Xinwen Ili No.1 mine (新汶矿业集团(伊犁)能源开发有限责任公司一矿) with an annual production capacity of 10 million tonnes(Mt), is located within the territory of Ili, Xinjiang. It is the first ten-million-ton scale coal mine approved by the National Development and Reform Commission (NDRC) in Xinjiang.[1]
Location
The undated satellite photo below shows the coal mine located in Tuanjie Road, Qiongbolaxiang, Qapqal,Ili,Xinjiang
Coal Mine Background
In August 2009, the National Development and Reform Commission (NDRC) has ratified the construction of Ili No.1 Coal Mine, approving 10 Mt/year of annual production capacity.[2]
According to the 2018 report of Xinwen Mine Industry Group, the construction work of Ili No.1 mine has been largely completed. It is projected to begin its operation in 2019.[3]
The coal mine has carried out a joint trial operation of the production system in April 2020, and obtained a safety production license on December 8, 2020.[4]
Project Details
- Sponsor: Xinwen Mine Industry Group Ili Energy Development Co.
- Parent Company: Shandong Energy Group
- Location: Tuanjie Road, Qiongbolaxiang, Qapqal,Ili,Xinjiang
- GPS Coordinates: 43.546231,80.961116
- Status: Operating
- Annual Production Capacity: 10 Mt/year
- Total Resources: 4,800Mt[5]
- Minable Reserves: 1,839.05Mt [6]
- Coal Type: Bituminous(non-caking coal, long flame coal)
- Mine Size: 118.5k㎡[7]
- Mine Type: Underground
- Start Year: 2020
- Source of Financing:
Articles and resources
References
- ↑ "新汶矿业集团抓住历史机遇加快产业向西转移"和讯新闻,2011/06/21
- ↑ "新疆伊犁一号煤矿项目通过核准"发改委, 2009/11/26
- ↑ "新汶矿业集团2018年度跟踪评级报告." 大公国际资信评估有限公司, 2018/08/10
- ↑ "伊犁一矿顺利取得安全生产许可证 设计年产能1000万吨",中国能源网,2020-12-14
- ↑ "全疆首座千万吨级煤矿矿井在伊犁开工" 人民网, 2010/01/04
- ↑ "新汶矿业集团2018年度跟踪评级报告" 大公国际资信评估有限公司, 2018/08/10
- ↑ "全疆首座千万吨级煤矿矿井在伊犁开工" 人民网, 2010/01/04