Patuakhali power station (Ashuganj)

From Global Energy Monitor

Patuakhali power station is a proposed 1,320-megawatt (MW) coal-fired power plant in Barisal division, Bangladesh.

Another 1,320-MW phase (phase 2) was proposed for the Patuakhali power station (Ashuganj) for commissioning by 2030,[1] but it was cancelled in June 2021.[2]

There are three different proposals for 1,320-MW coal-fired power stations in Patuakhali, by three sets of sponsors, all joint ventures between Bangladeshi and Chinese firms:


Location

The map below shows the general location of the project's site in Kalapara upazali, Patuakhali district, Barisal division, based on land acquisition.[3]

Loading map...

Background

In November 2018, Bangladesh published a document titled Revisiting Power System Master Plan (PSMP) 2016. The document included forecasts of power demand growth under various scenarios and outlined the power capacity to be added out to 2041. It included two phases for the proposed Patuakhali power station, to be owned by Bangladesh’s state-run Ashuganj Power Station Company Limited (APSCL). The first phase was proposed as 1,320 MW and expected to be commissioned by December 2024. The second phase was proposed as 1,320 MW and expected to be commissioned by December 2030.[1]

In July 2017, Ashuganj Power and China Energy Engineering Corporation signed an MoU to build phase 1 (2x660 MW) as a 50:50 joint venture. The Chinese partner agreed to arrange loans from the Export Import Bank of China for the project. The plant was planned to be ultra supercritical using imported coal of around 12,000 tonnes of coal per day from Indonesia, India, or Australia. Bangladesh’s state-owned West Zone Power Distribution Company Limited would build a transmission line from the proposed plant to Patuakhali sub-station to connect the national power grid. The first 660-MW unit was expected to be commissioned in 2021 and the second unit in 2023.[4][5]

Phase 1: "Land Acquisition, Land Development, and Protection" project

In February 2018, the project's sponsors stated that they planned to have land acquisition completed by December 2019.[6][7] The plant was planned for commissioning in 2024.[1]

Ashuganj Power's December 2020 Annual Report noted that "The acquisition of 930.615 acres of land for the project is almost finished. Within a very short period, land development and protection activities will be started."[3] It provided additional updates on the land acquisition, land development, and protection project for the construction of the 1,320 MW power station, including the following:

"Appointment of the consultant is in process for planning, design, drawing, cost estimation with BOQ and supervision of land development, embankment, earth protection, resettlement structural components, civil works (residential/non-residential), and all other related civil & electrical works. Negotiation has already been completed with the 1st ranked Firm. The contract will be executed very soon. However, the ongoing work of acquiring land and selection of a consultant is hampered due to the Covid-19 situation. Thereby the implementation of the project is a little bit delayed."[3]

The rough map of the project provided in the Annual Report masks that the land being acquired is primarily agricultural land and includes several waterways:[3]

Screen Shot 2021-09-22 at 6.57.34 PM.png


In September 2021, Bangladesh's National Portal for Ashuganj Power noted that the "Land Acquisition, Land Development and Protection" project's "physical progress" was 28.90% complete and "financial progress" 27.49% complete.[8]

Cancellation risk & cancellation

In August 2020, signalling a potential pivot in Bangladesh away from coal power towards increased reliance on gas-based power from imported liquified natural gas (LNG), Bangladesh’s minister of power, energy and mineral resources, Nasrul Hamid stated that the government was planning to review an array of planned coal plants with the exception of three which were in construction and nearing completion: the Rampal power station, the Matarbari power station and the Payra power station. According to Minister Hamid, "We are reviewing how we can move from coal-based power plants." Patuakhali power station (Ashuganj) was, therefore, likely to be reviewed by the government.[9]

On November 19, 2020, The Daily Star reported that Bangladesh's power, energy and mineral resources ministry had finalized an energy plan that cancelled all coal plants except five under construction. Patuakhali power station (Ashuganj) would potentially be cancelled as a result. The ministry was going to send the plan to the Prime Minister's Office for review.[10]

Phase 2 cancelled by government

In June 2021, the Bangladesh State Minister for Power, Energy, and Mineral Resources announced the government was officially dropping ten coal plant projects in its master energy plan totaling over 8 GW of power due to delays in implementation. The Patuakhali power station by Ashuganj Power was among the ten cancelled coal plants. The cancellation only appears to apply to station's second phase, which was expected to be commissioned by 2030.[2]

Opposition

In November 2019, in a report titled "Choked by Coal: The Carbon Catastrophe in Bangladesh," Market Forces and various other organizations highlighted the corruption, malpractice, and violations of human rights that have occurred in relation to land acquisition and relocation processes for many projects in Bangladesh.[11]

A May 2020 analysis by the Center for Research on Energy and Clean Air (CREA) found that seven coal-fired power plants proposed in the area would constitute one of the largest air pollutant, mercury, and CO2 emissions hotspots in South Asia and the world.[12]

Project Details

  • Sponsor: Ashuganj Power Station Company Limited (APSCL), China Energy Engineering Corporation
  • Parent company: Ashuganj Power Station Company Limited (APSCL), China Energy Engineering Corporation
  • Location: Dhankhali union, Kalapara upazali, Patuakhali district, Barisal division
  • Coordinates: 22.056481, 90.319494 (exact)
  • Status: Phase 1: Pre-Permitted, Phase 2: Cancelled
  • Gross Capacity: Phase 1: 1320 MW (2 x 660 MW), Phase 2: 1320 MW (2 x 660 MW)
  • Type: Ultra-supercritical
  • Projected in service: Phase 1: 2024, Phase 2: 2030
  • Coal Type:
  • Coal Source: Indonesia, India, or Australia
  • Source of financing: Phase 1: Export Import Bank of China
  • Permits and applications:

Contact details

Website: http://www.bpdb.gov.bd/

Articles and resources

References

  1. 1.0 1.1 1.2 "Revisiting Power System Master Plan (PSMP) 2016," Power Division, Ministry of Power, Energy and Mineral Resources Government of the People’s Republic of Bangladesh, published November 2018
  2. 2.0 2.1 "10 coal-fired power projects scrapped as part of master plan revision," UNB, June 27, 2021
  3. 3.0 3.1 3.2 3.3 "Annual Report 2019-2020," Ashuganj Power Station Company Ltd., December 27, 2020
  4. "Bangladesh Ropes In China Energy For 1,320-MW Power Project," Asia Power, July 18, 2017
  5. "Faster Rampal plant execution demanded," bdnews24.com, October 13, 2013
  6. "No progress in 19 power plants yet," The Bangladesh Post, March 9, 2018
  7. Govt to acquire 931 acres land, The Asian Age, February 26, 2018
  8. "Land Acquisition, Land Development and Protection for Patuakhali 1320 MW Super Thermal Power Plant Project," Bangladesh National Portal, accessed September 22, 2021
  9. Tom Baxter, "Bangladesh may ditch 90% of its planned coal power," China Dialogue, August 27, 2020
  10. "Future not coal power," The Daily Star, November 19, 2020
  11. "Choked by Coal: The Carbon Catastrophe in Bangladesh of their homes and farmlands," Market Forces, November 2019
  12. "Air quality, health and toxics impacts of the proposed coal power cluster in Payra, Bangladesh," Center for Research on Energy and Clean Air, May 2020

Related GEM.wiki articles