Yancheng Lianxin Iron and Steel Co Ltd
From Global Energy Monitor
This article is part of the Global Steel Plant Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Yancheng Lianxin Iron and Steel Co Ltd (盐城市联鑫钢铁有限公司), also known as Jiangsu Yancheng Lianxin Iron and Steel Company, is a blast furnace-basic oxygen furnace (BF-BOF) and electric arc furnace (EAF) steel plant operating in Yancheng, Jiangsu, China.
Location
The map below shows the exact location of the plant in Yancheng, Jiangsu, China:
- Location: Lingang Industrial Zone, Dafeng Port Economic Zone, Dafeng District, Yancheng City, Jiangsu Province
- Coordinates (WGS 84): 33.211332, 120.774892 (exact)
Background
According to the company's 2021 EIA report, it is planned to upgrade the existing No. 3 blast furnace from 1080m3 to 1200m3.[1][2]
Plant Details
Table 1: General Plant Details
Phase | Plant status | Announced date | Start date | Pre-retirement announcement date | Workforce size | Power source |
---|---|---|---|---|---|---|
Main plant | Operating[3] | – | 1958[4] | – | 3411[3] | Distributed Photovoltaic Power Generation[5] |
Closure | Operating pre-retirement[6] | – | –[6] | 2023-06-12[6] | – | Distributed Photovoltaic Power Generation[5] |
Expansion | Announced[6] | 2023-06-12[6] | 2024[6] | – | – | Distributed Photovoltaic Power Generation[5] |
Table 2: Ownership and Parent Company Information
Phase | Parent company | Parent company GEM ID | Owner | Owner company GEM ID |
---|---|---|---|---|
Main plant | Huachuang Jiangsu Investment Co Ltd [80.4%]; persons [19.6%] | E100000123261 [100%] | Yancheng Lianxin Iron and Steel Co., Ltd.[3] | E100000126645 |
Table 3: Process and Products
Phase | Steel product category | Steel products | Steel sector end users | ISO 14001 | ISO 50001 | Main production equipment | Detailed production equipment |
---|---|---|---|---|---|---|---|
Main plant | finished rolled[7] | hot rolled ribbed rebar, special steel[7] | building and infrastructure; tools and machinery[8] | 2022[8] | 2021[8] | BF, BOF, EAF[9] | 2 BOF (2x120-tonne); 1 EAF(1x70-tonne)[9] |
Closure | finished rolled[7] | hot rolled ribbed rebar, special steel[7] | building and infrastructure; tools and machinery[8] | – | – | EAF[6] | 1 EAF (70-tonne)[6] |
Expansion | finished rolled[7] | hot rolled ribbed rebar, special steel | building and infrastructure; tools and machinery[8] | – | – | EAF[6] | 1 EAF (100-tonne)[6] |
Table 4: Crude Steel Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Basic oxygen furnace steelmaking capacity | Electric arc furnace steelmaking capacity | Nominal crude steel capacity (total) |
---|---|---|---|---|
Main plant | operating | 2410 TTPA[10][10] | – | 2410 TTPA[10][10] |
Closure | operating pre-retirement | – | 790 TTPA[6] | 790 TTPA[6] |
Expansion | announced | – | 750 TTPA[6] | 750 TTPA[6] |
Table 5: Crude Iron Production Capacities (thousand tonnes per annum)
Phase | Capacity operating status* | Blast furnace capacity | Nominal iron capacity (total) |
---|---|---|---|
Main plant | operating | 3210 TTPA[11][11][12] | 3210 TTPA[11][11][12] |
Closure | operating pre-retirement | – | – |
Expansion | announced | – | – |
Table 6: Actual Crude Steel Production by Year (thousand tonnes per annum)
Year | BOF Production | Total (all routes) |
---|---|---|
2020 | – | – |
2021 | – | – |
2022 | 3000 TTPA[13] | 3000 TTPA[13] |
Blast Furnace Details
Table 7: Blast Furnace Details
Unit name | Status | Announced date | Construction date | Start date | Current size | Current capacity (ttpa) | Decarbonization technology | Most recent relining |
---|---|---|---|---|---|---|---|---|
#1 | operating[9] | unknown | unknown | 2012[12] | 1080 m³[9] | 1040[11] | unknown | unknown |
#2 | operating[9] | unknown | unknown | 2012[12] | 1080 m³[9] | 1040[11] | unknown | unknown |
#3 | operating[9] | unknown | unknown | 2013[12] | 1200 m³[9] | 1130[12] | unknown | unknown[12] |
Articles and Resources
Additional data
To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.
