TerraSpark WV Energy Campus power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

TerraSpark WV Energy Campus power station is an announced power station in Mount Storm, Grant, West Virginia, United States.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
TerraSpark WV Energy Campus power station Mount Storm, Grant, West Virginia, United States 39.176526, -79.29212 (approximate)[1]
Loading map...

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Emergency/Backup
Unit 1 Announced[1] coal: unknown[1] 400[2] supercritical[2] 2029 (planned)[3] False
Unit 2 Announced[1] coal: unknown[1] 400[2] supercritical[2] – False
Unit 3 Announced[1] coal: unknown[1] 400[2] supercritical[2] – False
Unit 4 Announced[1] coal: unknown[1] 400[2] supercritical[2] – False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 TerraPurus Inc [100%][4] TerraPurus Inc [100.0%]
Unit 2 TerraPurus Inc [100%][4] TerraPurus Inc [100.0%]
Unit 3 TerraPurus Inc [100%][4] TerraPurus Inc [100.0%]
Unit 4 TerraPurus Inc [100%][4] TerraPurus Inc [100.0%]

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

In June 2026, the U.S. Department of Energy (DOE) allocated US$18.5 million in funding for a proposed 1,600 MW coal-fired power station in West Virginia. Under the DOE’s “Restoring Reliability: Coal Recommissioning and Modernization” program, TerraPurus Inc. — doing business as TerraSpark — would undertake scoping and design studies for the proposed “TerraSpark WV Energy Campus” coal plant and Carbon Capture Utilization and Storage system.[5][6] The TerraSpark Energy Campus was reportedly expected to be built near the existing Mount Storm power station in Grant County, and would include a “Coal Innovation & Training Center” run by West Virginia University.[7]

Also in June 2026, energy technology company Babcock & Wilcox (B&W) announced they were collaborating with TerraSpark on the proposed power station. B&W was expected to design and supply four 400 MW supercritical boilers and emissions control equipment for the power plant, while Babcock & Wilcox Construction Co. was expected to construct the facility.[8] Mantel Capture, a startup reportedly backed by Shell, Eni, and BP, was slated to provide carbon capture technology.[9]

As of June 2026, a website for TerraSpark indicated that scoping and engineering work was slated to begin in 2026, and “initial online capacity” was expected in 2029.[10]

Financing

In June 2026, the U.S. Department of Energy listed US$18.5 million in DOE funding, US$21.4625 million in non-DOE funding, and US$39.9625 million in total value for the award package.[11] This funding related to scoping and design efforts; no full construction financial close, full project cost, construction debt, equity investor, final EPC contract, or lender group had been identified as of June 2026.

Articles and Resources

References

  1. ↑ 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 https://carbonherald.com/terraspark-secures-18-5m-doe-funding-for-carbon-capture-enabled-power-project/. {{cite web}}: Missing or empty |title= (help)
  2. ↑ 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 https://www.babcock.com/home/about/corporate/news/babcock-and-wilcox-to-support-terraspark-s-development-efforts-for-16-gw-coal-fired-power-plant-project-in-west-virginia-. {{cite web}}: Missing or empty |title= (help)
  3. ↑ https://terraspark.us/faq. {{cite web}}: Missing or empty |title= (help)
  4. ↑ 4.0 4.1 4.2 4.3 https://www.energy.gov/hgeo/project-selections-broad-agency-announcement-de-foa-0003605-restoring-reliability-coal-0. {{cite web}}: Missing or empty |title= (help)
  5. ↑ “Project Selections for Broad Agency Announcement DE-FOA-0003605, Restoring Reliability: Coal Recommissioning and Modernization (Topic 1),” U.S. Department of Energy, archived June 8, 2026
  6. ↑ “Energy Department to Invest $350 Million to Build, Modernize, and Restart Coal Plants,” U.S. Department of Energy, June 4, 2026
  7. ↑ “TerraSpark Secures $18.5M DOE Funding For Carbon Capture-Enabled Power Project,” Carbon Herald, June 8, 2026
  8. ↑ “Babcock & Wilcox to Support TerraSpark’s Development Efforts for 1.6 GW Coal-fired Power Plant Project in West Virginia,” Babcock & Wilcox, June 8, 2026
  9. ↑ “A New Coal Plant in the U.S.? Once Unthinkable, Now a Strong Maybe,” Power, June 16, 2026
  10. ↑ “Frequently Asked Questions,” TerraSpark, archived June 5, 2026
  11. ↑ "Project Selections for Broad Agency Announcement DE-FOA-0003605, Restoring Reliability: Coal Recommissioning and Modernization (Topic 1)". U.S. Department of Energy. June 2026. Retrieved June 2026. {{cite web}}: Check date values in: |access-date= (help)CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.