EVM-II power station

From Global Energy Monitor
Part of the
Global Oil and Gas Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related categories:

EVM-II power station (Planta termoeléctrica EVM II) is an operating power station of at least 850-megawatts (MW) in Axapusco, México, Mexico.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
EVM-II power station Axapusco, México, Mexico 19.74635, -98.674624 (exact)[1]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1: 19.74635, -98.674624

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year Retired year
Unit 1 operating[2] fossil gas - natural gas[3][2] 850[2] combined cycle[2] 2021[4]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Valia Energía [100%] Actis LLP

Background

The project was initially registered in 2012.[5]

$740 million in financing was agreed upon for EVM II in October 2018.[6] The project is "part of a broader energy modernization and expansion program being undertaken by Mexico’s state utility, CFE."[7] It is the located near EVM Energia's first project, EVM I power plant.[8]

EVM II began operating in January 2021.[9]

Articles and Resources

References

  1. https://goo.gl/maps/Xko5Pq3YTemz4oxX6. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 2.3 https://web.archive.org/web/20240125093914/https://www.evmenergia.com/evmii/. Archived from the original on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  3. https://web.archive.org/web/20240125142428/https://miranda-partners.com/newswire/valia-energia-completes-acquisition-of-evm-energia-evm/. Archived from the original on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  4. "EVM Energía - Nuestra planta EVM II ha superado la fase de construcción, las pruebas de puesta en servicio, de código de red y de validación de acuerdo a los procedimientos del Cenace por lo que nos encontramos ya en operación comercial a partir del 1o de enero de 2021". Facebook. 2021-01-05. Retrieved 2023-11-28. {{cite web}}: Text "Facebook" ignored (help)
  5. DISEÑO, CONSTRUCCIÓN, EQUIPAMIENTO E INSTALACIÓN DEL CICLO COMBINADO VALLE DE MÉXICO II, EN EL ESTADO DE MÉXICO., Proyecto México website, accessed Dec 2, 2019
  6. Anja Karl. "Financing agreed for EVM-II plant in Mexico - Gas To Power Journal". Retrieved 2021-06-23.
  7. Ambrogio Visconti, EVM Tenedora Completes $740 Million Financing of 850 MW Power Plant, Global Legal Chronicle, Oct 12, 2018
  8. 850 MW gas-fired power project in Mexico reaches financial close, IPP Journal, Dec 2, 2018
  9. "Generando energía más confiable y económica para México - Proyectos 7HA de GE en la región - Energía Valle de México - EVM II". GE Gas Power. Retrieved 2022-12-09.{{cite web}}: CS1 maint: url-status (link)