References
- ↑ 省生态环境厅关于盐城市联鑫钢铁有限公司3号高炉及钢产品升级项目环境影响报告书的批复,江苏省生态环境厅,January 26, 2021
- ↑ 关于盐城市联鑫钢铁有限公司3#高炉技改项目产能置换的公告,我的钢铁网,November 27, 2019
- ↑ 3.0 3.1 3.2 https://web.archive.org/web/20220111133314/https://www.qcc.com/firm/38003b035c71add15a33985ec8f94d34.html. Archived from the original on 11 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ https://web.archive.org/web/20191228164458/http://www.lianxinsteel.com:80/?p. Archived from the original on 28 December 2019.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 5.0 5.1 5.2 https://web.archive.org/web/20231127203401/https://baijiahao.baidu.com/s?id=1766306233373844266&wfr=spider&for=pc. Archived from the original on 27 November 2023.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 6.00 6.01 6.02 6.03 6.04 6.05 6.06 6.07 6.08 6.09 6.10 6.11 6.12 6.13 http://gxt.jiangsu.gov.cn/art/2023/6/12/art_6281_10920593.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 7.0 7.1 7.2 7.3 7.4 https://web.archive.org/web/20220120032709/http://www.lianxinsteel.com/?page_id. Archived from the original on 20 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 8.0 8.1 8.2 8.3 8.4 https://web.archive.org/web/20240119055443/http://cx.cnca.cn/CertECloud/result/skipResultList?certNumber=&orgName=%E7%9B%90%E5%9F%8E%E5%B8%82%E8%81%94%E9%91%AB%E9%92%A2%E9%93%81%E6%9C%89%E9%99%90%E5%85%AC%E5%8F%B8&fromIndex=true. Archived from the original on 19 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 9.0 9.1 9.2 9.3 9.4 9.5 9.6 9.7 https://web.archive.org/web/20220111133314/https://www.qcc.com/firm/38003b035c71add15a33985ec8f94d34.html. Archived from the original on 11 January 2022.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 10.0 10.1 10.2 10.3 (PDF) http://www.lianxinsteel.com/wp-content/uploads/2013/03/%E8%81%94%E9%91%AB%E9%92%A2%E9%93%813%E5%8F%B7%E9%AB%98%E7%82%89%E5%8F%8A%E9%92%A2%E4%BA%A7%E5%93%81%E5%8D%87%E7%BA%A7%E9%A1%B9%E7%9B%AE%E5%BE%81%E6%B1%82%E6%84%8F%E8%A7%81%E7%A8%BF.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 11.0 11.1 11.2 11.3 11.4 11.5 https://finance.sina.cn/futuremarket/gypzx/2019-11-27/detail-iihnzhfz2059687.d.html https://www.qcc.com/firm/13NB3T7.shtml;http://www.lianxinsteel.com/wp-content/uploads/2013/03/%E8%81%94%E9%91%AB%E9%92%A2%E9%93%813%E5%8F%B7%E9%AB%98%E7%82%89%E5%8F%8A%E9%92%A2%E4%BA%A7%E5%93%81%E5%8D%87%E7%BA%A7%E9%A1%B9%E7%9B%AE%E5%BE%81%E6%B1%82%E6%84%8F%E8%A7%81%E7%A8%BF.pdf; https://finance.sina.cn/futuremarket/gypzx/2019-11-27/detail-iihnzhfz2059687.d.html.
{{cite web}}
: Check|url=
value (help); Missing or empty|title=
(help) - ↑ 12.0 12.1 12.2 12.3 12.4 12.5 12.6 https://max.book118.com/html/2021/0101/8117112060003033.shtm.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 13.0 13.1 https://web.archive.org/web/20240111061042/http://www.jljob88.com/campus/index.php?m=job&a=company_detail&uid=cm1351817174922. Archived from the original on 11 January 2024.
{{cite web}}
: Missing or empty|title=
(help)