Vallourec Jeceaba steel plant (Usina siderúrgica de Jeceaba), also known as VSB (Vallourec & Sumitomo Tubos do Brasil), is a steel plant in Jeceaba, Minas Gerais, Brazil that operates electric arc furnace (EAF) and blast furnace (BF) technology.
Location
The map below shows the exact location of the plant in Jeceaba, Minas Gerais, Brazil:
Location: Distrito Industrial, S/N, 35.498-000 - Jeceaba, Minas Gerais, Brazil
Coordinates (WGS 84 ): -20.582683, -43.971555 (exact)
Background
Vallourec Jeceaba steel plant, also commonly known as Vallourec & Sumitomo Tubos do Brasil (VSB), is a Brazilian steel company belonging to the joint venture formed by the French group Vallourec and the Japanese Nippon Steel & Sumitomo Metal Corporation (NSSMC).[ 1] The plant specializes in producing seamless steel pipes for the oil and gas industry.[ 2]
Located in the municipality of Jeceaba, 100 km from Belo Horizonte in the Brazilian state of Minas Gerais, the R$3.2 billion, 2.5 million m² steel complex was announced in 2007 and inaugurated on September 1, 2011 by Brazilian President Dilma Rousseff.[ 3] [ 4]
The Jeceaba plant is equipped with a Tenova electric arc furnace[ 5] and has the capacity to produce 1 million tons of crude steel annually.[ 3] The plant's seamless pipe production capacity is listed at 600,000 tpa.[ 6]
In 2018, plant owner Vallourec moved its blast furnace operations from Belo Horizonte to Jeceaba, giving the Jeceaba plant the additional capacity to produce up to 300,000 tpa of pig iron.[ 7] Other facilities at the plant include a continuous caster, ladle furnace and seamless tube mill supplied by Germany's SMS Group GmbH.[ 8]
Ownership Tree
This ownership tree is part of the Global Energy Ownership Tracker , a project of Global Energy Monitor.
Plant Details
Table 1: General Plant Details
Table 2: Ownership and Parent Company Information
Parent company
Parent company PermID
Parent GEM entity ID
Owner
Owner company PermID
Owner GEM entity ID
Vallourec SA [100.0%]
4295867374 [100.0%]
E100001010324 [100.0%]
Vallourec Soluções Tubulares do Brasil SA [100%][ 9]
5001083353
E100000130951 [100%]
Table 3: Process and Products
Table 4: Plant-level Crude Steel Production Capacities (thousand tonnes per annum)
Table 5: Plant-level Crude Iron Production Capacities (thousand tonnes per annum)
1 Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Capacity operating status1
Blast furnace capacity
Nominal iron capacity (total)
cancelled
500[ 20]
500[ 20]
operating
350[ 21]
350[ 21]
Table 6: Upstream Products Production Capacities (thousand tonnes per annum)
Table 7: Actual Plant-level Crude Steel Production by Year (thousand tonnes per annum)
Table 8: Actual Plant-level Crude Iron Production by Year (thousand tonnes per annum)
Unit Details
Table 9: Blast Furnace Details
Table 10: Electric Arc Furnace Details
Table 11: Electric Arc Furnace Feedstock Details
Unit name
Scrap-based
% scrap
% pig iron (unknown if basic/merchant or granulated)
unknown EAF (1)
yes[ 10] [ 42] [ 15]
63.00[ 15] [ 19]
37.00[ 15] [ 19]
Articles and Resources
Additional data
To access additional data, including an interactive map of steel plants, a downloadable dataset, and summary data, please visit the Global Iron and Steel Tracker on the Global Energy Monitor website.
References
↑ "VSB anuncia reestruturação com reflexos diretos na usina de Jeceaba" . Câmara Municipal de Congonhas . March 27, 2018.{{cite web }}: CS1 maint: url-status (link )
↑ "Our units: Vallourec Soluções Tubulares do Brasil" . Vallourec . Retrieved 2022-02-09 .{{cite web }}: CS1 maint: url-status (link )
↑ 3.0 3.1 "Vallourec investe R$ 3,2 bilhões em Jeceaba" . O Tempo Economia . April 24, 2007.
