Pirpainti Thermal Power Station
| Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
| Related coal trackers: |
Pirpainti Thermal Power Station is a power station in Pirpainti, Bhagalpur, Bihar, India with multiple units of varying statuses, none of which are currently operating. It is also known as Pirpainti Bijlee, Bhagalpur power project.
Location
Table 1: Project-level location details
| Plant name | Location | Coordinates (WGS 84) |
|---|---|---|
| Pirpainti Thermal Power Station | Pirpainti, Bhagalpur, Bihar, India | 25.307395, 87.412455 (approximate)[1] |
Project Details
Table 2: Unit-level details
| Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Emergency/Backup |
|---|---|---|---|---|---|---|
| Unit 1 | Construction | coal: unknown | 800[2] | ultra-supercritical[3] | 2029 (planned)[4] | False |
| Unit 2 | Construction | coal: unknown | 800[2] | ultra-supercritical[3] | 2029 (planned)[4] | False |
| Unit 3 | Permitted[5] | coal: unknown | 800[2] | ultra-supercritical[3] | 2030 (planned)[4] | False |
| Unit 4 | Pre-permit | coal: unknown | 800 | ultra-supercritical | - | False |
| Unit 5 | Pre-permit | coal: unknown | 800 | ultra-supercritical | - | False |
| Unit 6 | Pre-permit | coal: unknown | 800 | ultra-supercritical | - | False |
Table 3: Unit-level ownership and operator details
| Unit name | Owner | Parent |
|---|---|---|
| Unit 1 | Adani Power Ltd [100%][3] | Adani Power Ltd [100.0%] |
| Unit 2 | Adani Power Ltd [100%][3] | Adani Power Ltd [100.0%] |
| Unit 3 | Adani Power Ltd [100%][3] | Adani Power Ltd [100.0%] |
| Unit 4 | Adani Power Ltd [100%][3] | Adani Power Ltd [100.0%] |
| Unit 5 | Adani Power Ltd [100%][3] | Adani Power Ltd [100.0%] |
| Unit 6 | Adani Power Ltd [100%][3] | Adani Power Ltd [100.0%] |
Project-level coal details
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.
Background
The project was proposed by the Pirpainti Bijlee Company, with power to be sold to the Bihar State Electricity Board. The Bihar State Electricity Board stated that the project would require 6.25 million tonnes of coal, an allocation which was sought in 2006. BSEB also stated that 1171 acres was identified for acquisition via the Industrial Development Authority (IDA) of Bihar and that the Water Resources Department gave consent for 55 Cusecs to be allocated from the Ganga River for the project. BSEB also stated that the environmental impact assessment report was completed and public hearings on it held in July 2010.[6]
In February 2014, a memorandum of understanding (MoU) was signed amongst Bihar State Power Generation Company, NHPC and Pirpainti Bijlee Company for development of the 1,320 MW Pirpainti power station. NHPC and Bihar State Power Generation Company were to develop the project through the joint venture Pirpainti Bijlee Company.[7]
The power station was originally scheduled to be commissioned in 2015-16,[6] but faced ongoing public opposition.[8]
In January 2016 it was reported the MoU for the plant would expire by the following month, and the project sponsors made no communication about an extension.[9]
As of May 2016 the project had yet to receive environmental clearance from the India MoEF.
Based on updates posted on the BSPHCL website, there were no developments of the project since 2010, and it appeared to be abandoned.[10]
In 2018 Odisha’s energy minister Susanta Singh requested Union power minister RK Singh to cancel PPAs between the state and NTPC for the 1,320-MW Pirpainti Thermal Power Station, on the back of surplus generation capacity in the state.[11]
2024 Revival
According to reporting from February 2024, the Bihar state government had revived the coal plant proposal at Pirpainti. Land had already been acquired for the project, which would have a capacity of 2,400 MW (3 x 800 MW).[12]
As of July 2024, the proposed power station was awaiting approval from the Union Coal Ministry. Bihar state officials reportedly expected the entire project to be completed within five years.[13] In September 2024, the Bihar government reportedly requested that the Union Coal Ministry provide a coal linkage from Rajmahal in the neighboring state of Jharkhand.[14]
In January 2025, the Bihar state government was reportedly planning to seek bids for the proposed power station by March 2025. According to a government official, environmental clearances for the project would be expedited.[15][16]
In March 2025, the Bihar government approved the construction of the proposed 2,400 MW coal plant in Pirpainti. A previous proposal for a solar plant in Pirpainti was reportedly replaced with the coal plant proposal after a technical survey found that coal was a “more viable option due to the availability of coal and favorable land conditions.” The Bihar State Power Generation Company was slated to oversee construction of the coal project.[17]
By June 2025, four private companies — Adani Power, JSW Energy, Torrent Power, and Bajaj Group’s Lalitpur Power — had expressed interest in establishing the proposed power station under a Tariff-based Competitive Bidding (TBCB) process. The Pirpainti power station would reportedly be Bihar’s first private investment in the power sector, at an estimated cost of Rs 28,000 crore.[18] As of June 2025, the proponent had not yet secured its Terms of Reference (ToR) or Environmental Clearance (EC).
