Zheneng Changxing power station (浙能长兴发电厂, 浙能长兴电厂迁建项目) is an operating power station of at least 1200-megawatts (MW) in Heping Town, Changxing, Huzhou, Zhejiang, China with multiple units, some of which are not currently operating. It is also known as 浙能长兴电厂二期 (Phase II Unit 1&2), 浙能长兴电厂三期 (Phase III Unit 1&2).

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Zheneng Changxing power station Heping Town, Changxing, Huzhou, Zhejiang, China 30.991944, 119.929722 (exact)
Loading map...

Unit-level coordinates (WGS 84):

  • Phase II Unit 1, Phase II Unit 2, Phase III Unit 1, Phase III Unit 2: 30.991944, 119.929722
  • Replace Unit 1, Replace Unit 2: 30.845049, 119.878251

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year Emergency/Backup
Phase II Unit 1 Operating coal: bituminous[1] 300 subcritical yes 2003 False
Phase II Unit 2 Operating coal: bituminous[1] 300 subcritical yes 2003 False
Phase III Unit 1 Operating coal: bituminous[1] 300 subcritical yes 2006 False
Phase III Unit 2 Operating coal: bituminous[1] 300 subcritical yes 2006 False
Replace Unit 1 Permitted[2] coal: bituminous[1][2] 1000[2] ultra-supercritical[2] yes[2] 2028 (planned)[3] False
Replace Unit 2 Permitted[2] coal: bituminous[1][2] 1000[2] ultra-supercritical[2] yes[2] 2028 (planned)[3] False

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase II Unit 1 Zhejiang Zheneng Changxing Power Generation Co Ltd [100%] Zhejiang Zheneng Electric Power Co Ltd [95.0%]; Changxing City Construction Investment Group Co Ltd [3.5%]; Changxing Zhejiang Financial Holding Group Co Ltd [1.3%]; unknown [0.2%]
Phase II Unit 2 Zhejiang Zheneng Changxing Power Generation Co Ltd [100%] Zhejiang Zheneng Electric Power Co Ltd [95.0%]; Changxing City Construction Investment Group Co Ltd [3.5%]; Changxing Zhejiang Financial Holding Group Co Ltd [1.3%]; unknown [0.2%]
Phase III Unit 1 Zhejiang Zheneng Changxing Power Generation Co Ltd [100%] Zhejiang Zheneng Electric Power Co Ltd [95.0%]; Changxing City Construction Investment Group Co Ltd [3.5%]; Changxing Zhejiang Financial Holding Group Co Ltd [1.3%]; unknown [0.2%]
Phase III Unit 2 Zhejiang Zheneng Changxing Power Generation Co Ltd [100%] Zhejiang Zheneng Electric Power Co Ltd [95.0%]; Changxing City Construction Investment Group Co Ltd [3.5%]; Changxing Zhejiang Financial Holding Group Co Ltd [1.3%]; unknown [0.2%]
Replace Unit 1 Zhejiang Zheneng Changxing Power Generation Co Ltd [100%] Zhejiang Zheneng Electric Power Co Ltd [95.0%]; Changxing City Construction Investment Group Co Ltd [3.5%]; Changxing Zhejiang Financial Holding Group Co Ltd [1.3%]; unknown [0.2%]
Replace Unit 2 Zhejiang Zheneng Changxing Power Generation Co Ltd [100%] Zhejiang Zheneng Electric Power Co Ltd [95.0%]; Changxing City Construction Investment Group Co Ltd [3.5%]; Changxing Zhejiang Financial Holding Group Co Ltd [1.3%]; unknown [0.2%]

Project-level coal details

  • Coal source(s): domestic/imported
  • Permit(s): 浙发改项字〔2025〕410号[3]

Ownership Tree

This ownership tree is part of the Global Energy Ownership Tracker, a project of Global Energy Monitor.

Background

Zheneng Changxing power station is a 4 x 300 MW coal plant commissioned in 2003-2006.[4][5][6] It is located next to the retired units of Huaneng Changxing power station.

The replacement units (Replace Unit 1 and Replace Unit 2) saw feasibility study and consulting services tendered in May 2025[7][8]. The feasibility study contract was awarded in July 2025[9]. In September 2025, land acquisition and demolition began[10]. In December 2025, a main machinery tender was issued[11]. In February 2026, main machinery and EPC general contracting contracts were awarded[12][13]. The project was approved, and construction is scheduled to start in December 2026[14]. In April 2026, the EPC contract was awarded[15].

Articles and Resources

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 https://www.gem.wiki/Coal_source_methodology_for_the_Global_Coal_Plant_Tracker. {{cite web}}: Missing or empty |title= (help)
  2. 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 https://mp.weixin.qq.com/s/_L8D_EunwidkELaxjCBWYA. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 3.2 https://mp.weixin.qq.com/s/YrbZf5UTt7wdqjTf5uN8yA. {{cite web}}: Missing or empty |title= (help)
  4. "Coal-Fired Plants in China - Zhejiang," Power Plants Around the World, accessed September 2016
  5. "List of major power stations in Zhejiang," Wikipedia, accessed September 2016
  6. 浙江浙能长兴发电有限公司 湖州市电力行业协会 10-24-2016
  7. "浙能长兴电厂迁建项目配套码头及支线航道工程可研采购". 中国招标网. 2025-05-09. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  8. "浙能长兴电厂迁建项目可研及接入系统咨询服务招标". 中国招标网. 2025-05-29. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  9. "浙江院中标浙能长兴电厂2×1000MW迁建项目可研及接入系统咨询". 北极星电力网. 2025-07-02. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  10. "浙能长兴电厂迁建项目新址启动征拆". 微信公众平台. 2025-12-04. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  11. "浙能长兴电厂2×1000MW迁建项目三大主机招标". 微信公众平台. 2026-01-06. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  12. "浙能长兴电厂迁建项目三大主机中标公示". 北极星电力网. 2026-02-02. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  13. "浙能长兴电厂迁建项目EPC总承包招标公告". 微信公众平台. 2026-03-09. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  14. "浙能长兴电厂迁建项目EPC中标候选人公示". 微信公众平台. 2026-03-25. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)
  15. "中国能建浙江院联合体中标浙能长兴电厂迁建EPC". 微信公众平台. 2026-06-30. Retrieved 2026-07-29.{{cite web}}: CS1 maint: url-status (link)