VOC Port NCB-I Coal Terminal

From Global Energy Monitor

The VOC Port NCB-I Coal Terminal is an operating captive coal terminal at V.O. Chidambaranar Port in Thoothukudi, Tamil Nadu, India. The berth supplies the adjacent 1,000 MW NTPL Tuticorin power station.

Location

NCB-I is situated alongside the port's northern breakwater.

Loading map...

Background

NCB-I was constructed as a captive thermal-coal berth for NLC Tamil Nadu Power Limited (NTPL), a joint venture between NLC India Limited and Tamil Nadu's state power utility. Commercial operation of the berth began on October 1, 2014.[1]

North Cargo Berth I was originally developed with a design capacity of 6.3 million tonnes per annum (mtpa).[2] A subsequent port tender listed the berth's capacity as 12.2 mtpa.[3]

The berth is approximately 306 metres long and was designed for vessels of up to approximately 80,000 DWT. Coal unloaded at NCB-I is carried by a dedicated conveyor to the NTPL power station.[4]

Project Details

  • Operator: NLC Tamil Nadu Power Limited
  • Owners: NLC India Limited and Tamil Nadu state power utility
  • Location: V.O. Chidambaranar Port, Thoothukudi, Tamil Nadu, India
  • Coordinates: 8.760200, 78.207800 (exact)
  • Annual Coal Capacity: 12.2 mtpa
  • Status: Operating
  • Start Year: 2014
  • Type: Imports
  • Terminal Type: Captive
  • Primary user: NTPL Tuticorin power station
  • Coal source: Primarily domestic coastal coal

Articles and Resources

Sources

  1. ↑ (2024) Administration Report 2023–24 . V.O. Chidambaranar Port Authority. Report.
  2. ↑ (2013) Administration Report 2012–13 . V.O. Chidambaranar Port Trust. Report.
  3. ↑ "Link Conveyor from Coal Jetty-I, Coal Jetty-II and North Cargo Berth-I to Port Coal Yard" (PDF). V.O. Chidambaranar Port Authority. 2023. Retrieved 2026-09-18.
  4. ↑ Detailed Project Report for Conversion of Berth IX as Container Terminal . V.O. Chidambaranar Port Authority. Report.

Related GEM.wiki articles

External Articles