In August 2025, Adani Power received a letter of intent from the Bihar state government to supply power from the Pirpainti Thermal Power Station to North Bihar Power Distribution Company Ltd. (NBPDCL) and South Bihar Power Distribution Company Ltd. (SBPDCL). Adani said its winning bid included a final power supply price of Rs 6.075 per kilowatt-hour (6.9 US cents per kWh). The company planned to build the proposed 3 x 800 MW ultra-supercritical plant under a Design, Build, Finance, Own, and Operate (DBFOO) model, and expected to commission the first unit within 48 months of finalizing the contract. The entire US$3 billion plant was slated to be completed within five years.[19][20]
In September 2025, Adani Power signed a 25-year Power Supply Agreement with the Bihar State Power Generation Company Ltd. (BSPGCL) to build the proposed Pirpainti Thermal Power Station. As part of the agreement, Adani Power will reportedly pay one rupee per year (US$11.50) for approximately 1020 acres (413 hectares) of land.[21]
In late September 2025, the Expert Appraisal Committee (EAC) recommended Terms of Reference (ToR) for the Pirpainti Thermal Power Station project.[22] A ToR certificate was issued in October 2025.[23]
In April 2026, the power station was granted Environmental Clearance (EC).[24]
In May 2026, the Pirpainti power station was included in the monthly Broad Status report of under-construction thermal power projects, but physical progress was listed at 0%. The report indicated that Units 1 and 2 were expected to start operating in 2029, and Unit 3 was expected in 2030.[25]
By September 2026, Units 1 and 2 had started construction.[26]
Proposed Phase II
In August 2026, Adani Power sought fresh Terms of Reference (ToR) for a proposed 2,400 MW (3 x 800 MW) ultra-supercritical Phase II expansion at Pirpainti. In September 2026, the Expert Appraisal Committee (EAC) of the Ministry of Environment, Forest and Climate Change recommended ToR be granted for Phase II.[27] A ToR certificate was issued in late September 2026.[28]
Previous proposals
According to the website Bihar Days (2011), Ganga Power & Natural Resources (GPNR) Ltd signed a memorandum of understanding (MoU) with Bihar State Electricity Board (BSEB) for setting up a super critical thermal power project (2×660 MW) at Pirpainty in Bhagalpur district, to begin operation in 2014.[29]
Financing
As of July 2024, the project cost was estimated at Rs 21,400. As of July 2024, the state was awaiting the the concurrence of the Union Coal Ministry before firming up its collaboration in the construction of the plant, and the equity sharing among partners.[13]
In August 2025, Adani Power said it had received a Letter of Intent from Bihar State Power Generation Company Ltd. to develop and operate the 2,400 MW Pirpainti Thermal Power Station under a Design, Build, Finance, Own, and Operate (DBFOO) model. Adani said the 3×800 MW project would require an investment of approximately US$3 billion.[30] In August 2025, the Bihar Electricity Regulatory Commission adopted the tariff discovered through competitive bidding for procurement from the 2,400 MW project, also describing it as a DBFOO project.[31] As of June 2026, no financial close, debt-equity split, or named debt lender had been identified.
Opposition
In January 2015 groups of farmers whose plots were acquired for the proposed power plant two years ago started mobilising against the project over non-payment of compensation.[8]
According to reporting from September 2025, landowners were continuing to raise concerns about the amount of compensation for the loss of productive agricultural land, including orchards of mangoes and lychees. Some landowners also alleged that productive farmland was misclassified as “barren”, resulting in lower compensation levels.[21]
According to reporting from October and November 2026, residents of the Pahariya and Santhali Adivasi hamlets said they were not consulted about their displacement from the land acquired for the power station. As the groups were reportedly not included in the project’s Environmental Impact Assessment, there was no plan for their compensation or resettlement.[32][33]
Articles and Resources
References
- ↑ 1.0 1.1 (PDF) https://parivesh.nic.in/certificates/Adani_Power_Limited/2/1219515668/V_1_IA_BR_THE_569377_2026_1219515677_-signed.pdf.
{{cite web}}: Missing or empty|title=(help) - ↑ 2.0 2.1 2.2 "Bihar govt gives nod for setting up 2,400 MW coal-fired thermal power plant at Pirpainti". The Times of India. 2024-02-03. Archived from the original on 2024-02-19. Retrieved 2024-02-09.
- ↑ 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 https://www.adani.com/newsroom/media-releases/adani-power-receives-loi-to-develop-and-operate-2400-mw-greenfield-thermal-power-plant-in-bihar.
{{cite web}}: Missing or empty|title=(help) - ↑ 4.0 4.1 4.2 (PDF) https://cea.nic.in/wp-content/uploads/thermal_broad/2026/05/BS_May_2026_Approved.pdf.
{{cite web}}: Missing or empty|title=(help) - ↑ 5.0 5.1 (PDF) https://parivesh.nic.in/utildoc/137845189_1760097285974.pdf.
{{cite web}}: Missing or empty|title=(help) - ↑ 6.0 6.1 Bihar State Electricity Board, "New Projects", Bihar State Electricity Board website, accessed November 2011.