↑ "Inauguração de complexo siderúrgico reúne autoridades em Minas" . Assembleia de Minas . September 1, 2011.{{cite web }}: CS1 maint: url-status (link )
↑ "2022 AIST Electric Arc Furnace Roundup" . AIST (Association for Iron & Steel Technology) . Retrieved 2020-09-14 .{{cite web }}: CS1 maint: url-status (link )
↑ "Enhancement of Strategic Partnership with Vallourec" (PDF) . Nippon Steel & Sumitomo Metal . February 1, 2016.{{cite web }}: CS1 maint: url-status (link )
↑ "Alto-forno da VSB já está funcionando" . Câmara Municipal de Congonhas . March 26, 2018.{{cite web }}: CS1 maint: url-status (link )
↑ "Vallourec & Sumitomo Tubos do Brasil (VSB)" . SMS group GmbH . Retrieved 2020-07-30 .{{cite web }}: CS1 maint: url-status (link )
↑ 9.0 9.1 9.2 9.3 9.4 https://web.archive.org/web/20211027104504/https://www.vallourec.com/en/brazil/about-us . Archived from the original on 2021-10-27.
↑ 10.00 10.01 10.02 10.03 10.04 10.05 10.06 10.07 10.08 10.09 "EAF Study Tour Brazil 2014" (PDF) . AIST . 2014. Archived from the original (PDF) on 2022-03-18.
↑ https://www.vallourec.com/en/Components/News/News_BR/2021/2021092515-10years-JECEABA .
↑ https://exame.com/negocios/vallourec-encerra-producao-de-aco-em-belo-horizonte/ .
↑ "Vallourec deve transferir produção de ferro-gusa e aço de BH para Jeceaba" . G1-Minas Gerais . 2016-02-02. Archived from the original on 2022-02-05.
↑ https://web.archive.org/web/20220108143418/https://diariodocomercio.com.br/economia/vallourec-investira-r-220-milhoes/ . Archived from the original on 2022-01-08.
↑ 15.0 15.1 15.2 15.3 15.4 15.5 15.6 "2023 Universal Registration Document" (PDF) . Vallourec . 2024-03-08. Archived from the original (PDF) on 2025-03-11.
↑ "Issued Certificates and Ongoing Audits" . www.responsiblesteel.org . Archived from the original on 2025-03-11. Retrieved 2024-11-13 .
↑ 17.0 17.1 17.2 17.3 17.4 17.5 Almeida, Eduardo Magalhães; Oliveira, Thiago André de; Barreto, Antônio Francisco Martins; Chesseret, Laurent (2013). "PROCESSO DE DESFOSFORAÇÃO NO CONSTEEL ® DA VALLOUREC SUMITOMO TUBOS DO BRASIL" . ABM Proceedings of the Seminar on Steelmaking, Casting and Non-Ferrous Metallurgy . Archived from the original on 2025-03-14. {{cite web }}: CS1 maint: multiple names: authors list (link )
↑ 18.0 18.1 18.2 18.3 "AçoBrasil - Uma viagem pela indústria do aço" (PDF) . Instituto Aço Brasil . 2013-11-30. Archived from the original (PDF) on 2022-01-21.
↑ 19.0 19.1 19.2 19.3 19.4 "Controle do Nível de Nitrogênio no Forno Elétrico a Arco com Tecnologia Consteel® da Vallourec & Sumitomo Tubos do Brasil" . ABM Proceedings . 2013. Archived from the original on 2025-09-05.
↑ 20.0 20.1 20.2 https://web.archive.org/web/20220318151821/https://ibram.org.br/noticia/alto-forno-em-jeceaba/ . Archived from the original on 2022-03-18.
↑ 21.0 21.1 21.2 21.3 21.4 "Brazil Steel Databook - Anuário Estatístico 2023" (PDF) . Instituto Aço Brasil . 2023-07-31. Archived from the original (PDF) on 2023-08-10.
↑ 22.0 22.1 22.2 22.3 (PDF) https://www.acobrasil.org.br/site/wp-content/uploads/2024/06/Mini_anuario_2024_AcoBrasil.pdf .
