Hermanowice-Jarosław Gas Pipeline is a proposed natural gas pipeline in Poland.[1]
Location
The pipeline would run from Hermanowice, Poland, to Jarosław, Poland.
Pipeline Details
- Proposed Capacity:
- Length: 39 km / 24.2 miles[3]
- Diameter: 700 mm[2]
- Cost: €39 million (estimated)[4]
- Status: Proposed[5]
- Start Year: 2029[1]
- PCI Number: 6.2.2[6]
Background
The pipeline is listed as a Project of Common Interest by the European Commission, making it eligible for public funding. It is part of a proposed network in Eastern Europe meant to improve connectivity between Poland, Hungary, and Slovakia. The other pipelines in the network include: Rozwadów Koskowola Wronów Pipeline, Jarosaw Rozwadów Pipeline, Rembelszczyzna Wronow Pipeline, Hermanowice Strachocina Pipeline, Tworóg Tworze Pipeline, Pogórska Wola Tworze Pipeline, Strachocina Pogórska Wola Pipeline, Gustorzyn Wronów Pipeline.[1]
In 2012, the European Network of Transmission System Operators for Gas (ENTSOG) Gas Regional Investment Plan BEMIP listed the "probable date of commissioning and the main milestones" for the Hermanowice-Jarosław pipeline as ending the permitting phase in 2015, reaching final investment decision in 2015 and commissioning in 2018.[4] However, the European Commission included the project among "new onshore pipelines and compressor stations in Eastern Poland" with a commissioning date of 2029.[1]
The project is included in Gaz System's Ten-Year Development Plan for 2026-2035.[5]
Articles and resources
References
- ↑ 1.0 1.1 1.2 1.3 North – South Gas Corridor in Eastern Poland, European Commission, November 2019
- ↑ 2.0 2.1 2.2 2.3 "Development Plan for satisfying current and future transmission demand for natural gas for 2014-2023" (PDF). Gaz-System. 2014. Retrieved August 26, 2021.
{{cite web}}: CS1 maint: url-status (link) - ↑ "Technical information on Projects of Common Interest" (PDF). Energy - European Commission. October 2014. Retrieved October 7, 2025.
{{cite web}}: CS1 maint: url-status (link) - ↑ 4.0 4.1 BEMIP Gas Regional Investment Plan 2012 - 2021 – Annex: Infrastructure Projects, ENTSOG, 2012
- ↑ 5.0 5.1 "KRAJOWY DZIESIĘCIOLETNI PLAN ROZWOJU SYSTEMU PRZESYŁOWEGO NA LATA 2026-2035" (PDF). Gaz System. March 2025. Retrieved October 7, 2025.
{{cite web}}: CS1 maint: url-status (link) - ↑ GAZ-SYSTEM (2019). "PROJEKTY O STATUSIE PCI" (PDF). Retrieved August 24, 2021.
{{cite web}}: CS1 maint: url-status (link)