- ↑ "NHPC inks pact for 1,320-mw thermal plant in Bihar," Millenium Post, February 26, 2014.
- ↑ 8.0 8.1 "Compensation derails project," The Telegraph, Jan 6, 2015
- ↑ "Bihar may lose two power projects," Business Standard, Jan 11, 2016
- ↑ "New Power Projects," BSPHCL website, accessed December 2016
- ↑ "NTPC may abandon two units if states renege on PPAs," Financial Express, July 31, 2018
- ↑ "Bihar govt gives nod for setting up 2,400 MW coal-fired thermal power plant at Pirpainti," The Times of India, February 3, 2024
- ↑ 13.0 13.1 “Pirpainti power plant budgeted, Bihar awaits coal ministry's nod,” Energy Central, July 29, 2024
- ↑ “बिहार ने पीरपैंती बिजली घर के लिए मांगा कोयला,” Hindustan, September 18, 2024
- ↑ “Bihar to seek bidders for Pirpainti Plant by March,” Economic Times, January 29, 2025
- ↑ “Bihar to Bid Out 2,400 MW Power Plant by March,” Construction World, January 31, 2025
- ↑ “Nitish govt clears decks for 2400 MW thermal power plant in big boost to Bihar’s power sector,” The Print, March 1, 2025
- ↑ “Four private power companies show interest in setting up 2,400 MW plant at Pirpainti,” Times of India, June 27, 2025
- ↑ “Adani Power receives LoI to develop and operate 2,400 MW greenfield thermal power plant in Bihar,” Adani, August 7, 2025
- ↑ “Adani to build India's biggest privately funded coal power plant in a decade,” Mining Weekly, August 8, 2025
- ↑ 21.0 21.1 “Adani Power Receives 1,020 Acres For Lease In Bihar’s Bhagalpur – At Rs 1 Per Acre Per Year,” The Wire, September 21, 2025
- ↑ Minutes of AGENDA FOR 30th MEETING OF THE EXPERT APPRAISAL COMMITTEE (EAC) (THERMAL POWER PROJECTS) TO BE HELD..., MOEFCC, October 10, 2025
- ↑ “Proposed 2400 (3x800) MW Coal Based Ultra Super Critical Thermal Power Project by M/sAdani Power Limited, located at Sirmatpur & adjacent villages in Tehsil/block Pirpainti, District Bhagalpur, Bihar – Prescribing of Terms of Reference – regarding,” Ministry of Environment, Forest and Climate Change, October 27, 2025
- ↑ “Proposed 2400 (3x800) MW Coal Based Ultra Super Critical Thermal Power Project by M/s Adani Power Limited, located at Villages Simatpur, Mariakol G.P., Mundwa urf Tundwa, Sundarpur, Mayanagar, Pirpainti and Raipur in Tehsil/block Pirpainti, District, Bhagalpur, Bihar – Environment Clearance – regarding,” Ministry of Environment, Forest and Climate Change, April 15, 2026
- ↑ “Broad Status Report of Under Construction Thermal Power Projects (May’ 2026),” Central Electricity Authority, May 2026
- ↑ “BROAD STATUS REPORT OF UNDER CONSTRUCTION THERMAL POWER PROJECTS (September’ 2026),” Central Electricity Authority, September 2026
- ↑ “Minutes of AGENDA FOR 50TH MEETING OF THE EXPERT APPRAISAL COMMITTEE ( EAC) (THERMAL POWER PROJECTS) TO BE HELD ON 07TH SEPTEMBER, 2026…,” Ministry of Environment, Forest and Climate Change, September 18, 2026
- ↑ “Expansion of Pirpainti Thermal Power Plant from 2400 (3x800) MW (Phase I) to 4800 MW by adding 2400 (3x800) MW Ultra Super Critical TPP under Phase II in the Existing Area by M/s. Adani Power Limited located at Villages Simatpur, Mariakol G.P., Mundwa urf Tundwa, Sundarpur, Mayanagar, Pirpainti and Raipur in Tehsil/block Pirpainti, District, Bhagalpur, Bihar – Prescribing of Terms of Reference-regarding,” Ministry of Environment, Forest and Climate Change, September 29, 2026
- ↑ "MOU signed for power project in Bhagalpur" Bihar Days, accessed December 27, 2011.
- ↑ "Adani Power receives LoI to develop and operate 2,400 MW greenfield thermal power plant in Bihar". Adani Power. August 7, 2025. Retrieved June 2026.
{{cite web}}: Check date values in:|access-date=(help) - ↑ "Case No. 36/2025: Order on adoption of tariff for procurement from Pirpainti Thermal Power Station" (PDF). Bihar Electricity Regulatory Commission. August 27, 2025. Retrieved June 2026.
{{cite web}}: Check date values in:|access-date=(help) - ↑ “Adani power pushes Adivasis out,” People’s Archive of Rural India, October 26, 2026
- ↑ “Two Adivasi hamlets resist eviction without compensation for Adani's Bihar power plant,” News Laundry, November 10, 2026
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.