↑ 23.0 23.1 "Pocket Yearbook - A Siderurgia em Números 2020" (PDF) . Instituto Aço Brasil . 2020-04-30. Archived from the original (PDF) on 2021-12-30.
↑ 24.0 24.1 "Pocket Yearbook - A Siderurgia em Números 2021" (PDF) . Instituto Aço Brasil . 2021-06-30. Archived from the original (PDF) on 2022-01-20.
↑ 25.0 25.1 "Pocket Yearbook - A Siderurgia em Números 2022" (PDF) . Instituto Aço Brasil . 2022-06-30. Archived from the original (PDF) on 2022-06-25.
↑ 26.0 26.1 "Pocket Yearbook - Indústria do Aço em Números 2023" (PDF) . Instituto Aço Brasil . 2023-06-30. Archived from the original (PDF) on 2024-01-19.
↑ 27.0 27.1 27.2 27.3 (PDF) https://www.acobrasil.org.br/site/wp-content/uploads/2025/08/AcoBrasil_Anuario_2025-1.pdf .
↑ 28.0 28.1 28.2 28.3 "Brazil Steel Databook - Anuário Estatístico 2021" (PDF) . Instituto Aço Brasil . 2021-07-31. Archived from the original (PDF) on 2022-01-20.
↑ 29.0 29.1 "Brazil Steel Databook - Anuário Estatístico 2022" (PDF) . Instituto Aço Brasil . 2022-07-31. Archived from the original (PDF) on 2022-07-22.
↑ 30.0 30.1 (PDF) https://www.acobrasil.org.br/site/wp-content/uploads/2024/07/Anuario_Completo_2024.pdf .
↑ 31.0 31.1 31.2 https://web.archive.org/web/20220318151821/https://ibram.org.br/noticia/alto-forno-em-jeceaba/ . Archived from the original on 2022-03-18.
↑ 32.0 32.1 32.2 32.3 32.4 32.5 32.6 https://web.archive.org/web/20220319014121/https://abmproceedings.com.br/ptbr/article/o-inicio-de-operacao-do-alto-forno-2-da-vsb . Archived from the original on 2022-03-19.
↑ 33.0 33.1 33.2 https://web.archive.org/web/20220522173014/https://www.vallourec.com/en/investors/financial-results/registration-documents-archives . Archived from the original on 2022-05-22.
↑ 34.0 34.1 34.2 34.3 https://abmproceedings.com.br/en/article/processo-de-desfosforao-no-consteelr-da-vallourec-sumitomo-tubos-do-brasil .
↑ 35.0 35.1 (PDF) https://web.archive.org/web/20220929093913/https://www.paulwurth.com/wp-content/uploads/2020/08/Brochure-Refractory-and-Engineering-Hot-Blast-Stoves-en.pdf . Archived from the original (PDF) on 2022-09-29.
↑ 36.0 36.1 https://web.archive.org/web/20221203223426/https://www.paulwurth.com/en/technology/blast-furnace-ironmaking/modern-blast-furnace-design/ . Archived from the original on 2022-12-03.
↑ 37.0 37.1 https://web.archive.org/web/20220613081439/https://www.ge.com/digital/blog/vallourec-optimizes-energy-consumption-data-science . Archived from the original on 2022-06-13.
↑ 38.0 38.1 https://web.archive.org/web/20220320120702/https://www.vallourec.com/en/all-news/group-brazil-vallourec-florestal . Archived from the original on 2022-03-20.
↑ 39.0 39.1 https://imis.aist.org/store/detail.aspx?id=PR-RU2022-1 .
↑ 40.0 40.1 https://web.archive.org/web/20220119215734/https://www.congonhas.mg.leg.br/institucional/noticias/alto-forno-da-vsb-ja-esta-funcionando . Archived from the original on 2022-01-19.
↑ (PDF) https://web.archive.org/web/20240518214507/https://www.vallourec.com/app/uploads/2023/09/2022-Vallourec-Registration-Document_EN.pdf . Archived from the original (PDF) on 2024-05-18.
↑ 42.0 42.1 https://imis.aist.org/store/detail.aspx?id=PR-RU2024-2 .
Resources