF meltshop and bloom caster to OMK/s Vyksa works". www.steelorbis.com. September 9, 2020. Retrieved October 10, 2023.{{cite web}}: CS1 maint: url-status (link)
  8. 8.0 8.1 8.2 8.3 8.4 8.5 8.6 8.7 https://web.archive.org/web/20220320120524/https://www.spglobal.com/commodity-insights/en/market-insights/latest-news/metals/090220-omk-to-build-complex-to-make-steel-in-dri-pellet-fed-electric-arc-furnace. Archived from the original on 2022-03-20. {{cite web}}: Missing or empty |title= (help)
  9. 9.0 9.1 https://web.archive.org/web/20221012005126/https://tass.ru/ekonomika/13654391. Archived from the original on 2022-10-12. {{cite web}}: Missing or empty |title= (help)
  10. 10.0 10.1 https://web.archive.org/web/20200917144433/https://www.steelorbis.com/steel-news/latest-news/danieli-to-supply-eaf-meltshop-and-bloom-caster-to-omks-vyksa-works-1163035.htm. Archived from the original on 2020-09-17. {{cite web}}: Missing or empty |title= (help)
  11. https://web.archive.org/web/20220126174805/https://www.finanz.ru/novosti/aktsii/italyanskaya-danieli-postavit-oborudovanie-dlya-elektrometallurgicheskogo-kompleksa-omk-1029553235. Archived from the original on 2022-01-26. {{cite web}}: Missing or empty |title= (help)
  12. 12.0 12.1 https://web.archive.org/web/20210720143045/https://sber.pro/publication/kliuchevye-sobytiia-i-trendy-metallurgicheskoi-otrasli-v-2021-godu. Archived from the original on 2021-07-20. {{cite web}}: Missing or empty |title= (help)
  13. (PDF) https://www.oecd.org/industry/ind/latest-developments-in-steelmaking-capacity-2022.pdf. {{cite web}}: Missing or empty |title= (help)
  14. https://ecolant.net/(planned). {{cite web}}: Missing or empty |title= (help)
  15. 15.0 15.1 https://web.archive.org/web/20220318235558/https://omk.ru/press/news/32865/. Archived from the original on 2022-03-18. {{cite web}}: Missing or empty |title= (help)
  16. https://web.archive.org/web/20220319104240/https://sbis.ru/contragents/5247046110/524701001. Archived from the original on 2022-03-19. {{cite web}}: Missing or empty |title= (help)
  17. 17.0 17.1 17.2 https://web.archive.org/web/20220629172159/http://ecolant.net/. Archived from the original on 2022-06-29. {{cite web}}: Missing or empty |title= (help)
  18. https://web.archive.org/web/20220812023133/https://metallobazy.ru/news/1844. Archived from the original on 2022-08-12. {{cite web}}: Missing or empty |title= (help)
  19. (PDF) https://web.archive.org/web/20220111173338/https://www.oecd.org/industry/ind/latest-developments-in-steelmaking-capacity-2021.pdf. Archived from the original (PDF) on 2022-01-11. {{cite web}}: Missing or empty |title= (help)
  20. 20.0 20.1 https://web.archive.org/web/20220126174501/https://omk.ru/vyksa/publications/32577/. Archived from the original on 2022-01-26. {{cite web}}: Missing or empty |title= (help)
  21. https://web.archive.org/web/20200926174520/https://www.danieli.com/en/news-media/news/omk-contracts-danieli-new-2-5-mtpy-direct-reduction-plant_37_570.htm. Archived from the original on 2020-09-26. {{cite web}}: Missing or empty |title= (help)

Other resources



Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.